Panoramic view of integrated photovoltaic power station energy storage side equipment topology and inspection SOP training

Panoramic view of integrated photovoltaic power station energy storage side equipment topology and inspection SOP training

Full-cycle inspection and maintenance plan matrix for the energy storage side of photovoltaic power stations (day/week/month/quarter/year)

This article stipulates the time nodes, technical requirements and division of responsibilities for daily inspections, regular maintenance, quarterly inspections and annual overhauls of all energy storage power station equipment throughout the life cycle.

1. Daily inspection plan (daily inspection: online SCADA monitoring + on-site inspection)

Daily inspections are divided into "online 7×24h real-time monitoring" and "on-site routine inspections", with the core being the timely discovery of abnormal alarms and environmental hazards.

(1) Daily online SCADA/EMS monitoring (completed before 09:00)

Charge and discharge efficiency and energy calculation: retrieve the RTE (charge and discharge efficiency) of the entire station on the previous day, and the entire liquid-cooled station must be ≥ 85%.

Extreme value data and pressure difference/temperature difference troubleshooting:

Cell extreme voltage and voltage difference: the static voltage difference must be < 20 mV, and the voltage difference at the end of charge and discharge must be < 50 mV.

Single unit extreme temperature and temperature difference: the maximum operating temperature must be < 40.0 ℃, and the extreme temperature difference within the cluster must be ≤ 3.0 ℃.

Insulation resistance trace: Check the insulation monitor data. The DC-to-ground insulation resistance must be ≥ 1000 Ω/V.

Alarm log review: Search the SCADA system alarm logs for the past 24 hours to confirm that there are no primary or secondary unreset alarms.

(2) Daily on-site inspection (completed before 14:00)

Station environment and perimeter: The perimeter fence is not damaged and the electronic fence is normal; the flood control drainage channel is smooth and the water retaining board (≥ 500 mm) is in place; the explosion-proof pressure relief valve outside the cabin is intact and unobstructed.

Station power and fire protection main screen: The station AC power distribution cabinet has no abnormal tripping; the station DC panel/UPS is running normally; the fire control main screen (FACP) operating light is always on, and there is no fire alarm/fault alarm.

High-voltage switch and box transformer: The SF6 pressure gauge of the 35kV switch cabinet is in the green zone (0.35 ~ 0.45 MPa); the vacuum circuit breaker shows "energy stored"; the oil level of the booster box transformer is at the 25°C scale line, and the moisture absorber silica gel is dark blue.

PCS variable flow chamber and temperature control: The PCS fan runs smoothly without abnormal noise; the liquid cooling unit circulating water pump pressure is between 0.15 ~ 0.30 MPa, and the expansion tank liquid level is at 1/2 ~ 2/3, with no leakage.

2. Weekly inspection plan (weekly inspection: on-site in-depth inspection and functional self-inspection)

Weekly inspections focus on in-depth functional testing of auxiliary systems, safety protection devices and electrical connection points.

Explosion-proof exhaust and gas probe test: Press the "forced exhaust button" outside the cabin on site to test the explosion-proof exhaust fan forced start time (must be < 2s) and wind speed (must be ≥ 8 m/s). Spot check the CO/H2/VOC probe communication is normal.

Battery pack float voltage measurement: Use a digital multimeter to measure the DC screen lead-acid/gel battery cell float voltage. The qualified range is 13.50 V ~ 13.80 V.

Infrared thermal imaging temperature rise scanning: Use an infrared thermal imaging camera to scan when the power station is charging and discharging at 0.5C full power:

35kV cable terminals and high-voltage switch cabinet busbars (maximum temperature must be < 70 ℃, temperature difference ΔT ≤ 5 ℃); PCS incoming and outgoing circuit breaker terminals (maximum temperature must be < 65 ℃); battery cluster high-voltage box (BDU) terminals and main connecting copper bars (maximum temperature must be < 60 ℃, temperature difference ΔT ≤ 5 ℃).

Inspection of water marks and filter screen in liquid cooling pipes: Check the self-sealing liquid cooling quick-change joint inside the Pack. Use a water mark test paper close to the joint gap to confirm that there is no trace leakage; check the pressure difference between the inlet and outlet of the Y-type filter.

3. Monthly inspection and maintenance plan (monthly maintenance: cleaning, water quality analysis and strategic alignment)

Monthly maintenance focuses on physical cleaning of equipment, chemical analysis of coolant water quality, and calibration of control strategies.

(1) Monthly equipment cleaning and physical maintenance

Disassembly and cleaning of PCS and air-conditioning dust filter: Remove the PCS air inlet and air-cooled air-conditioning primary filter cotton, clean and dry them completely and then reinstall them.

Hatch door sealing and anti-condensation: Check the EPDM strip of the door and add anti-rust grease; test the automatic start-up function of the anti-condensation heater when the humidity is > 70% RH.

(2) Coolant water quality chemical analysis and filter cleaning SOP

Water quality index testing: sampling and measuring coolant:

Conductivity: must be < 5.0 μS/cm (when the conductivity is ≥ 10.0 μS/cm, the resin filter element must be replaced or the fluid must be changed);

pH value: must be maintained between 7.0 ~ 8.5; freezing point: must be ≤ -35.0 ℃.

Y-type filter cleaning: stop the water pump to release the pressure, remove the 100-mesh stainless steel filter of the Y-type filter, clean the scale and impurities, replace the fluororubber sealing ring and put it back, refill and exhaust to the water pressure of 0.18 ~ 0.22 MPa.

(3) Strategy alignment and passive balancing resistance check

Alignment of peak and valley arbitrage strategies: Check the EMS internal charge and discharge clock to be 100% aligned with the latest peak and valley electricity price period of the local power grid.

Passive equalization resistor infrared temperature measurement: When passive equalization is started, use an infrared thermal imager to scan the BMU board discharge resistor. The heating temperature must be < 60.0 ℃, and there should be no burnt open circuit.

4. Quarterly inspection and maintenance plan (quarterly inspection: mechanical fastening, actual protection measurement and capacity depth balancing)

Quarterly maintenance focuses on bolt tightening torque verification, safety protection function logic testing and battery depth equalization.

Random test of high-voltage bolt tightening torque (executed during power outage): Use a calibrated insulated torque wrench to randomly test the bolt tightening torque at a ratio of 20%: M6 pole bolts: 6.0 ~ 8.0 N·m; M8 copper bar bolts: 18.0 ~ 20.0 N·m; M10 BDU terminals: 38.0 ~ 42.0 N·m; M12 PCS busbar: 80.0 ~ 85.0 N·m; re-mark the anti-loosening marking line after random testing.

Actual measured SOP for anti-islanding protection: In the PCS grid-connected discharge (50% power) state, manually disconnect the grid-side analog circuit breaker. The oscilloscope measured the PCS to cut off the AC current output within < 200 ms and report a grid-side power loss alarm.

Fire-extinguishing cylinder weighing and drive valve self-inspection: weigh and recheck the heptafluoropropane fire-extinguishing cylinder, the mass reduction must be ≤ 5% of the nominal net weight; check the pressure of the nitrogen-driven small cylinder (6.0 ± 0.2 MPa); check that the mechanical safety pin of the electromagnetic drive valve is in the pulled out/unlocked state.

Artificial offline power supply and depth equalization: When the extreme voltage difference of a certain cluster of cells is > 100 mV and automatic equalization fails, use a portable power supply instrument to perform 20A limited power supply on the low-voltage Pack. After power supply, the extreme voltage difference must be < 15 mV after leaving it alone for 1 hour.

5. Annual overhaul and preventive test plan (annual maintenance: station-wide power outage maintenance and drill)

The annual overhaul is the highest-level comprehensive overhaul of the entire power station. It is usually arranged to carry out power outage overhaul during the power grid maintenance window period.

Waterless dry purge in the cabin: Use 0.20 ~ 0.30 MPa dry waterless compressed air (equipped with insulated nozzle hose) to purge the dust accumulated on the PCS, high-voltage cabinet and BMS control board in a "top-down" order.

Test the different-frequency resistance of the station's main grounding network: Use a different-frequency grounding resistance tester to measure. The power-frequency resistance of the entire station's main grounding network must be < 0.5 Ω. Check the corrosion of underground flat steel (corrosion rate > 30% requires repair welding).

AC/DC high voltage preventive test:

High voltage switch cabinet and cable withstand voltage test;

Box-type transformer oil dissolved gas analysis (DGA) and winding insulation testing;

Lightning arrester (SPD) continuous leakage current test (must be < 1.0 mA).

Protection setting sheet 100% aligned: Export the setting value of the microcomputer protection device and check it word for word with the latest setting notice from the power grid dispatching department. The error must be 0.0%.

Accurate time synchronization and network packet loss rate of the whole station: GPS/Beidou dual-mode time synchronization, the clock error of the whole station equipment must be ≤ 1.0 ms; the packet loss rate of the whole station LAN in the 24-hour Ping test must be < 0.01%.

Full-station RTE efficiency calibration and capacity degradation assessment: Carry out 100% DoD full-capacity charge and discharge, calculate the whole-station RTE efficiency and battery SOH health (SOH < 70%, apply for decommissioning).

Thermal runaway level three fire emergency drill: Cooperate with the local fire department to conduct a full-process practical drill including thermal runaway warning, gas extinguishing release, strong exhaust air cutoff and water spray cooling.

CoreTect photovoltaic power station energy storage side operation and maintenance engineering department operation and maintenance plan execution table

光伏电站储能侧设备拓扑与巡检 SOP 培训一体化全景图

光伏电站储能侧设备拓扑与巡检 SOP 培训一体化全景图

光伏电站储能侧全周期巡检与保养计划矩阵篇(日/周/月/季/年)

本篇规定了储能电站全站设备在全生命周期内的日常巡视、定期维保、季度检修及年度大修的时间节点、技术要求与责任划分。

一、 每日巡检计划(日巡:线上 SCADA 监控 + 现场巡视)

每日巡检分为“线上 7×24h 实时监测”与“现场例行巡视”,核心在于及时发现异常告警与环境隐患。

(一)每日线上 SCADA / EMS 监控(09:00 前完成)

充放电效率与能量核算:调取前一日整站 RTE(充放电效率),液冷整站须 ≥ 85%。

极值数据与压差/温差排查:

单体极值电压与压差:静置压差须 < 20 mV,充放电末期压差须 < 50 mV。

单体极值温度与温差:运行最高温度须 < 40.0 ℃,簇内极值温差须 ≤ 3.0 ℃。

绝缘阻抗轨迹:检查绝缘监测仪数据,直流对地绝缘电阻阻抗须 ≥ 1000 Ω/V。

告警日志检视:检索 SCADA 系统过去 24 小时告警日志,确认无一、二级未复位告警。

(二)每日现场例行巡视(14:00 前完成)

站区环境与周界:周界围栏无破损,电子围栏正常;防汛排水沟通畅,挡水板(≥ 500 mm)到位;舱外防爆泄压阀完好无遮挡。

站用电与消防主屏:站用 AC 配电柜无异常跳闸;站用直流屏/UPS 运行正常;消防控制主屏(FACP)运行灯常亮,无火警/故障告警。

高压开关与箱变:35kV 开关柜 SF6 气压表处于绿区(0.35 ~ 0.45 MPa);真空断路器显示“已储能”;升压箱变油位在 25 ℃ 刻度线,吸湿器硅胶呈深蓝色。

PCS 变流舱与温控:PCS 风机运行平稳无异响;液冷机组循环水泵压力在 0.15 ~ 0.30 MPa,膨胀罐液位处于 1/2 ~ 2/3 处,无漏液。

二、 每周巡检计划(周巡:现场深入检测与功能自检)

每周巡检侧重于对辅助系统、安全保护装置及电气连接点的深入功能测试。

防爆排风与气体探头测试:现场按下舱外“强制排风按钮”,测试防爆排风机强启时间(须 < 2s),风速(须 ≥ 8 m/s)。抽查 CO/H2/VOC 探头通讯正常。

蓄电池组浮充电压测量:使用数字万用表测量站用直流屏铅酸/胶体蓄电池单体浮充电压,合格范围为 13.50 V ~ 13.80 V。

红外热成像温升扫描:在电站 0.5C 满功率充放电状态下,使用红外热像仪扫描:

35kV 电缆终端头及高压开关柜母排(最高温度须 < 70 ℃,温差 ΔT ≤ 5 ℃);PCS 进出线断路器端子(最高温度须 < 65 ℃);电池簇高压箱 (BDU) 端子及主要连接铜排(最高温度须 < 60 ℃,温差 ΔT ≤ 5 ℃)。

液冷管道水痕与滤网检查:检查 Pack 内部自封式液冷快换接头,使用水痕试纸贴近接头缝隙,确认无微量滴漏;检查 Y 型过滤器进出口压差。

三、 月度巡检与维保计划(月维:清洁、水质分析与策略对齐)

月度维保侧重于设备的物理清洁、冷却液水质化学分析及控制策略校对。

(一)月度设备清洁与物理维护

PCS 及空调防尘网拆洗:拆下 PCS 进风口及风冷空调初效过滤棉,清洗并完全晾干后装回。

舱门密封与防凝露:检查舱门 EPDM 胶条,加注防锈润滑脂;测试湿度 > 70% RH 时防凝露加热器自动启动功能。

(二)冷却液水质化学分析与过滤器清洗 SOP

水质指标检测:取样测量冷却液:

电导率:须 < 5.0 μS/cm(当电导率 ≥ 10.0 μS/cm 时必须更换树脂滤芯或换液);

pH 值:须保持在 7.0 ~ 8.5 之间;冰点:须 ≤ -35.0 ℃。

Y 型过滤器清洗:停水泵泄压,拆下 Y 型过滤器 100 目不锈钢滤网清洗水垢与杂质,更换氟橡胶密封圈后装回,补液排气至水压 0.18 ~ 0.22 MPa。

(三)策略对齐与被动均衡电阻检查

峰谷套利策略对齐:核对 EMS 内部充放电时钟,与当地电网最新峰谷电价时段 100% 对齐。

被动均衡电阻红外测温:在被动均衡启动时,用红外热像仪扫描 BMU 板放电电阻,发热温度须 < 60.0 ℃,无烧焦开路。

四、 季度巡检与检修计划(季检:力学紧固、保护实测与容量深度均衡)

季度检修侧重于螺栓紧固力矩校验、安全保护功能逻辑实测及电池深度均衡。

高压螺栓紧固力矩抽测(停电执行):使用校准后的绝缘扭力扳手,按 20% 比例抽测螺栓紧固力矩:M6 极柱螺栓:6.0 ~ 8.0 N·m;M8 铜排螺栓:18.0 ~ 20.0 N·m;M10 BDU 端子:38.0 ~ 42.0 N·m;M12 PCS 母排:80.0 ~ 85.0 N·m;抽测后重打防松标记线。

防孤岛保护(Anti-Islanding)实测 SOP:在 PCS 并网放电(50% 功率)状态下,手动断开网侧模拟断路器,示波器实测 PCS 须在 < 200 ms 内切断交流电流输出并报网侧失电告警。

灭火钢瓶称重与驱动阀自检:对七氟丙烷灭火钢瓶进行称重复核,质量减少须 ≤ 5% 标称净重;检查氮气驱动小钢瓶压力(6.0 ± 0.2 MPa);检查电磁驱动阀机械安全保险销处于拉出/解除锁定状态。

人工离线加补电深度均衡:当某簇单体极值压差 > 100 mV 且自动均衡失效时,使用便携式补电仪对低电压 Pack 进行 20A 限制加补电,补电后静置 1 小时极值压差须 < 15 mV。

五、 年度大修与预防性试验计划(年修:全站停电检修与演练)

年度大修是全电站最高级别的全面检修,通常安排在电网维护窗口期进行全站停电大修。

舱内无水干吹扫:使用 0.20 ~ 0.30 MPa 干燥无水压缩空气(配绝缘喷嘴软管),按“自上而下”顺序吹扫 PCS、高压柜及 BMS 控制板卡积灰。

站用主接地网异频电阻测试:使用异频接地电阻测试仪测量,整站主接地网工频电阻须 < 0.5 Ω。检查地下扁钢腐蚀情况(腐蚀率 > 30% 须补焊)。

交流/直流高压预防性试验:

高压开关柜及电缆耐压试验;

箱变变压器油溶解气体分析(DGA)及绕组绝缘测试;

避雷器(SPD)持续泄漏电流测试(须 < 1.0 mA)。

保护定值单 100% 对齐:导出微机保护装置定值,与电网调度部门最新的整定通知单逐字逐句核对,误差须为 0.0%。

全站精确对时与网路丢包率:GPS/北斗双模对时,全站设备时钟误差须 ≤ 1.0 ms;24 小时 Ping 测试全站局域网丢包率须 < 0.01%。

全站 RTE 效率校准与容量退化评估:进行 100% DoD 全容量充放电,核算整站 RTE 效率及电池 SOH 健康度(SOH < 70% 申请退役)。

热失控三级消防应急演练:联合当地消防部门,进行热失控前兆预警、气灭释放、强排风切断及水喷淋降温的全流程实战演练。

CoreTect 光伏电站储能侧运维工程部运维计划执行表