CoreTect_Industrial and Commercial Energy Storage-Household Energy Storage Operation and Maintenance SOP_V2.0

Energy Storage Asset Operation and Maintenance Management Manual

Chapter 0 New System Delivery Acceptance Procedure (FAT/SAT)

0.1 到货开箱检验(Arrival Inspection)

⚠ If transportation damage is found, take photos immediately and send a written claim notice to the supplier within 24 hours. If the time limit is exceeded, the customer will be deemed to have accepted that there is no damage.

0.2 Static detection before power-on (Pre-Energization)

It must be executed in a completely power-off state, and the executor is: L2 level engineer or above.

DC insulation resistance test: 1000V megger, positive pole to ground, negative pole to ground, requirement ≥2MΩ

AC insulation resistance test: 500V megger, L line to ground, N line to ground, requirement ≥1MΩ

Ground continuity test: Use a milliohmmeter to verify the cabinet shell ground resistance, requiring ≤0.1Ω

DC polarity check: Use a multimeter to confirm that the positive and negative poles of the battery are connected correctly, and be careful not to reverse the connection.

AC phase sequence confirmation: The phase sequence table confirms that the three-phase inverter L1/L2/L3 sequence is correct (if applicable)

Bolt torque spot check: randomly select 5 main circuit terminals to verify the torque (M8: 12N·m, M10: 25N·m)

0.3 First power-on function verification (Energization Test)

⚠ The first power-on must be supervised by a CoreTect L2 or above engineer on-site throughout the entire process. Agents are strictly prohibited from performing this alone.

0.4 72-hour trial operation (Burn-In Test)

Continuous operation for 72 hours, Level 1 cloud daily remote inspection data

Qualification standards: Single cell pressure difference ≤ 20mV, maximum temperature rise ≤ 10°C, no P1/P2 level alarm

After passing the test within 72 hours, a "SAT Acceptance Certificate" will be issued as the legal basis for the SLA contract to officially take effect.

If a fault occurs and is resolved within 72 hours, reset the timer and start timing again.

0.5 Customer handover (Handover Checklist)

Chapter 1 General Principles and Overview of Operation and Maintenance Management System

1.1 Operation and maintenance vision and service concept

CoreTect abandons the traditional "break-fix" model and is committed to building a "data-driven O&M" system: through standardized on-site operations and cloud data monitoring, preventive maintenance is fully implemented and gradually evolves to predictive maintenance as data is accumulated, maximizing the life cycle of energy storage assets and eliminating safety accidents.

1.2 Scope of application and service boundaries

Scope of jurisdiction (SLA coverage area): Industrial and commercial/residential energy storage system cabinets, BMS communication links, cloud gateways (4G DTU/ESP32) and temperature control security subsystems authorized by CoreTect to leave the factory and take over.

1.3 Core terms and definitions (Glossary)

1.4 Operation and maintenance organizational structure and work order flow

Chapter 2 Monthly/Quarterly Standard Inspection and Maintenance Procedures

2.1 Prerequisites for operation - PPE and tools

2.2 Safety isolation and electrical testing (LOTO SOP)

Switch the system to "standby" through CoreTect Cloud or local screen and confirm that the current shows 0A

Disconnect the external AC main circuit breaker of the energy storage cabinet, hang a warning sign saying "Someone is working, closing is prohibited" and lock it with a physical lock.

Disconnect the DC main circuit breaker of the high-voltage control box and also tag out and lock it.

Forced static discharge: wait 15 minutes to completely discharge the large DC-Link capacitor inside the PCS

High-voltage electricity test: Use the multimeter at DC 1000V to measure the voltage between the positive pole and the negative pole of the DC busbar and the positive pole and the ground.

⚠ Judgment criteria: Voltage <36V DC is considered safe before subsequent physical contact operations can be carried out. Contact is strictly prohibited if it does not meet the standards!

2.3 Monthly appearance inspection (once a month, L1 level or above)

2.4 Quarterly in-depth maintenance (once per quarter, L2 level and above)

2.4.1 Thermal imaging scan (executed in charged and fully loaded state)

2.4.2 Insulation test and torque retightening (performed after power off)

DC system insulation: 1000V megger, positive pole to ground, negative pole to ground. Requirements: ≥2MΩ safe; <1MΩ closing is strictly prohibited

AC system insulation: 500V megger, L/N line to ground. Requirements: ≥1MΩ

Torque retightening: For abnormal points in thermal imaging, use an insulated torque wrench to retighten (M6: 5N·m, M8: 12N·m, M12: 45N·m)

2.4.3 BMS data verification

2.5 CoreTect Cloud automated inspection mechanism

2:00 a.m. every day: The cloud automatically generates a daily health report with green/yellow/red markings, and pushes it to the customer and operation and maintenance center.

🟢 90-100 points (Excellent): normal maintenance cycle

🟡 70-89 points (Fair): sub-healthy, the system will push an early warning and come with a life extension maintenance quote.

🔴 <70 points (Critical): High-risk status, triggering manual intervention work order

2.6 Job ending and data closed loop

Count tools: Be careful to prevent short circuits caused by leftover metal tools. The number of items entering and leaving the tool bag must be consistent.

BMS data extraction: forced download of underlying operating log archives for the past 30 days

Restore power supply: remove the LOTO lock, close the circuit breaker, and issue a power-on command from the cloud

Wait for 15 minutes before evacuating if there is no alarm.

Work order closed loop: Upload inspection photos with time watermark on the mobile terminal, and customer electronic signature

Chapter 3 Core Component Replacement and On-site Repair Procedures

⚠ All operations must be performed by CoreTect certified engineers. Before any disassembly, the LOTO safety isolation procedures in Section 2.2 must be completed.

3.1 Golden principles for troubleshooting

Fatal warning: Reversing the order of disassembling and assembling the wiring harness will cause an instant short circuit in the collection line, burn the motherboard, and even cause arc burns!

Disassembly sequence (strictly follow)

Cut off weak current: First unplug all cell voltage/temperature sampling cables (white multi-core cables)

Disconnect communication: Unplug the RS485/CAN communication network cable and screen cable

Disconnect the main negative output: remove the black main negative wire connected to BMS P- (load terminal)

Disconnect the battery negative input: Finally remove the total negative input line connected to BMS B- (battery terminal)

Installation sequence (completely opposite to disassembly)

Connect the battery terminal: Connect the battery negative copper bar to the B- terminal of the new BMS, torque 12N·m, and draw the anti-loosening line

Connect to the output terminal: Connect the negative pole of the external output to the P- terminal of the BMS

Sampling line verification and connection: Use a multimeter to measure each pin of the cable in sequence, confirm that the voltage increases in steps of 3.2V/6.4V/9.6V and then insert it.

Restore communication: Plug back the 4G DTU network cable and temperature measurement NTC probe

Software burning and verification

Turn on the DC circuit breaker, power on, and connect the laptop via USB to RS485 cable

Load CoreTect's exclusive parameter package for this model of battery (overvoltage 3.65V, undervoltage 2.70V, etc.)

The cloud backend confirms that the device is back online, completes the trial run for 15 minutes, and submits the replacement SN code.

3.3 Procedure for replacing the entire inverter main board

Applicable scenarios: The resistance between IGBT D-S ≈ 0Ω; the inverter reports hardware protection (E006/F10) when it is powered on and cannot be reset.

⚠ Before replacement, photos must be taken to collect evidence (full view of the inside of the cabinet, close-up of IGBT, distribution box, seal status) as RCA legal evidence!

Execute LOTO and confirm that the DC BUS voltage is <36V

Unplug all communication cables and loosen the connecting cables between the driver board and power board.

Remove the radiator fixing screws, remove the old thermal grease, and clean the radiator aluminum base plate

Install the new motherboard and evenly apply thermal grease (thickness 0.1-0.2mm)

Tighten according to the specified torque (M6: 5N·m, M8: 12N·m)

Do not connect the load, only close the DC circuit breaker, and observe whether the bus voltage rises normally.

Import CoreTect standard parameter configuration file, especially verify the 60Hz frequency setting

Turn on the no-load inverter and measure the AC output with a multimeter: it should be 220V/60Hz sine wave

Gradually load to 50% rated power, and monitor the IGBT temperature rise (personnel must stay at all times for the first 30 minutes)

3.4 Single cell voltage difference equalization and replacement procedures

Applicable scenarios: Cloud alarm cell voltage difference (ΔV) >100mV, or the internal resistance of a certain string of cells is abnormal.

Battery replacement steps

Accurately locate backward battery cell numbers in the cloud

Use a professional suction cup to lift the battery core vertically upwards (314Ah cell is about 5.5kg). It is strictly prohibited to lift by the pole!

New batteries are put into the array, and a 1mm thick FR4 insulation board is inserted in the middle to prevent friction short circuit.

Connect the copper bar, and the torque is strictly set to 6N·m (M6 stud). After tightening, use a red marker to draw a "one-word anti-loosening line"

Deep equalization: CC-CV mode, 3.60V cut-off, 20A~50A current, charge until the current drops below 0.5A

Chapter 4 Extreme Scenarios and Disaster Emergency Plan (ERP)

4.1 Typhoon and severe flood disaster preparedness plan

4.1.1 48 hours before the typhoon makes landfall (triggered by PAGASA Signal No.2 and above)

Cloud action: Automatically issue a "forced full charge command" to the inverter to increase the SOC lower limit to 80%

On-site actions: Check whether the rainproof shutters of the outdoor cabinet are locked, and clean the drainage ditch within 2 meters around the cabinet.

4.1.2 When water is about to cover 10cm from the bottom of the cabinet - emergency fuse

⚠ Remotely forcibly shut down the inverter and BMS charging and discharging. Instruct customers to wear insulating boots and immediately pull down the DC main switch and AC main switch.

4.1.3 Restoring power supply after disaster (fatal red line)

⚠ Absolute prohibition: Customers are strictly prohibited from closing the switch and sending electricity by themselves after the water recedes! Warranty will be void if the machine explodes due to illegal startup!

The engineer came to the door with a 1000V megohmmeter. If there was water vapor inside, he used an industrial hot air blower to blow it dry.

Insulation resistance test: the positive and negative poles must be >2MΩ to ground. Power can be restored only after reaching the standard.

4.2 Battery thermal runaway emergency procedures (Thermal Runaway)

Trigger conditions: The unit temperature exceeds 75°C and continues to rise, or the cabinet makes a hissing pressure release sound and acrid white smoke.

Chapter 5 PCS (energy storage converter) operation and maintenance standards

5.1 PCS safety isolation and electrical inspection specifications

Turn off the AC grid circuit breaker, load circuit breaker, PV isolation switch and battery DC main gate in sequence

Forced to stand for ≥5 minutes (15 minutes for models above 100kW) to completely discharge the internal DC-Link large capacitor

Use a multimeter at DC 1000V range to measure BAT+ and BAT- to confirm that the internal residual voltage is <36V DC

5.2 PCS electrical connection and torque maintenance

5.3 PCS heat dissipation and dust-proof maintenance

External dust screen (monthly): Remove the air inlet dust screen, clean it with a high-pressure air gun (pressure <0.3MPa), dry it thoroughly and then reinstall it.

Cooling fan test (quarterly): The on-screen diagnostic menu forces the fan to run at 100%. If there is abnormal noise in the bearing, replace it.

Thermal conductive silicone grease inspection (annual): Check whether the silicone grease is dry, cracked and powdery, and reapply if there is any abnormality (thickness 0.1~0.2mm)

Chapter 6 Communication and Cloud Platform Operation and Maintenance Standards

6.1 Physical link layer check

Communication cable anti-interference: RS485 and CAN communication lines must use twisted pair shielded wires, and the shielding layer is grounded at one end at the inverter end.

Keep a distance of more than 15cm from AC and DC thick cables, and it is strictly prohibited to bundle them in parallel in the same cable trough.

Terminal matching resistor: If the bus distance exceeds 50 meters, a 120Ω terminal resistor must be connected in parallel at the end of the bus

6.2 Edge intelligent gateway operation and maintenance

Signal strength: RSSI>-85dBm, if it is lower than this value, the antenna must be moved to an unobstructed outdoor location

Watchdog test (quarterly): Unplug the 4G antenna to simulate a network disconnection, and observe whether the gateway can automatically restart and reconnect within 300 seconds.

6.3 Network security management

Default password modification: The factory default password (admin/admin) must be modified during the SAT stage, and a strong password of ≥12 digits must be set.

API key rotation: Third-party integration API keys such as Telegram Bot are rotated once a year

Operation log retention: All parameter modifications and remote control instructions are automatically recorded in the cloud and retained for ≥ 2 years

Chapter 7 Failure Response and RCA Investigation

7.1 SLA响应矩阵

7.2 Analysis of RCA root causes of major accidents

Evidence collection of illegal loads: Check the distribution box. If an oversized inductive load is found to be privately connected, take photos to collect evidence and characterize it as a violation by the customer.

Harsh environment evidence collection: If you find water leaking from the roof dripping into the cabinet or the anti-tamper warranty sticker is torn, immediately shut down the machine and take photos

Black box log extraction: Export the BMS bottom-level logs 5 minutes before the crash to analyze whether there is an ultra-high voltage surge in the power grid.

Issue an 8D standard RCA report within 48 hours to clarify the ownership of responsibilities

Chapter 8 Special Specifications for On-site Operation in the Philippines

8.1 Extreme moisture and salt spray corrosion protection

Contact sealing (quarterly): Use electronic cleaner to clean the oxide layer, apply industrial conductive paste after tightening, and spray conformal anti-paint

Anti-condensation management (every rainy season inspection): Check whether the anti-condensation heating plate at the bottom of the cabinet is working properly

8.2 Pest and rodent disaster investigation

Mandatory action: Every time you open the cabinet, the debris at the bottom must be cleaned, and the cable entry and exit holes must be tightly sealed with fireproof mud.

Industrial insect repellent/rodent repellent tablets are regularly placed in the corner of the electrical cabin (replaced quarterly)

8.3 Surge protection of old power grids

Lightning protection module (SPD) inspection: Check the status indicator window every quarter, green = normal, red = activated and needs to be replaced

Before the typhoon season (before June every year): Special SPD inspection of the entire station, and lightning protection modules that are nearing the end of their service life are replaced in advance

Chapter 9 Customer Service and Asset Management

9.1 SOH life tracking and asset health score

The cloud integrates SOC, SOH, maximum pressure difference, and historical overtemperature times to automatically generate a hundred-point "health score"

Monthly physical examination report: The system automatically generates a PDF report on the first day of each month and sends it to the customer.

Commercial conversion: If the score is lower than 80 points, customer service will proactively send an early warning and attach a "Deep Balance and Life Extension Maintenance Quotation"

9.2 SaaS service package grading

9.3 Reference price for paid maintenance

9.4 Spare parts warehouse management (One-in, One-out principle)

Bottom line of safety inventory: 4G gateway, DC circuit breaker, fuse tube, spare battery core, and BMS motherboard should be kept above the safe level

Trade-in and write-off: The engineer applies for a new motherboard for rush repair. When returning, he must hand back the burned old parts and enter them into the system for write-off.

Chapter 10 Annual Maintenance Calendar and KPI System

10.1 Overview of maintenance frequency

10.2 Philippine climate-adapted annual calendar

10.3 Operation and maintenance KPI system

Chapter 11 Firmware Upgrade and Network Security Management

11.1 BMS firmware upgrade procedures

⚠ Version locking principle: Firmware upgrades during the warranty period must be authorized in writing by CoreTect headquarters. Private upgrades will invalidate the warranty.

Backup: Export the complete parameter configuration file from BMS before upgrading, and backup one copy locally and in the cloud.

Version Compatibility Confirmation: Check the compatibility list of new firmware with current battery models

Switch to standby mode and confirm that the charge and discharge current is 0A

Connect the USB to RS485 cable to the laptop and open the corresponding brand PC software

Power outages are strictly prohibited during the upgrade! Monitor the progress bar throughout the process

After the upgrade is completed and the system is restarted, check that all protection parameters are consistent with the backup files one by one.

The cloud confirms that the device is back online, performs 5-minute charge and discharge verification, and files the work order.

11.2 Network security management

Chapter 12 Employee Training and Certification System

Detailed course content can be found in the separate document "CoreTect Engineer Training Course Manual CT-TRN-2026-V1.0"

12.1 Level 3 certification path

12.2 Certification maintenance regulations

L1/L2 certification is renewed every 2 years (retake the practical assessment)

If a safety violation occurs (if LOTO is not implemented), the on-site qualification will be immediately suspended and you must participate in retraining and re-assess.

Chapter 13 Environmental Compliance and Used Battery Disposal

13.1 Relevant regulatory framework in the Philippines

13.2 SOP for disposal of used batteries

⚠ It is strictly prohibited to discard, disassemble, short-circuit or burn used batteries with fire! LFP batteries are hazardous solid waste.

After the battery core is determined to be scrapped, a "hazardous waste" label is attached and the serial number and weight are recorded.

Stored in the dedicated hazardous waste isolation area of ​​the Marikina warehouse (fireproof cabinet, independent area)

When a certain amount is accumulated (recommended once a quarter), contact a DENR-approved hazardous waste treatment provider

Issue a hazardous waste transport manifest (Waste Transport Manifest), and the processor issues a recycling certificate for archiving

13.3 Carbon emission reduction record (customer-oriented ESG report)

Annual power generation per device (kWh) → Carbon reduction (×0.71 kg CO₂/kWh, Philippine power grid emission coefficient)

Automatically generate a "Green Energy Contribution Report" every month as the data source for customers' ESG reports

Compare electricity bills before and after installation to calculate actual economic savings and strengthen motivation for renewal

Appendix A: Monthly inspection record form (printable)

Equipment number: ______________ Customer name: ______________ Address: ____________________________

Inspection date: ______________ Engineer name: ______________ Certification level: □L1 □L2

Weather conditions: □ Sunny □ Cloudy □ Rain Arrival time: ______ Departure time: ______

Comprehensive assessment of this inspection: □ All qualified □ There is a yellow warning (the work order has been registered) □ There is a red warning (the response has been initiated)

Signature of Customer Representative: ____________________ Date: ____________________

Engineer's signature: ____________________ Certificate number: ______________

Appendix B: Standard List of Spare Parts Safety Stock

CoreTect Global Technology | CT-SOP-OM-2026-V2.0 | Internal Top Secret Document

CoreTect_工商储能-户用储能运维SOP_V2.0

储能资产运维管理手册

第 0 章 新系统交付验收规程(FAT / SAT)

0.1 到货开箱检验(Arrival Inspection)

⚠ 若发现运输损坏,立即拍照,24小时内向供应商发出书面索赔通知,超时视为客户接受无损坏。

0.2 上电前静态检测(Pre-Energization)

必须在完全断电状态下执行,执行人:L2级以上工程师。

直流绝缘阻抗测试:1000V兆欧表,正极对地、负极对地,要求 ≥2MΩ

交流绝缘阻抗测试:500V兆欧表,L线对地、N线对地,要求 ≥1MΩ

接地连续性测试:毫欧表验证机柜外壳接地电阻,要求 ≤0.1Ω

直流极性核查:万用表确认电池正负极接线正确,严防反接

AC相序确认:相序表确认三相逆变器L1/L2/L3顺序正确(如适用)

螺栓扭矩抽查:随机抽取5处主回路端子,验证扭矩(M8:12N·m,M10:25N·m)

0.3 首次上电功能验证(Energization Test)

⚠ 首次上电必须由CoreTect L2级以上工程师全程现场监督,严禁代理商单独执行。

0.4 72小时试运行(Burn-In Test)

连续运行72小时,Level 1云端每日远程巡查数据

合格标准:单体压差≤20mV、最高温升≤10℃、无P1/P2级告警

72小时合格后出具《SAT验收合格证书》,作为SLA合同正式生效的法律依据

若72小时内出现故障并处理完毕,重置计时器,重新开始计时

0.5 客户移交(Handover Checklist)

第 1 章 总则与运维管理体系概述

1.1 运维愿景与服务理念

CoreTect摒弃传统"事后抢修(Break-fix)"模式,致力于打造"数据驱动运维(Data-driven O&M)"体系:通过标准化现场操作与云端数据监控,全面落实预防性维护,随着数据沉淀逐步向预测性维护演进,最大化延长储能资产生命周期,杜绝安全事故。

1.2 适用范围与服务边界

管辖范围(SLA覆盖区):CoreTect授权出厂及接管的工商业/户用储能系统柜、BMS通讯链路、云端网关(4G DTU/ESP32)及温控安防子系统。

1.3 核心术语与定义(Glossary)

1.4 运维组织架构与工单流转

第 2 章 月度/季度标准巡检与维保规程

2.1 作业前置条件——PPE与工具

2.2 安全隔离与验电(LOTO SOP)

通过CoreTect Cloud或本地屏幕将系统切至"待机",确认电流显示0A

断开储能柜外部交流主断路器,挂"有人工作,禁止合闸"警示牌并用实体锁锁定

断开高压控制盒直流主断路器,同样挂牌上锁

强制静置放电:等待15分钟,让PCS内部DC-Link大电容完全放电

高压验电:万用表直流1000V档,测量直流母排正极对负极、正极对地电压

⚠ 判定标准:电压<36V DC视为安全,方可进行后续物理接触作业。不达标严禁接触!

2.3 月度外观巡检(每月1次,L1级以上)

2.4 季度深度维保(每季度1次,L2级以上)

2.4.1 热成像扫描(带电满载状态执行)

2.4.2 绝缘测试与扭矩复紧(断电后执行)

直流系统绝缘:1000V兆欧表,正极对地、负极对地。要求:≥2MΩ安全;<1MΩ严禁合闸

交流系统绝缘:500V兆欧表,L/N线对地。要求:≥1MΩ

扭矩复紧:针对热成像异常点,使用绝缘扭矩扳手重新紧固(M6:5N·m,M8:12N·m,M12:45N·m)

2.4.3 BMS数据核查

2.5 CoreTect Cloud自动化巡检机制

每日凌晨2:00:云端自动生成每日健康报告,含绿/黄/红三色标注,推送至客户及运维中心

🟢 90-100分(Excellent):正常维护周期

🟡 70-89分(Fair):亚健康,系统推送预警并附带延寿保养报价

🔴 <70分(Critical):高危状态,触发人工上门干预工单

2.6 作业收尾与数据闭环

清点工具:严防遗留金属工具引发短路,工具袋出入数量必须一致

BMS数据提取:强制下载过去30天底层运行日志存档

恢复送电:拆除LOTO锁,闭合断路器,云端下发开机指令

留观15分钟无告警后方可撤离

工单闭环:移动端上传带时间水印的检查照片,客户电子签名

第 3 章 核心部件更换与现场抢修规程

⚠ 所有操作必须由CoreTect认证工程师执行。任何拆卸动作前,必须完成第2.2节LOTO安全隔离程序。

3.1 排障黄金原则

致命警告:拆装线束顺序颠倒将导致采集线瞬间短路,烧毁主板,甚至引发人员电弧灼伤!

拆卸顺序(严格遵循)

断弱电:首先拔掉所有电芯电压/温度采样排线(白色多芯排线)

断通讯:拔掉RS485/CAN通讯网线及屏幕排线

断主负极输出:拆除接在BMS P-(负载端)上的黑色总负极线

断电池负极输入:最后拆除接在BMS B-(电池端)上的总负极输入线

安装顺序(与拆卸完全相反)

接电池端:连接电池总负极铜排至新BMS的B-端子,扭矩12N·m,划防松线

接输出端:连接外部输出负极至BMS的P-端子

采样线核验与接入:万用表依次测量排线各针脚,确认电压呈3.2V/6.4V/9.6V梯级递增后插入

恢复通讯:插回4G DTU网线与测温NTC探头

软件烧录与验证

开启直流空开,上电,通过USB转RS485线连接笔记本

载入CoreTect针对该型号电池的专属参数包(过压3.65V、欠压2.70V等)

云端后台确认设备重新上线,完成试运行15分钟,提交换件SN码

3.3 逆变器主板整板更换规程

适用场景:IGBT D-S之间阻值≈0Ω;逆变器上电即报硬件保护(E006/F10)且无法复位。

⚠ 更换前必须拍照取证(机柜内部全貌、IGBT特写、配电箱、封条状态),作为RCA法务证据!

执行LOTO,确认DC BUS电压<36V

拔除所有通讯线,松开驱动板与功率板连接排线

拆除散热器固定螺丝,清除旧导热硅脂,清洁散热器铝基板

安装新主板,均匀涂抹导热硅脂(厚度0.1-0.2mm)

按规定扭矩紧固(M6:5N·m,M8:12N·m)

不接负载,仅合直流空开,观察母线电压是否正常上升

导入CoreTect标准参数配置文件,特别核实60Hz频率设定

开启空载逆变,万用表测量AC输出:应为220V/60Hz正弦波

逐步加载至50%额定功率,监控IGBT温升(前30分钟须人员全程留守)

3.4 单体电芯压差均衡与更换规程

适用场景:云端报警单体压差(ΔV) >100mV,或某串电芯内阻异常。

电芯更换步骤

云端精准定位落后电芯编号

使用专业吸盘垂直向上提取电芯(314Ah单体约5.5kg),严禁抓着极柱提拉!

新电芯入列,中间插入1mm厚FR4绝缘板防止摩擦短路

连接铜排,扭矩严格设定为6N·m(M6螺柱)。紧固后用红色记号笔画"一字防松线"

深度均衡:CC-CV模式,3.60V截止,20A~50A电流,充至电流降至0.5A以下

第 4 章 极端场景与灾难应急预案(ERP)

4.1 台风与严重洪涝灾害预案

4.1.1 台风登陆前48小时(PAGASA Signal No.2及以上触发)

云端动作:自动向逆变器下发"强制满充指令",提高SOC下限至80%

现场动作:检查室外机柜防雨百叶窗是否锁死,清理机柜周围2米内排水沟

4.1.2 积水即将漫过机柜底部10cm时——紧急熔断

⚠ 远程强制关闭逆变器及BMS充放电。指导客户穿绝缘靴,立即拉下直流总闸和交流总闸。

4.1.3 灾后恢复送电(致命红线)

⚠ 绝对禁令:严禁客户在水退后自行合闸送电!违规开机导致的炸机不予质保!

工程师携1000V兆欧表上门,内部有水汽则使用工业热风机吹干

绝缘阻抗测试:正负极对地必须>2MΩ,达标后方可恢复送电

4.2 电池热失控应急规程(Thermal Runaway)

触发条件:单体温度>75℃持续上升,或机柜发出嘶嘶泄压声并有刺鼻白烟。

第 5 章 PCS(储能变流器)运维标准

5.1 PCS安全隔离与验电规范

依次断开交流电网断路器、负载断路器、PV隔离开关及电池直流总闸

强制静置≥5分钟(100kW以上机型需15分钟),让内部DC-Link大电容完全放电

万用表直流1000V档测量BAT+与BAT-,确认内部残余电压<36V DC

5.2 PCS电气连接与扭矩维保

5.3 PCS散热与防尘维保

外置防尘网(每月):拆卸进风口防尘网,高压气枪(压力<0.3MPa)清洗,彻底晾干后装回

散热风扇测试(每季度):屏幕诊断菜单强制启动风扇100%运转,有轴承异响则更换

导热硅脂检查(每年):检查硅脂是否干裂粉化,如有异常重新涂抹(厚度0.1~0.2mm)

第 6 章 通讯与云平台运维标准

6.1 物理链路层检查

通讯线缆抗干扰:RS485和CAN通讯线必须使用双绞屏蔽线,屏蔽层在逆变器端单端接地

与交直流粗电缆保持15cm以上间距,严禁在同一线槽内平行捆扎

终端匹配电阻:总线距离超过50米,总线最末端必须并联120Ω终端电阻

6.2 边缘智能网关运维

信号强度:RSSI>-85dBm,低于此值必须将天线移至室外无遮挡处

看门狗测试(每季度):拔掉4G天线模拟断网,观察网关能否在300秒内自动重启重连

6.3 网络安全管理

默认密码修改:SAT阶段必须修改出厂默认密码(admin/admin),设定≥12位强密码

API密钥轮换:Telegram Bot等第三方集成API密钥每年轮换一次

操作日志留存:云端所有参数修改、远程控制指令自动记录,保留≥2年

第 7 章 故障响应与RCA调查

7.1 SLA响应矩阵

7.2 重大事故RCA根因分析

违规负载取证:核查配电箱,若发现私接超大感性负载,拍照取证,定性为客户违规

恶劣环境取证:若发现屋顶漏水滴入机柜或防拆保修贴纸被撕毁,立即封机拍照

黑匣子日志提取:导出崩溃前5分钟BMS底层日志,分析是否存在电网超高压浪涌

48小时内出具8D标准RCA报告,明确责任归属

第 8 章 菲律宾现场运维特种规范

8.1 极端防潮与盐雾腐蚀防护

接点密封(每季度):用电子清洁剂清理氧化层,拧紧后涂抹工业导电膏,喷涂三防漆

防凝露管理(每次雨季巡检):核查机柜内底部防凝露加热板是否正常工作

8.2 虫鼠害灾难排查

强制动作:每次开柜必须清理底部杂物,电缆进出孔用防火泥严密封堵

电气舱角落定期投放工业驱虫/驱鼠药锭(每季度更换一次)

8.3 老旧电网浪涌防护

防雷模块(SPD)检查:每季度检查状态指示窗,绿色=正常,红色=已动作需更换

台风季前(每年6月前):全站SPD专项检查,提前更换临近使用寿命的防雷模块

第 9 章 客户服务与资产管理

9.1 SOH寿命追踪与资产健康评分

云端融合SOC、SOH、最大压差、历史过温次数,自动生成百分制"健康评分"

月度体检报告:系统每月首日自动生成PDF报告发送给客户

商业转化:评分低于80分,客服主动发送预警并附带《深度均衡与延寿保养报价单》

9.2 SaaS服务包分级

9.3 有偿维修参考价格

9.4 备件仓储管理(One-in, One-out原则)

安全库存底线:4G网关、直流空开、保险丝管、备用电芯、BMS主板保持安全水位以上

以旧换新核销:工程师申领新主板抢修,返回时必须交回烧毁旧件录入系统核销

第 10 章 年度维护日历与KPI体系

10.1 维护频次总览

10.2 菲律宾气候适配版年度日历

10.3 运维KPI体系

第 11 章 固件升级与网络安全管理

11.1 BMS固件升级规程

⚠ 版本锁定原则:质保期内固件升级必须获得CoreTect总部书面授权,私自升级导致质保失效。

备份:升级前从BMS导出完整参数配置文件,本地+云端各备份一份

版本兼容性确认:核对新固件与当前电池型号的兼容性列表

切换待机模式,确认充放电电流为0A

USB转RS485线连接笔记本,打开对应品牌上位机软件

升级期间严禁断电!全程监控进度条

升级完成系统重启后,逐项核对所有保护参数与备份文件一致

云端确认设备重新上线,执行5分钟充放电验证,工单归档

11.2 网络安全管理

第 12 章 员工培训与认证体系

详细课程内容见单独文件《CoreTect工程师培训课程手册 CT-TRN-2026-V1.0》

12.1 三级认证路径

12.2 认证维护规定

L1/L2认证每2年更新一次(重新参加实操考核)

发生安全违规事件(如未执行LOTO),立即暂停现场资格,须参加再培训后重新考核

第 13 章 环境合规与废旧电池处理

13.1 菲律宾相关法规框架

13.2 废旧电芯处理SOP

⚠ 严禁随意丢弃、拆解、短路或用火焚烧废旧电池!LFP电池属有害固体废弃物。

电芯判定报废后,贴上"危险废弃物"标签,记录序列号和重量

存入Marikina仓库专用危废隔离区(防火柜,独立区域)

累积到一定数量(建议每季度一次),联系DENR认可的危废处理商

出具危废转运清单(Waste Transport Manifest),处理商出具回收证明存档

13.3 碳减排记录(面向客户ESG报告)

每台设备年度发电量(kWh)→ 减碳量(×0.71 kg CO₂/kWh,菲律宾电网排放系数)

每月自动生成《绿色能源贡献报告》作为客户ESG报告的数据来源

对比安装前后电费账单,计算实际经济节省,强化续约动机

附录A:月度巡检记录表(可打印)

设备编号:______________ 客户名称:______________ 地址:__________________________

巡检日期:______________ 工程师姓名:______________ 认证级别:□L1 □L2

天气状况:□晴 □阴 □雨 抵达时间:______ 离开时间:______

本次巡检综合评定:□全部合格 □存在黄色预警(已登记工单) □存在红色告警(已启动响应)

客户代表签字:________________________ 日期:__________________

工程师签字:__________________________ 证书编号:______________

附录B:备件安全库存标准清单

CoreTect Global Technology | CT-SOP-OM-2026-V2.0 | 内部绝密文件