Integrated panoramic view of PV side equipment topology and inspection SOP training of photovoltaic power stations

Integrated panoramic topology diagram of PV side of photovoltaic power station

Photovoltaic power station PV side topology module

"Photovoltaic power station PV side system equipment level operation and maintenance manual" complete chapter outline

1. Part 0: Project Acceptance and Early Handover Specifications (Basic General Outline)

(1) Cold static acceptance: component open-circuit voltage (Voc) and short-circuit current (Isc) spot test, square array insulation resistance test (≥ 2 MΩ), high-voltage cable and box transformer withstand voltage test, bolt tightening torque review (M6~M16), lightning protection grounding grid impedance (< 4 Ω).

(2) Hot charging acceptance and trial operation: power-on logic sequence, SCADA/inverter P2P sampling verification, 72-hour continuous trial operation assessment (PR performance ratio ≥ 82%).

(3) Delivery documents and spare parts handover: IV curve factory report, infrared hot spot detection report, module/inverter spare parts inventory.

2. Part 1: Photovoltaic modules and array system equipment-level inspection and operation and maintenance SOP (corresponding to topology module 1)

(1) Physical appearance and structural inspection of photovoltaic modules: Inspection of tempered glass bursts, backplane scratches/yellowing/degumming, aluminum alloy frame deformation, and EVA film bubbles.

(2) Component hot spots (Hotspots) and junction box diodes: Infrared thermal imaging camera scans hot spots (temperature difference ΔT ≥ 20 ℃ or local temperature > 80 ℃ must be replaced within 48 hours), junction box bypass diode breakdown and short circuit test.

(3) Crack test (EL) and PID effect prevention: portable EL crack detector operation, PID effect (potential induced decay) diagnosis and Anti-PID nighttime reverse pressure repair SOP (500 ~ 1000V DC).

(4) Component specification cleaning SOP: cleaning period control (cleaning during high temperature periods at noon is strictly prohibited and must be done before sunrise/evening), water quality requirements (pH 6.0~8.0, hardness < 100 mg/L), and water pressure control (< 0.4 MPa).

3. Part 2: Equipment-level inspection and operation and maintenance SOP for photovoltaic brackets and tracking transmission systems (corresponding to topology module 2)

(1) Maintenance of fixed brackets: inspection of anti-corrosion layer of hot-dip galvanized/aluminum alloy brackets, tightening torque of anchor bolts and diagonal brace bolts (M10/M12), settlement and pull-out force test of bracket foundation (cast-in-place piles/bolt piles).

(2) Tracking bracket transmission mechanism (flat single shaft/double shaft): replenishing and replacing the lubricating oil of the reduction gearbox, testing the current of the drive motor, and troubleshooting the jamming of the rotating bearing and coupling.

(3) Tracking electronic control system and strong wind/snow Stow protection: Tracking angle deviation calibration (error < 1.5°), anemometer/snow load sensor linkage strong wind tiling (Stow) protection mode actual measurement (response time < 30 s).

4. Part 3: Photovoltaic inverter (string/centralized) system equipment-level inspection and operation and maintenance SOP (corresponding to topology module three)

(1) Inverter cabin/cabinet dustproof and AC/DC channels: cabin door sealing, air inlet dust screen cleaning/replacement, waterless dry purge SOP (0.20 ~ 0.30 MPa), AC/DC circuit breaker and terminal infrared temperature measurement (< 65 ℃).

(2) IGBT power module and filter circuit: IGBT junction temperature monitoring (full load < 85 ℃), thermal grease overcoating SOP (performed every 3 years, thickness 50~100 μm), DC bus support capacitance/ESR test, filter inductor insulation (≥ 100 MΩ) and noise (< 75 dB).

(3) Sampling, phase locking and adaptive protection: sampling accuracy verification (error ≤ ± 0.5%), anti-islanding protection (Anti-Islanding) measured SOP (≤ 2.0 s cut-off), low/high voltage ride-through (LVRT/HVRT) logic, cooling fan array maintenance.

5. Part 4: Convergence and low-voltage distribution system equipment-level inspection and operation and maintenance SOP (corresponding to topology module four)

(1) AC/DC combiner box cabinet and sampling: The combiner box cabinet is sealed and moisture-proof, Hall string current sampling module (extreme value deviation < 5%), string open circuit voltage (Voc) and operating current (Isc) are tested.

(2) Fuse and Surge Protector (SPD): aR-class fast fuse striker/damage inspection, contact resistance test (≤ 0.1 mΩ); SPD window color (green for normal, red for failure).

(3) MC4 terminals and DC cables are protected against arcing: check for blackening/melting of the MC4 interface (infrared temperature rise < 15°C), and lay the DC cable along the bracket to prevent wear and arcing.

6. Part 5: High-voltage power transformation, distribution and booster station system equipment-level inspection and operation and maintenance SOP (corresponding to topology module 5)

(1) 35kV/10kV high-voltage switch cabinet: SF6 gas pressure (0.35 ~ 0.45 MPa), vacuum circuit breaker spring energy storage, mechanical five-proof locking.

(2) On-site box-type transformer (box-type transformer): oil-immersed box-type transformer oil level gauge/oil color (DGA chromatographic analysis), respirator color-changing silica gel (dark blue); dry-type box-type transformer winding temperature and fan start and stop (100 ℃ start, 130 ℃ alarm, 150 ℃ trip).

(3) High-voltage cable heads and arresters: Infrared temperature measurement of high-voltage cable terminal heads (full load < 70 ℃), partial discharge (PD) ultrasonic testing (< 20 pC), zinc oxide arrester leakage current (< 1.0 mA).

(4) Station main grounding grid: power frequency grounding resistance test (< 4 Ω or < 1 Ω), corrosion inspection and repair welding of grounding flat steel.

7. Part 6: Station environment and station auxiliary system equipment level inspection and operation and maintenance SOP (corresponding to topology module 6)

(1) Station area perimeter and flood control: security infrared radiation, flood control drainage ditch, flood control water retaining board (≥ 500 mm), vegetation cover and clearing.

(2) Station AC power distribution panel and ATS: station variable winding temperature, AC 380V power distribution cabinet bolt tightening and temperature measurement, ATS dual power automatic switching test (< 100 ms).

(3) Station DC panel and UPS: battery cell float voltage (13.50 V ~ 13.80 V), internal resistance test, UPS inverter status check.

(4) Station-level fire control main screen: Fire control main screen (FACP) self-test, smoke/temperature sensor probe test.

8. Part 7: Meteorological Monitoring and Intelligent Environment System Equipment Level Inspection and Operation and Maintenance SOP (corresponding to Topology Module 7)

(1) Total radiation and scattered irradiance meter: cleaning of the pyranometer glass cover, level bubble calibration, desiccant discoloration inspection, and irradiance sampling error calibration (≤ ± 2%).

(2) Ambient temperature and humidity meter and component board temperature sensor: calibration of the shutter ambient temperature and humidity meter, inspection of the attachment status of the patch type component board temperature sensor and temperature measurement accuracy calibration (error ≤ ± 1.0 ℃).

(3) Wind speed and direction meter and sunshine meter: ultrasonic/mechanical wind speed and direction meter rotation sensitivity test, sunshine meter photoelectric sensor cleaning.

9. Part 8: Secondary System and Power Prediction Scheduling SOP (corresponding to Topology Module 8)

(1) Photovoltaic SCADA monitoring background and database: SCADA main/standby server dual-machine hot backup switching (< 1.0 s), time series database disk space and historical curve retrieval.

(2) Photovoltaic power prediction system (short-term/ultra-short-term): Numerical Weather Prediction (NWP) data reception, power prediction model calibration, short-term (072h) and ultra-short-term (04h) prediction accuracy calculation (must be ≥ 85%).

(3) AGC/AVC power control and grid dispatch: AGC automatic power generation control active power derating/power limiting response (response < 1.0 s), AVC reactive power voltage regulation, inverter PR energy efficiency ratio calculation.

(4) Comprehensive troubleshooting SOPs for typical faults: SOPs for segmented positioning of strings with too low insulation resistance (Riso Low) in the entire station, SOPs for overvoltage/undervoltage/overfrequency trip recovery on the grid side of the inverter, and SOPs for zero-current/low-current cascade troubleshooting of photovoltaic array strings.

10. Part 9: Full-cycle inspection and maintenance plan matrix (day/week/month/quarter/year)

(1) Day/week/month/quarter/year five-level inspection and maintenance nodes and technical requirements.

(2) Closed-loop management of full-cycle operation and maintenance of the entire power station.

Full-cycle inspection and maintenance plan matrix for PV side of photovoltaic power station (day/week/month/quarter/year)

This part stipulates the time nodes and operating specifications for daily routine inspections, weekly inspections, monthly maintenance, quarterly inspections and annual overhaul (preventive testing) of all photovoltaic power station equipment throughout the life cycle.

1. Daily inspection plan (daily inspection: SCADA 7×24h online monitoring + on-site inspection)

(1) Daily online SCADA monitoring (completed before 09:00)

Energy efficiency ratio (PR) and power accounting: retrieve the PR (energy efficiency ratio, standard PR ≥ 82%) and power generation capacity of the entire station on the previous day, and analyze the matching between lighting and power generation.

String current dispersion rate monitoring: Comparing the operating current of each string under the same combiner box or inverter, the extreme value dispersion rate must be < 5%. If the current of a certain string is 0 A, immediately issue a work order for troubleshooting.

Meteorological data verification: Check that the weather station irradiance data (W/m²) and plate temperature data are collected normally.

Alarm log retrieval: Search SCADA alarm logs for the past 24 hours to confirm that there are no unreset low insulation or grid-side trip alarms.

(2) Daily on-site inspection (completed before 14:00)

Station area environment and flood control: The security fence is not damaged; the flood control drainage channel is smooth, and the water retaining board (≥ 500 mm) is in place.

Station power and fire main screen: The station transformer makes no abnormal noise; the station DC panel/UPS operates normally; the fire main screen (FACP) operating light is always on.

High-voltage switch and box transformer: The SF6 air pressure of the 35kV switch cabinet is in the green zone (0.35 ~ 0.45 MPa); the oil level of the box transformer is at the 25°C scale, and the respirator silica gel is dark blue.

Inverter and combiner box: The inverter fan runs smoothly and makes no abnormal noise; the combiner box indicator light is normal and the cabinet door is locked tightly.

2. Weekly inspection plan (weekly inspection: on-site in-depth inspection and thermal imaging temperature measurement)

Full-load infrared thermal imaging temperature measurement: Use an infrared thermal imaging camera to scan when there is sufficient sunlight (irradiance ≥ 700 W/m²) and the power station is running at full power:

35kV cable terminal and switch cabinet busbar (maximum temperature must be < 70 ℃, phase-to-phase temperature difference ΔT ≤ 5 ℃);

Inverter AC/DC side circuit breaker and wiring terminals (maximum temperature must be < 65 ℃);

Fuses and DC circuit breaker terminals inside the combiner box (maximum temperature must be < 60°C).

Tracking bracket rotation and Stow protection check: Spot check the flat single-axis/double-axis tracking bracket, the tracking angle error must be < 1.5°; test the strong wind sensor (>17.2 m/s) linkage to the strong wind tiling Stow protection response.

Measurement of DC screen battery float charge voltage: Use a digital multimeter to measure the DC screen lead-acid/gel battery cell float charge voltage. The qualified range is 13.50 V ~ 13.80 V.

3. Monthly inspection and maintenance plan (monthly maintenance: cleaning, water quality analysis and vegetation clearing)

(1) Component dust assessment and standardized cleaning

Dust shielding evaluation: Compare the power generation of components in the clean test area and the contaminated area. When dust obstruction causes power generation loss ≥ 3%, start the cleaning plan.

Standard cleaning execution: avoid high temperature periods at noon (must be carried out before sunrise or in the evening), cleaning water quality pH 6.0~8.0, hardness < 100 mg/L, water pressure < 0.4 MPa.

Weeds and tree blocking and clearing: Cut and clear the weeds and trees in front of the photovoltaic array to ensure that there is no shadow on the array (to avoid causing hot spots).

(2) Cleaning of the inverter dust filter and analysis of liquid cooling water quality

Inverter dust filter: Remove the dust filter from the inlet of the inverter, rinse and dry it completely and then reinstall it.

Liquid-cooled inverter coolant detection: measure the coolant conductivity (must be < 5.0 μS/cm, if ≥ 10.0 μS/cm, the resin filter must be replaced), pH value (7.0 ~ 8.5) and freezing point (≤ -35.0 ℃), and clean the Y-type filter.

4. Quarterly inspection and maintenance plan (quarterly inspection: mechanical fastening, protection measurement and hot spot scanning)

Random test of the tightening torque of the bracket bolts (sampling test rate 20%): Use an insulated torque wrench to randomly test the anchor bolts and diagonal support bolts of the fixed bracket (M10 torque: 3842 N·m, M12 torque: 8085 N·m). After the random test, re-spray the anti-loosening marking line.

Anti-islanding measured SOP: When the inverter is connected to the grid and discharging (50% power), manually disconnect the grid-side analog circuit breaker. The inverter must cut off the AC current output within ≤ 2.0s (actual measurement < 200ms) measured by the oscilloscope.

Full square array infrared hot spot scanning: Use a drone or handheld infrared thermal imaging camera to conduct infrared scanning of the entire station components. Severe hot spot components with a single point temperature higher than the surrounding cell ΔT ≥ 20 ℃ or a local temperature > 80 ℃ must be replaced within 48 hours.

MC4 terminal temperature rise and fuse spot test: spot test the MC4 connector temperature rise (must be < 15 ℃); use a microohmmeter to test the DC fuse contact resistance (must be ≤ 0.1 mΩ).

5. Annual overhaul and preventive test plan (annual maintenance: station-wide power outage overhaul and EL/PID repair)

Waterless dry purging in the cabin/cabinet: Use 0.20 ~ 0.30 MPa dry waterless compressed air (with insulated nozzle hose) to purge the dust accumulated inside the inverter, switch cabinet and combiner box.

Component EL crack testing and Anti-PID night repair:

Randomly test 5% of the components for portable EL (electroluminescence) crack detection to check for cracks and weak soldering;

For square arrays with power attenuation, start the Anti-PID generator at night and apply 500 ~ 1000V DC reverse high voltage for PID repair.

AC/DC high voltage preventive test:

High-voltage switchgear and cable withstand voltage test and ultrasonic partial discharge test (partial discharge pulse < 20 pC);

Box-type transformer oil dissolved gas analysis (DGA chromatography analysis) and winding insulation testing;

Lightning arrester (SPD) continuous leakage current test (must be < 1.0 mA).

Impedance test of the station's main grounding network: Use a different-frequency grounding resistance tester to measure. The power-frequency resistance of the entire station's main grounding network must be < 4.0 Ω (or < 1.0 Ω).

Photovoltaic power prediction model calibration: Calibrate short-term (072h) and ultra-short-term (04h) power prediction models, and the prediction accuracy must be ≥ 85%.

Time synchronization accuracy and network packet loss rate of the whole station: GPS/Beidou time synchronization error of the whole station must be ≤ 1.0 ms; 24-hour Ping test LAN packet loss rate of the whole station must be < 0.01%.

CoreTect power station PV side operation and maintenance engineering department operation and maintenance plan execution table

光伏电站PV侧设备拓扑与巡检 SOP 培训一体化全景图

光伏电站PV侧一体化全景拓扑图

光伏电站PV侧拓扑模块

《光伏电站PV侧系统设备级运维手册》全套篇章大纲

一、 第 0 篇:项目验收与前期交接规范(基础总纲篇)

(一)冷态静态验收:组件开路电压(Voc)与短路电流(Isc)抽测、方阵绝缘阻抗测试(≥ 2 MΩ)、高压电缆与箱变耐压试验、螺栓紧固力矩复核(M6~M16)、防雷接地网阻抗(< 4 Ω)。

(二)热态带电验收与试运行:上电逻辑顺序、SCADA/逆变器 P2P 采样校验、72 小时连续试运行考核(PR 性能比 ≥ 82%)。

(三)交付文件与备件移交:IV 曲线出厂报告、红外热斑检测报告、组件/逆变器备件清点。

二、 第 1 篇:光伏组件与方阵系统设备级巡检与运维 SOP(对应拓扑模块一)

(一)光伏组件物理外观与结构检修:钢化玻璃爆裂、背板划痕/黄变/脱胶、铝合金边框形变、EVA 膜气泡排查。

(二)组件热斑(Hotspots)与接线盒二极管:红外热像仪扫描热斑(温差 ΔT ≥ 20 ℃ 或局部温度 > 80 ℃ 须 48h 内更换)、接线盒旁路二极管击穿短路测试。

(三)隐裂测试 (EL) 与 PID 效应防范:便携式 EL 隐裂检测仪操作、PID 效应(电势诱导衰减)诊断与 Anti-PID 夜间反向加压修复 SOP(500 ~ 1000V DC)。

(四)组件规范清洗 SOP:清洗时段控制(严禁正午高温时段清洗,须在日出前/傍晚进行)、水质要求(pH 6.0~8.0,硬度 < 100 mg/L)、水压控制(< 0.4 MPa)。

三、 第 2 篇:光伏支架与跟踪传动系统设备级巡检与运维 SOP(对应拓扑模块二)

(一)固定支架检修:热镀锌/铝合金支架防腐层检查、地脚螺栓与斜撑螺栓紧固力矩(M10/M12)、支架基础(灌注桩/螺栓桩)沉降与拔出力测试。

(二)跟踪支架传动机构(平单轴/双轴):减速齿轮箱润滑油补充与更换、驱动电机电流测试、旋转轴承与联轴器卡阻排查。

(三)跟踪电控系统与大风/大雪 Stow 保护:跟踪角度偏差校准(误差 < 1.5°)、风速仪/雪载传感器联动大风平铺(Stow)保护模式实测(响应时间 < 30 s)。

四、 第 3 篇:光伏逆变器(组串式/集中式)系统设备级巡检与运维 SOP(对应拓扑模块三)

(一)逆变器舱/柜防尘与交直流通道:舱门密封、进风口防尘网清洗/换新、无水干吹扫 SOP(0.20 ~ 0.30 MPa)、AC/DC 断路器与端子红外测温(< 65 ℃)。

(二)IGBT 功率模组与滤波电路:IGBT 结温监控(满载 < 85 ℃)、导热硅脂复涂 SOP(每3年执行,厚度 50~100 μm)、直流母线支撑电容容量/ESR 测试、滤波电感绝缘(≥ 100 MΩ)与噪音(< 75 dB)。

(三)采样、锁相与适应性保护:采样精度校验(误差 ≤ ± 0.5%)、防孤岛保护(Anti-Islanding)实测 SOP(≤ 2.0 s 切断)、低/高电压穿越(LVRT/HVRT)逻辑、散热风扇阵列维保。

五、 第 4 篇:汇流与低压配电系统设备级巡检与运维 SOP(对应拓扑模块四)

(一)交流/直流汇流箱柜体与采样:汇流箱柜体密封防潮、霍尔组串电流采样模块(极值偏差 < 5%)、组串开路电压(Voc)与运行电流(Isc)测试。

(二)熔断器 (Fuse) 与防雷器 (SPD):aR 级快速熔断器撞针/损坏排查、接触电阻测试(≤ 0.1 mΩ);防雷器视窗颜色(绿色正常,红色失效更换)。

(三)MC4 端子与直流电缆防拉弧:MC4 接口发黑/熔融排查(红外温升 < 15 ℃)、直流电缆沿支架敷设防磨损拉弧。

六、 第 5 篇:高压变配电与升压站系统设备级巡检与运维 SOP(对应拓扑模块五)

(一)35kV/10kV 高压开关柜:SF6 气体压力(0.35 ~ 0.45 MPa)、真空断路器弹簧储能、机械五防闭锁。

(二)就地箱式变压器(箱变):油浸式箱变油位计/油色(DGA 色谱分析)、呼吸器变色硅胶(深蓝色);干式箱变绕组温度与风机启停(100 ℃ 启、130 ℃ 告警、150 ℃ 跳闸)。

(三)高压电缆头与避雷器:高压电缆终端头红外测温(满载 < 70 ℃)、局放(PD)超声波检测(< 20 pC)、氧化锌避雷器泄漏电流(< 1.0 mA)。

(四)站用主接地网:工频接地电阻测试(< 4 Ω 或 < 1 Ω)、接地扁钢腐蚀检修与补焊。

七、 第 6 篇:站区环境与站用辅助系统设备级巡检与运维 SOP(对应拓扑模块六)

(一)站区周界与防汛:安防红外对射、防汛排水沟、防汛挡水板(≥ 500 mm)、草木遮挡清理。

(二)站用 AC 配电屏与 ATS:站用变绕组温度、AC 380V 配电柜螺栓紧固与测温、ATS 双电源自动切换测试(< 100 ms)。

(三)站用直流屏与 UPS:蓄电池单体浮充电压(13.50 V ~ 13.80 V)、内阻测试、UPS 逆变状态检查。

(四)站级消防主屏:消防控制主屏(FACP)自检、烟感/温感探头测试。

八、 第 7 篇:气象监测与智能环境系统设备级巡检与运维 SOP(对应拓扑模块七)

(一)总辐射与散射辐照度仪:总辐射表玻璃罩清洁、水平仪气泡校准、干燥剂变色检视、辐照度采样误差校准(≤ ± 2%)。

(二)环境温湿度计与组件板温传感器:百叶箱环境温湿度计校准、贴片式组件板温传感器贴附状态检视与测温精度校准(误差 ≤ ± 1.0 ℃)。

(三)风速风向仪与日照计:超声波/机械风速风向仪转动灵敏度测试、日照计光电传感器清洁。

九、 第 8 篇:二次系统与功率预测调度 SOP(对应拓扑模块八)

(一)光伏 SCADA 监控后台与数据库:SCADA 主/备服务器双机热备切换(< 1.0 s)、时序数据库磁盘空间与历史曲线调取。

(二)光伏功率预测系统(短期/超短期):数值天气预报(NWP)数据接收、功率预测模型校准、短期(072h)及超短期(04h)预测准确率核算(须 ≥ 85%)。

(三)AGC / AVC 功率控制与电网调度:AGC 自动发电控制有功降额/限电响应(响应 < 1.0 s)、AVC 无功电压调节、逆变器 PR 能效比核算。

(四)典型故障综合排查 SOP:全站绝缘阻抗过低 (Riso Low) 组串分段定位 SOP、逆变器网侧过压/欠压/过频跳闸恢复 SOP、光伏方阵组串零电流/低电流级联排查 SOP。

十、 第 9 篇:全周期巡检与维保计划矩阵篇(日/周/月/季/年)

(一)日/周/月/季/年五级巡检维保节点与技术要求。

(二)全电站全周期运维大闭环管理。

光伏电站PV侧全周期巡检与维保计划矩阵篇(日/周/月/季/年)

本部分规定了光伏电站全站设备在全生命周期内的每日例巡、每周检测、月度维保、季度检修及年度大修(预防性试验)的时间节点与操作规范。

一、 每日巡检计划(日巡:SCADA 7×24h 线上监控 + 现场跑点)

(一)每日线上 SCADA 监控(09:00 前完成)

能效比 (PR) 与功率核算:调取前一日全站 PR(能效比,标准 PR ≥ 82%)及发容量,分析光照与发电量匹配度。

组串电流离散率监控:对比同一汇流箱或逆变器下各组串运行电流,极值离散率须 < 5%。若某组串电流为 0 A,立即下发工单排查。

气象数据核对:检查气象站辐照度数据(W/m²)与板温数据采集正常。

告警日志检索:检索 SCADA 过去 24 小时告警日志,确认无未复位绝缘低或网侧跳闸告警。

(二)每日现场例行巡视(14:00 前完成)

站区环境与防汛:安防围栏无破损;防汛排水沟通畅,挡水板(≥ 500 mm)到位。

站用电与消防主屏:站用变压器无异响;站用直流屏/UPS 运行正常;消防主屏(FACP)运行灯常亮。

高压开关与箱变:35kV 开关柜 SF6 气压处于绿区(0.35 ~ 0.45 MPa);箱变油位在 25 ℃ 刻度,呼吸器硅胶呈深蓝色。

逆变器与汇流箱:逆变器风扇运行平稳无异响;汇流箱指示灯正常,柜门闭锁紧密。

二、 每周巡检计划(周巡:现场深入检测与热成像测温)

满负荷红外热成像测温:在阳光充足(辐照度 ≥ 700 W/m²)、电站满功率运行状态下,使用红外热像仪扫描:

35kV 电缆终端头及开关柜母排(最高温度须 < 70 ℃,相间温差 ΔT ≤ 5 ℃);

逆变器 AC/DC 侧断路器及接线端子(最高温度须 < 65 ℃);

汇流箱内部熔断器与直流断路器端子(最高温度须 < 60 ℃)。

跟踪支架转动与 Stow 保护检查:抽查平单轴/双轴跟踪支架,跟踪角度误差须 < 1.5°;测试大风传感器(> 17.2 m/s)联动大风平铺 Stow 保护响应。

直流屏蓄电池浮充电压测量:使用数字万用表测量站用直流屏铅酸/胶体蓄电池单体浮充电压,合格范围为 13.50 V ~ 13.80 V。

三、 月度巡检与维保计划(月维:清洁、水质分析与草木清理)

(一)组件灰尘度评估与规范清洗

灰尘遮挡评估:对比清洗测试区与污染区组件发电量。当灰尘遮挡导致发电量损失 ≥ 3% 时,启动清洗计划。

规范清洗执行:避开正午高温时段(须在日出前或傍晚进行),清洗水质 pH 6.0~8.0,硬度 < 100 mg/L,水压 < 0.4 MPa。

杂草与树木遮挡清理:对光伏方阵前排杂草及树木进行刈割清理,确保方阵无阴影遮挡(避免引发热斑)。

(二)逆变器防尘网清扫与液冷水质分析

逆变器防尘网:拆下逆变器进风口防尘滤网,冲洗并完全晾干后装回。

液冷逆变器冷却液检测:测量冷却液电导率(须 < 5.0 μS/cm,若 ≥ 10.0 μS/cm 须更换树脂滤芯)、pH 值(7.0 ~ 8.5)及冰点(≤ -35.0 ℃),清洗 Y 型过滤器。

四、 季度巡检与检修计划(季检:力学紧固、保护实测与热斑扫描)

支架螺栓紧固力矩抽测(抽测率 20%):使用绝缘扭力扳手抽测固定支架地脚螺栓及斜撑螺栓(M10 扭矩:3842 N·m,M12 扭矩:8085 N·m),抽测后重新喷涂防松标记线。

防孤岛保护(Anti-Islanding)实测 SOP:在逆变器并网放电(50% 功率)状态下,手动断开网侧模拟断路器,示波器实测逆变器须在 ≤ 2.0s(实测 < 200ms)内切断交流电流输出。

全方阵红外热斑扫描:使用无人机或手持红外热像仪对全站组件进行红外扫描。单点温度高于周围电池片 ΔT ≥ 20 ℃ 或局部温度 > 80 ℃ 的严重热斑组件,须在 48 小时内完成更换。

MC4 端子温升与熔断器抽测:抽测 MC4 接头温升(须 < 15 ℃);使用微欧计测试直流熔断器接触电阻(须 ≤ 0.1 mΩ)。

五、 年度大修与预防性试验计划(年修:全站停电大修与 EL/PID 修复)

舱内/柜内无水干吹扫:使用 0.20 ~ 0.30 MPa 干燥无水压缩空气(配绝缘喷嘴软管),吹扫逆变器、开关柜及汇流箱内部积灰。

组件 EL 隐裂抽测与 Anti-PID 夜间修复:

抽测 5% 组件进行便携式 EL(电致发光)隐裂检测,排查隐裂与虚焊;

对于出现功率衰减的方阵,在夜间启动 Anti-PID 发生器,施加 500 ~ 1000V DC 反向高压进行 PID 修复。

交流/直流高压预防性试验:

高压开关柜及电缆耐压试验与超声波局放测试(局放脉冲 < 20 pC);

箱变变压器油溶解气体分析(DGA 色谱分析)及绕组绝缘测试;

避雷器(SPD)持续泄漏电流测试(须 < 1.0 mA)。

站用主接地网阻抗测试:使用异频接地电阻测试仪测量,整站主接地网工频电阻须 < 4.0 Ω(或 < 1.0 Ω)。

光伏功率预测模型校准:校准短期(072h)及超短期(04h)功率预测模型,预测准确率须 ≥ 85%。

全站对时精度与网路丢包率:全站 GPS/北斗对时误差须 ≤ 1.0 ms;24 小时 Ping 测试全站局域网丢包率须 < 0.01%。

CoreTect 电站PV侧运维工程部运维计划执行表