Part 8: Photovoltaic power station energy storage side secondary system, EMS and overall station comprehensive troubleshooting SOP

Part 8: Photovoltaic power station energy storage side secondary system, EMS and overall station comprehensive troubleshooting SOP

This article corresponds to the panoramic topology diagram of the energy storage power station [Module 8: Secondary and EMS system], covering the local EMS server, SCADA monitoring background, dual-machine hot standby switching, time series database management, core control strategy (AGC / AVC / peak and valley arbitrage), relay protection device setting review, microgrid seamless switching and black start, station communication optical ring network, NTP/PTP time synchronization, telecontrol RTU four-remote testing and full-station cross-system comprehensive troubleshooting SOP.

1. Local EMS server, SCADA backend and control strategy maintenance SOP

EMS (Energy Management System) is responsible for station-wide power dispatching, strategy calculation, data storage and real-time interaction with the power grid dispatching main station.

(1) EMS server dual-machine hot standby and redundant switching test SOP

Master/standby server status check: Check the running status of the master server (Master) and the backup server (Slave), confirm that the dual-machine heartbeat cable (Heartbeat Cable) is connected normally, and the real-time redundant mirror synchronization of the database is without delay.

Dual-machine hot standby automatic switching test SOP (performed every six months): When the power station is running smoothly, manually unplug the main server network cable or cut off the main server power supply (simulating a sudden host failure). The backup server must automatically take over control of the entire site within < 1.0s, the SCADA monitoring screen must not freeze or crash, and the charging and discharging strategies being executed must not be interrupted.

(2) Database storage management and performance optimization

Database check: Check local time series database (such as InfluxDB, TDengine or MySQL) disk partition space. Disk remaining space must be > 30%.

Data archiving specifications: Second-level sampling data of the entire site must be saved locally for ≥ 90 days; minute-level historical data and alarm logs must be saved for ≥ 3 years. Database index reconstruction and cold data offline backup must be performed every quarter.

(3) Core control strategy execution and accuracy accounting SOP

Peak-Shaving strategy: Check the charge and discharge schedule within the EMS strategy engine to be 100% aligned with the latest peak-to-valley flat price period of the local power grid (such as off-peak charging: 23:0007:00, peak discharge: 11:00-15:00, 18:00~21:00).

AGC (automatic generation control) response and tracking accuracy: When receiving the AGC power adjustment instruction issued by the power grid dispatcher, the EMS must complete the instruction decomposition and issue it to each PCS within < 1.0s. The tracking accuracy of the actual output power of the whole station to the AGC instruction must be ≥ 99.0%.

AVC (automatic voltage control) reactive power regulation: Automatically controls the PCS output reactive power according to the grid-side node voltage fluctuation, and controls the 35kV bus voltage deviation within ± 2.5% of the rated voltage range.

2. Maintenance SOP for microcomputer relay protection devices, microgrid controllers and anti-backflow devices

Secondary protection equipment is the "last barrier" to prevent the expansion of electrical faults and ensure the safety of equipment and people.

(1) Microcomputer relay protection device self-test and setting sheet review SOP

Protection device panel self-inspection: Check the microcomputer protection devices (overcurrent protection, quick-break protection, zero-sequence overvoltage protection, differential protection) on the high-voltage switch cabinet and the main control room protection screen. The green light of "Run" of the device is always on, and the yellow and red light of "Alarm" or "Abnormal" are off.

Protection setting sheet review SOP (every year or when the setting changes): Derive the current setting value (Protection Settings) inside the protection device, and check it word for word with the "Relay Protection Setting Notice" issued and stamped by the power grid dispatching department. The current/voltage setting error must be 0.0% (absolutely consistent).

(2) Microgrid controller on-grid/off-grid seamless switching and black start (Black Start)

On-grid/off-grid seamless transfer (Seamless Transfer): In a microgrid or distributed energy storage scenario, when a grid drop or power outage is detected, the microgrid controller must control the static switch (STS) to disconnect the grid connection point within < 20ms, and at the same time control the main energy storage PCS to switch from PQ mode to V/F (voltage/frequency) mode to ensure that important loads do not lose power.

Black Start control logic: When there is a large-scale power outage in the entire network, the microgrid voltage is established by relying on the energy storage system's own battery and the station's DC panel to start.

Steps: Start the station UPS ➔ Activate the main control BMS and PCS ➔ The PCS establishes 380V/690V AC voltage in V/F mode ➔ Charge the booster transformer ➔ Close the important load circuit breakers step by step.

(3) Station anti-backflow protection device

When the energy storage/photovoltaic system is prohibited from sending power back to the public grid, the anti-backflow protection device monitors the current at the grid connection point in real time. When it is detected that the reverse power reaches the set threshold (for example, set to 10 kW), the anti-backflow device must send a derating or shutdown command to the EMS and PCS within < 200ms.

3. Station communication network, precise clock synchronization and telecontrol RTU "four remote" maintenance SOP

(1) Industrial optical ring network switch and packet loss rate test

Optical fiber self-healing ring network (RSTP/ERPS) self-healing test: artificially unplug an optical fiber in the ring network (simulating optical cable interruption), the ring network must complete self-healing reconstruction within < 20ms, and communication will not be interrupted.

Network packet loss rate and delay test: Use a network analyzer in the backend of the main control room to conduct a ping test on all BMS, PCS and gateways of the entire site. The network delay of the whole site LAN must be < 5ms, and the 24-hour continuous test packet loss rate must be < 0.01%.

(2) Precise clock synchronization of the whole station (NTP / IEEE 1588 PTP)

The clock source is combined with the satellite time synchronization receiver in the main control room (GPS/Beidou dual-mode time synchronization source). The clock error of all servers, BMS cluster controllers, PCS control panels and relay protection devices in the entire site must be ≤ 1.0 ms to ensure that the timestamps recorded in the SOE accident sequence are completely consistent when a failure occurs.

(3) Telecontrol RTU and dispatch gateway "four remote" test SOP

Communicate with the power grid dispatching main station through the IEC 60870-5-104 protocol, and conduct regular "four remote" function checks:

Telemetry (YC): Check the total active/reactive power of the entire station, bus voltage, total cluster current and other analog quantities, with an error ≤ ± 0.5%;

Remote signaling (YX): Test switch circuit breaker opening and closing status, fault alarm signal, displacement response time < 100ms;

Remote control (YK): Test and dispatch remote control of the main circuit breaker opening and closing function, and the logic locking is safe and correct;

Remote adjustment (YT): Test dispatch to remotely set PCS active/reactive power settings.

4. Typical cross-system comprehensive troubleshooting and recovery SOP (code-level diagnosis) for the entire site

When a complex fault occurs in the power station that spans the battery, PCS, temperature control and grid side, the operation and maintenance team must conduct unified command in the main control room and conduct troubleshooting according to the following SOPs:

(1) Comprehensive fault one: Insulation resistance of the whole station is too low (Riso Low) Cascade troubleshooting and positioning SOP

Step 1: Environment investigation. Check the temperature and humidity of each battery compartment and PCS compartment on the EMS interface. If the humidity in the cabin is > 85% RH, start the cabin dehumidifier for strong dehumidification for 2 hours, and then reset the test; if the humidity is normal (< 70% RH), it is determined that the physical insulation is damaged and enter step 2.

Step 2: AC and DC splitting. Open the PCS DC side main circuit breaker and decouple the PCS from the battery array. Use a 1000V megger to measure the PCS DC bus impedance to ground (if the impedance is < 1MΩ, check the PCS DC filter capacitor and IGBT) and the battery array total bus impedance to the ground (if the impedance is < 1MΩ, go to step 3).

Step 3: Cluster-level positioning. Open the DC circuit breakers of all battery cluster high-voltage units (BDUs). Close the single cluster switches one by one. When the Cluster N switch is closed, the insulation monitor alarms and the impedance drops suddenly, and Cluster N can be locked as a fault cluster.

Step 4: Module location and repair. Operation and maintenance personnel wore PPE and entered the cabin, unplugging the series high-voltage lines between the Packs in Cluster N. Use a megger to measure the resistance of the positive/negative poles of the Pack to the shell one by one, and find faulty Packs with impedance < 1MΩ. ➔ Open the cover and check whether there is leakage of liquid cooling pipelines, antifreeze water accumulation, or broken high-voltage cables. ➔ Clean the leakage/bandage and replace the cables. ➔ Test the insulation resistance impedance > 10MΩ. ➔ Restore closing.

(2) Comprehensive fault two: battery cell thermal runaway precursor (CO/H2 gas and temperature abnormality) three-level response SOP

Step 1: First-level millisecond automatic response. When the BMS/fire probe detects that single CO > 50ppm or H2 > 200ppm and the temperature change rate dT/dt ≥ 2.0 ℃/min, the BMS automatically cuts off the high-voltage contactor of the fault cluster, and the EMS issues an instruction to trip the AC/DC main circuit breaker, and at the same time automatically starts the outdoor explosion-proof exhaust fan for strong ventilation.

Step 2: Secondary automatic fire linkage. If the sensor further triggers a temperature/smoke secondary fire alarm, the cabin air conditioner and air duct fire damper (damper) will be automatically closed. After the audible and visual alarm outside the cabin counts down for 30 seconds, the electric explosion valve will be automatically activated to release the heptafluoropropane gas fire extinguishing agent. The cabin will be extinguished and left to stand for no less than 20 minutes.

Step 3: Three-level manual treatment and backup cooling. The operation and maintenance personnel wore positive-pressure air respirators and explosion-proof clothing to reach the safe area 50 meters away from the upwind outlet, and used infrared thermal imaging cameras to continuously monitor the temperature of the outer wall of the battery compartment through the partition wall. If the temperature stops falling and rebounds (there is a tendency to re-ignite), start the external Pack-level water spray/immersion system to continue cooling the battery.

(3) Comprehensive fault three: Communication interruption between PCS and grid side or grid overvoltage/undervoltage/abnormal frequency trip troubleshooting SOP

Communication interruption: Check the PCS network port indicator corresponding to the optical ring network switch in the main control room. If the light is off, test the fiber attenuation (must be < 3.0 dB); if the fiber is normal, restart the PCS control board communication module.

Abnormal grid-side voltage trip: retrieve the power quality analyzer waveform in the main control room. If the grid side voltage exceeds 1.1 Un (overvoltage) or is lower than 0.85 Un (undervoltage), check the over/under voltage protection action time of the PCS. After the grid voltage returns to normal, reset the fault on the EMS interface and resume operation according to the logic of "boost transformer ➔ AC circuit breaker ➔ DC contactor ➔ PCS standby ➔ power start"

Photovoltaic power station energy storage side secondary system, EMS and comprehensive fault site inspection sign-in form for the whole station

Power station name: _______________________________ Inspection date: ____ month ____ day, 2026

Inspection area: Main control room secondary system and EMS control backend Inspection person in charge: ____________________

1. Field equipment inspection and test data records:

2. Inspection defect registration and defect elimination dispatch:

3. Inspection sign-in and review signature:

Inspection engineer (signature): _______________ Supervision engineer (signature): _______________

Review (signature) of the shift leader: _______________ Sign-in and filing time: ____ hour on ____ month ____ day 2026

第8篇:光伏电站储能侧二次系统、EMS 与全站综合故障排查 SOP

第8篇:光伏电站储能侧二次系统、EMS 与全站综合故障排查 SOP

本篇对应储能电站全景拓扑图【模块八:二次与 EMS 系统】,涵盖本地 EMS 服务器、SCADA 监控后台、双机热备切换、时序数据库管理、核心控制策略(AGC / AVC / 峰谷套利)、继电保护装置定值复核、微电网无缝切换与黑启动、站用通信光环网、NTP/PTP 对时、远动 RTU 四遥测试以及全站跨系统综合故障排查 SOP。

一、 本地 EMS 服务器、SCADA 后台与控制策略维保 SOP

EMS(能量管理系统)负责全站功率调度、策略计算、数据存储以及与电网调度主站的实时交互。

(一)EMS 服务器双机热备与冗余切换测试 SOP

主/备服务器状态检查:查看主服务器(Master)与备用服务器(Slave)运行状态,确认双机心跳线(Heartbeat Cable)连通正常,数据库实时冗余镜像同步无延迟。

双机热备自动切换测试 SOP(每半年执行):在电站平稳运行状态下,人为拔掉主服务器网线或切断主服务器电源(模拟主机突发故障)。备用服务器必须在 < 1.0s 内自动接管全站控制权,SCADA 监控画面无卡顿崩溃,正在执行的充放电策略不中断。

(二)数据库存储管理与性能优化

数据库检查:检查本地时序数据库(如 InfluxDB、TDengine 或 MySQL)磁盘分区空间。磁盘剩余空间必须 > 30%。

数据归档规范:全站秒级采样数据本地须保存 ≥ 90 天;分钟级历史数据及告警日志须保存 ≥ 3 年。每季度须执行一次数据库索引重建与冷数据离线备份。

(三)核心控制策略执行与精度核算 SOP

峰谷套利(Peak-Shaving)策略:核对 EMS 策略引擎内部的充放电时间表,与当地电网最新的峰谷平电价时段(如谷时充电:23:0007:00,高峰放电:11:0015:00、18:00~21:00)100% 对齐。

AGC(自动发电控制)响应与跟踪精度:当接收到电网调度下发的 AGC 功率调节指令时,EMS 须在 < 1.0s 内完成指令分解并下发至各 PCS。全站实际输出功率对 AGC 指令的跟踪精度须 ≥ 99.0%。

AVC(自动电压控制)无功调节:根据网侧节点电压波动,自动控制 PCS 输出无功功率,将 35kV 母线电压偏差控制在 ± 2.5% 额定电压范围内。

二、 微机继电保护装置、微电网控制器与防逆流装置维保 SOP

二次保护设备是防止电气故障扩大化、保障设备与人身安全的“最后一道屏障”。

(一)微机继电保护装置自检与定值单复核 SOP

保护装置面板自检:检查高压开关柜及主控室保护屏上的微机保护装置(过流保护、速断保护、零序过压保护、差动保护)。装置“运行”绿灯常亮,“告警”或“异常”黄红灯灭。

保护定值单复核 SOP(每年或定值变更时):导出保护装置内部当前的整定值(Protection Settings),与电网调度部门下发并盖章的《继电保护整定通知单》逐字逐句核对,电流/电压定值误差须 0.0%(绝对一致)。

(二)微电网控制器并/离网无缝切换与黑启动(Black Start)

并/离网无缝切换(Seamless Transfer):在微电网或分布式储能场景下,当检测到电网跌落或停电时,微电网控制器须控制静态开关(STS)在 < 20ms 内断开并网点,同时控制主储能 PCS 由 PQ 模式切换为 V/F(电压/频率)模式,确保重要负荷不掉电。

黑启动(Black Start)控制逻辑:在全网大面积停电时,依靠储能系统自身电池及站用直流屏启动,建立微电网电压。

步骤:启动站用 UPS ➔ 激活主控 BMS 及 PCS ➔ PCS 在 V/F 模式下建立 380V/690V 交流电压 ➔ 充压升压变压器 ➔ 逐级拉合重要负荷断路器。

(三)站用防逆流保护装置

当储能/光伏系统禁止向公用电网倒送电时,防逆流保护装置实时监测并网点电流。当检测到逆向功率达到设定阈值(如设为 10 kW)时,防逆流装置须在 < 200ms 内向 EMS 及 PCS 发送降额或切机指令。

三、 站用通信网络、精确时钟同步与远动 RTU“四遥”维保 SOP

(一)工业光环网交换机与丢包率测试

光纤自愈环网(RSTP/ERPS)自愈测试:人为拔掉环网中某一根光纤(模拟光缆中断),环网须在 < 20ms 内完成自愈重构,通讯不中断。

网络丢包率与延迟测试:在主控室后台使用网络分析仪对全站各 BMS、PCS 及网关进行 Ping 测试。全站局域网网络延迟须 < 5ms,24 小时连续测试数据包丢包率须 < 0.01%。

(二)全站精确时钟同步(NTP / IEEE 1588 PTP)

时钟源结合主控室卫星对时接收机(GPS / 北斗双模对时源)。全站所有服务器、BMS 簇控制器、PCS 控制板及继电保护装置的时钟误差须 ≤ 1.0 ms,确保发生故障时 SOE 事故顺序记录的时间戳完全吻合。

(三)远动 RTU 与调度网关“四遥”测试 SOP

与电网调度主站通过 IEC 60870-5-104 协议进行通讯,定期进行“四遥”功能核对:

遥测 (YC):核对全站总有功/无功功率、母线电压、簇总电流等模拟量,误差 ≤ ± 0.5%;

遥信 (YX):测试开关断路器分合闸状态、故障告警信号,变位响应时间 < 100ms;

遥控 (YK):测试调度远程控制主断路器分合闸功能,逻辑闭锁安全正确;

遥调 (YT):测试调度远程设定 PCS 有功/无功功率定值。

四、 全站典型跨系统综合故障排查与恢复 SOP(代码级诊断)

当电站发生跨越电池、PCS、温控与网侧的复合型故障时,运维团队必须在主控室统一指挥,按以下 SOP 进行排查:

(一)综合故障一:全站绝缘电阻阻抗过低 (Riso Low) 级联排查与定位 SOP

第1步:环境排查。在 EMS 界面检查各电池舱及 PCS 舱的温湿度。若舱内湿度 > 85% RH,启动舱内除湿机强力除湿 2 小时,重新复位测试;若湿度正常(< 70% RH),判定为物理绝缘破损,进入第2步。

第2步:交直流切分。断开 PCS 直流侧主断路器,将 PCS 与电池阵列解列。用 1000V 摇表分别测 PCS 直流母线对地阻抗(若阻抗 < 1MΩ 检查 PCS 直流滤波电容及 IGBT)和电池阵列总母线对地阻抗(若阻抗 < 1MΩ 进入第3步)。

第3步:簇级定位。断开所有电池簇高压箱(BDU)的直流断路器。逐一合上单簇开关,当合上 Cluster N 开关时绝缘监测仪报警阻抗骤降,即可锁定 Cluster N 为故障簇。

第4步:模组定位与修复。运维人员穿戴 PPE 进舱,拔掉 Cluster N 簇内 Pack 之间的串联高压线。用摇表逐个测量 Pack 正/负极对壳体阻抗,找到阻抗 < 1MΩ 的故障 Pack ➔ 打开盖板检查是否有液冷管路渗漏防冻液积水或高压线缆破皮 ➔ 清理漏液 / 包扎更换线缆 ➔ 测试绝缘电阻阻抗 > 10MΩ ➔ 恢复合闸。

(二)综合故障二:电池单体热失控前兆(CO/H2 气体及温度异常)三级响应 SOP

第1步:一级毫秒级自动响应。当 BMS/消防探头检测到单体 CO > 50ppm 或 H2 > 200ppm 且温度变化率 dT/dt ≥ 2.0 ℃/min 时,BMS 自动切断故障簇高压接触器,EMS 下发指令跳开交流/直流主断路器,同时自动启动舱外防爆排风机强力换气。

第2步:二级自动火灾联动。若传感器进一步触发温感/烟感二级火警,自动关闭舱内空调及风道防火阀(Damper),舱外声光报警器倒计时 30 秒后,自动启动电爆阀,释放七氟丙烷气体灭火剂,舱内闷熄静置不少于 20 分钟。

第3步:三级人工处置与后备降温。运维人员穿戴正压式空气呼吸器及防爆服到达上风口 50 米外安全区,用红外热像仪隔墙持续监测电池舱外墙温度。若温度止跌回升(有复燃趋势),启动外接 Pack 级水喷淋/浸没系统对电池进行持续冷却降温。

(三)综合故障三:PCS 与网侧通讯中断或电网过压/欠压/频率异常跳闸排查 SOP

通讯中断:检查主控室光环网交换机对应的 PCS 网口指示灯。若灯灭,测试光纤衰减(须 < 3.0 dB);若光纤正常,重启 PCS 控制板通讯模块。

网侧电压异常跳闸:在主控室调取电能质量分析仪波形。若网侧电压超过 1.1 Un(过压)或低于 0.85 Un(欠压),核对 PCS 的过/欠压保护动作时间。电网电压恢复正常后,在 EMS 界面进行故障复位,按“升压变 ➔ AC 断路器 ➔ DC 接触器 ➔ PCS 待机 ➔ 功率启动”的逻辑恢复运行

光伏电站储能侧二次系统、EMS 与全站综合故障现场巡检签到表

电站名称:_______________________________ 巡检日期:2026 年 ____ 月 ____ 日

巡检区域:主控室二次系统及 EMS 控制后台 巡检负责人:____________________

一、现场设备巡检与测试实测数据记录:

二、 巡检缺陷登记与消缺派工:

三、 巡检签到与复核签字:

巡检工程师(签字):_______________ 监护工程师(签字):_______________

值班长复核(签字):_______________ 签到归档时间:2026 年 ____ 月 ____ 日 ____ 时

Need on-site BESS or PV support?

Contact our Philippines or China hub — response within one business day.

Contact Us