Part 0: Specifications for Acceptance and Preliminary Handover of Photovoltaic Power Station Energy Storage Side Projects (Basic General Outline)

Part 0: Specifications for Acceptance and Preliminary Handover of Photovoltaic Power Station Energy Storage Side Projects (Basic General Outline)

This article stipulates the acceptance conditions, testing standards, defect rectification and delivery list from the completion of energy storage power station construction to the formal handover for operation and maintenance.

1. Specifications for cold static acceptance after construction is completed (unenergized state)

Cold acceptance is carried out before the system is powered on, and the core is to ensure that electrical insulation, mechanical connections and pipeline sealing meet standards.

(1) Insulation resistance and withstand voltage test specifications

DC side (battery cluster to PCS DC bus): Use a 1000V / 2500V insulation megger to measure the insulation resistance between the positive pole and the ground, the negative pole and the ground and between the positive and negative poles.

Eligibility criteria: The insulation resistance value must be ≥ 1000 Ω/V (for 1500V systems, the insulation resistance value must be ≥ 1.5 MΩ).

AC side and step-up transformer: 35kV side winding insulation resistance must be ≥ 1000 MΩ; 400V side insulation resistance must be ≥ 5 MΩ; absorption ratio K = R60s / R15s ≥ 1.3.

Withstand voltage test (Hip-Test): DC circuit applies 1.5 Un + 1000V power frequency withstand voltage for 1 minute, leakage current < 5 mA, no breakdown discharge flashover phenomenon.

(2) Mechanical connection and bolt tightening torque inspection

Use a calibrated torque wrench to conduct 100% bolt tightening inspections on all high-voltage connection copper bars and cable terminals, and spray anti-loosening marking lines:

(3) Lightning protection grounding and pipeline sealing

Grounding grid resistance: Use a grounding resistance tester to measure. The impedance of the main grounding grid of the entire station must be < 0.5 Ω.

Nitrogen-filled air tightness test of liquid-cooled pipelines: Inject dry nitrogen into the pipeline to 0.60 MPa, and let it stand for 30 minutes. The pressure drop must be ≤ 0.005 MPa.

2. Hot charging acceptance and trial operation specifications

(1) Auxiliary power supply and power-on sequence

上电逻辑步骤:

Step 1: Connect the external 380V AC station auxiliary power supply to receive power.

Step 2: Close the auxiliary distribution box circuit breaker in the cabin.

Step 3: Activate the temperature-controlled water pump and explosion-proof fire protection system.

Step 4: Close the BMS control power circuit breaker.

Step 5: Turn on the PCS control power supply and complete network-side synchronization.

Check that the three-phase voltage deviation of the auxiliary power supply must be within ± 5% of the rated voltage range.

(2) BMS and EMS point-to-point (P2P) verification

Extract at least 20% of the battery cells, use a high-precision multimeter to measure the cell voltage and temperature, and compare with the BMS/SCADA interface. The voltage error must be ≤ ± 2 mV, and the temperature error must be ≤ ± 1.0 ℃.

Simulate communication interruption: Unplug a cluster of CAN/network cables, and the EMS must pop up a communication interruption alarm within < 2s.

(3) 72h trial operation assessment standards

The system must undergo a continuous trial run of 72 hours, including at least 3 full-capacity deep charge-discharge cycles (0.5C rate).

Assessment standards: There are no primary or secondary emergency trips during the trial operation, the charge and discharge switching response time is < 100 ms, and the liquid-cooled station charge and discharge efficiency (RTE) must be ≥ 85%.

3. Handover defect order rectification and standard delivery list

(1) A/B/C three-level defect classification and closed-loop processing

Class A defects (fatal defects/strictly prohibited from receiving power): unqualified insulation resistance, failure of fire probe, leakage of liquid cooling pipeline, failure of anti-mislocking ➔ Must be 100% corrected before receiving power.

Class B defects (serious defects/time-limited rectification): communication packet loss of individual BMS nodes, large cell voltage difference (50 ~ 100 mV), slight abnormal noise of the fan ➔ Allowed to operate with limited power and eliminated within 7 days.

Category C defects (minor defects/remaining rectification): scratches on the exterior paint, skewed nameplate, slight flaws in the dustproof tape ➔ Included in the defect elimination plan within 30 days.

(2) Operation and maintenance delivery documents and spare parts handover list

Photovoltaic power station energy storage side project completion acceptance and delivery closed-loop table

Project name: _______________________________ Acceptance date: ____ month ____ day, 2026

Power plant scale: _______MW / __________MWh EPC construction unit: ____________________

1. Cold and hot key indicator acceptance confirmation form:

2. Operation and maintenance delivery documents, drawings and spare parts inventory and handover confirmation form:

3. Deadline for registration and rectification of defects left on site:

4. Three-party signature confirmation and handover seal form:

第0篇:光伏电站储能侧项目验收与前期交接规范(基础总纲篇)

第0篇:光伏电站储能侧项目验收与前期交接规范(基础总纲篇)

本篇规定了储能电站施工完成至正式移交运维阶段的验收条件、测试标准、缺陷整改及交付清单。

一、 施工完工冷态静态验收规范(未带电状态)

冷态验收在系统未带电前进行,核心确保电气绝缘、机械连接与管道密封达标。

(一)绝缘电阻与耐压测试规范

直流侧(电池簇至 PCS 直流母线):使用 1000V / 2500V 绝缘摇表测量正极对地、负极对地及正负极间绝缘电阻。

合格标准:绝缘阻抗值必须 ≥ 1000 Ω/V(对于 1500V 系统,绝缘电阻阻抗值须 ≥ 1.5 MΩ)。

交流侧及升压变压器:35kV 侧绕组绝缘电阻须 ≥ 1000 MΩ;400V 侧绝缘电阻须 ≥ 5 MΩ;吸收比 K = R60s / R15s ≥ 1.3。

耐压测试(Hip-Test):直流回路施加 1.5 Un + 1000V 工频耐压 1 分钟,漏电流 < 5 mA,无击穿放电闪络现象。

(二)机械连接与螺栓紧固力矩检验

使用经过校准的扭力扳手,对所有高压连接铜排、电缆端子进行 100% 螺栓紧固抽检,并喷涂防松标记线:

(三)防雷接地与管路密封

接地网电阻:使用接地电阻测试仪测量,整站主接地网阻抗须 < 0.5 Ω。

液冷管路充氮气密性测试:向管路注入干燥氮气至 0.60 MPa,静置保压 30 分钟,压降须 ≤ 0.005 MPa。

二、 热态带电验收与试运行规范

(一)辅助电源与上电顺序

上电逻辑步骤:

第1步:外接 380V AC 站用辅助电源合闸受电。

第2步:闭合舱内辅助配电箱断路器。

第3步:激活温控水泵及防爆消防系统。

第4步:闭合 BMS 控制电源断路器。

第5步:闭合 PCS 控制电源并完成网侧同步。

检查辅助电源三相电压偏差须在 ± 5% 额定电压范围内。

(二)BMS 与 EMS 点对点(P2P)校验

抽取至少 20% 的电池单体,用高精度万用表实测单体电压、温度,与 BMS/SCADA 界面比对,电压误差须 ≤ ± 2 mV,温度误差须 ≤ ± 1.0 ℃。

模拟通讯中断:拔掉某簇 CAN/网线,EMS 须在 < 2s 内弹出通讯中断告警。

(三)72h 试运行考核标准

系统须进行连续 72 小时试运行,包含至少 3 次全容量深度充放电循环(0.5C 速率)。

考核标准:试运行期间无一、二级紧急跳闸,充放电切换响应时间 < 100 ms,液冷整站充放电效率(RTE)须 ≥ 85%。

三、 交接缺陷单整改与标准交付清单

(一)A/B/C 三级缺陷分类与闭环处置

A 类缺陷(致命缺陷 / 严禁受电):绝缘阻抗不合格、消防探头失效、液冷管路渗漏、防误闭锁失效 ➔ 必须 100% 整改完毕后方可受电。

B 类缺陷(严重缺陷 / 限期整改):BMS 个别节点通讯丢包、单体压差偏大(50 ~ 100 mV)、风机轻微异响 ➔ 允许限功率运行,7 天内消除。

C 类缺陷(轻微缺陷 / 遗留整改):舱外漆面划痕、铭牌歪斜、防尘胶条微瑕 ➔ 列入 30 天内消缺计划。

(二)运维交付文件与备品备件移交清单

光伏电站储能侧工程竣工验收与交付闭环表

项目名称:_______________________________ 验收日期:2026 年 ____ 月 ____ 日

电站规模:_______MW / __________MWh EPC 施工单位:__________________

一、 冷态与热态关键指标验收确认表:

二、 运维交付文件、图纸与备品备件清点移交确认表:

三、 现场遗留缺陷登记与整改限期表:

四、 三方签字确认与交接盖章表: