Part 8: Photovoltaic power station PV side secondary system and power prediction and dispatching

Part 8: PV side secondary system and power prediction and dispatching SOP of photovoltaic power station

This article corresponds to the panoramic topology diagram of the photovoltaic power plant [Module 8: Secondary System and Power Forecasting and Scheduling], which serves as the center for site-wide monitoring and command and dispatching, covering photovoltaic SCADA monitoring background, dual-machine hot standby switching, database management, photovoltaic power prediction system (short-term/ultra-short-term), AGC automatic power generation control, AVC automatic voltage control, PR energy efficiency ratio calculation, microcomputer relay protection setting review, GPS/Beidou full-station time synchronization, and telecontrol RTU Four-remote testing and comprehensive site-wide cross-system troubleshooting SOP.

1. Photovoltaic SCADA monitoring background, database and dual-machine hot standby maintenance SOP

The SCADA system realizes centralized monitoring and remote control of data from the entire station's photovoltaic arrays, inverters, box-type transformers, high-voltage cabinets and weather stations.

(1) SCADA main/standby server dual-machine hot standby switching test SOP

Main/standby server running status check: Check the SCADA main server (Master) and backup server (Slave) running status, confirm that the dual-machine heartbeat cable (Heartbeat Cable) is connected normally, and the database real-time redundant mirror synchronization is without delay.

Dual-machine hot standby automatic switching test SOP (executed every six months):

When the power station is running smoothly, the network cable of the main server is manually unplugged or the power supply of the main server is cut off (simulating a sudden host failure). The standby server must automatically take over control of the entire site within < 1.0s. The SCADA monitoring screen must not freeze or crash, the data must not be lost, and the AGC/AVC strategy being executed must not be interrupted.

(2) Time series database management and performance optimization

Database disk space check: Check local time series database (such as InfluxDB, TDengine or MySQL) disk partition space. Disk remaining space must be > 30%.

Data archiving and backup: Second-level sampling data of the entire site must be saved locally for ≥ 90 days; minute-level historical data and alarm logs must be saved for ≥ 3 years. Database index reconstruction and cold data offline backup must be performed every quarter.

2. Photovoltaic power prediction system (NWP) and AGC/AVC power control SOP

(1) Photovoltaic power prediction system (short-term/ultra-short-term) algorithm calibration

The photovoltaic power prediction system predicts the future output power of the power station based on numerical weather prediction (NWP) data and measured data from weather stations.

NWP weather forecast data reception: Check that the NWP data reception channel is normal and receive the latest irradiance, cloud cover, temperature and wind speed forecast data on time every day.

Forecast accuracy calculation and model calibration:

Evaluation indicator: monthly calculation of power prediction accuracy. The accuracy of short-term power prediction (072h) must be ≥ 85.0%; the accuracy of ultra-short-term power prediction (04h) must be ≥ 90.0% (the accuracy rate meets the standard to avoid power grid dispatch assessment fines).

Model calibration: When the prediction accuracy for three consecutive days is <80%, the photovoltaic array photoelectric conversion attenuation coefficient and the meteorological inversion model must be recalibrated.

(2) AGC/AVC power control and whole-station PR energy efficiency ratio calculation

AGC (automatic power generation control) active power derating and power limit response:

When receiving the AGC power limit instruction issued by the grid dispatcher (for example, the dispatcher requires the power station to limit the power output by 50%), SCADA/EMS must complete the instruction decomposition and issue it to each inverter within < 1.0s. The tracking accuracy of the actual output power of the whole station to the AGC instruction must be ≥ 99.0%.

AVC (automatic voltage control) reactive power regulation:

According to the grid-side node voltage fluctuation, the inverter output reactive power (lead/lag) is automatically controlled to control the 35kV bus voltage deviation within ± 2.5% of the rated voltage range.

Whole-site PR (Performance Ratio) energy efficiency ratio calculation:

Calculate the PR energy efficiency ratio of the entire site every month: PR = (Actual output grid power kWh) / [Nominal installed capacity kWp × (Actual cumulative irradiance kWh/m² / 1 kW/m²)] × 100%. Qualification standard: PR of the entire site must be ≥ 82.0%.

3. Relay protection device, full station time synchronization and telecontrol RTU "four remote" maintenance SOP

(1) Microcomputer relay protection device and anti-backflow system

Review of the relay protection setting list: Check the microcomputer protection devices (overcurrent, quick-break, zero-sequence overvoltage, differential protection) on the high-voltage switch cabinet and the main control room protection screen. Derive the device setting value and check it word for word with the latest setting notice from the power grid dispatching department. The current/voltage setting value error must be 0.0% (absolutely consistent).

Anti-backflow protection device test: In power stations where reverse transmission is prohibited, the anti-backflow protection device is tested. When it is detected that the reverse power reaches the set threshold (such as 10 kW), the anti-backflow device must send a derating or shutdown command to the SCADA and inverter within < 200ms.

(2) Precise clock synchronization of the whole station (NTP / IEEE 1588 PTP)

Check that the satellite time synchronization receiver (GPS/Beidou dual-mode time synchronization source) in the main control room receives normally. The clock error of all servers, inverter control boards, weather stations and relay protection devices in the entire site must be ≤ 1.0 ms to ensure that the timestamps of the sequence of events record (SOE) are completely consistent when an accident occurs.

(3) Telecontrol RTU and dispatch gateway "four remote" test SOP

Communicate with the power grid dispatching main station through the IEC 60870-5-104 protocol, and conduct regular "four remote" function checks:

Telemetry (YC): Check the total active/reactive power of the entire station, 35kV bus voltage, and string current analog quantities, with an error ≤ ± 0.5%;

Remote signaling (YX): Test switch circuit breaker opening and closing status, fault alarm signal, displacement response time < 100ms;

Remote control (YK): Test and dispatch remote control of the main circuit breaker opening and closing function, and the locking logic is safe and correct;

Remote adjustment (YT): Test dispatch remotely issues the active/reactive power settings of the inverter.

4. Typical cross-system troubleshooting and recovery SOP (code-level diagnosis) of the entire photovoltaic power station

(1) Comprehensive fault one: The insulation resistance of the whole station is too low (Riso Low). SOP for troubleshooting of string cascading

Step 1: Environment investigation. Check meteorological data in SCADA interface. If heavy rain and snowfall cause the matrix humidity to be >90% RH, and the insulation recovers after the rain has cleared and the humidity drops, it is determined to be caused by high humidity and condensation. If the humidity is normal but the insulation is low, go to step 2.

Step 2: Separate the inverter side and square array side. Disconnect the DC side input circuit breaker of the inverter. Use a 1000V insulated megger to measure the impedance of the inverter DC input to ground and the photovoltaic array DC bus impedance to ground. If the impedance on the inverter side is low, repair the inverter DC input filter circuit; if the impedance on the array side is low, go to step 3.

Step 3: String plugging and unplugging test (locating the faulty string). Unplug all DC string MC4 plugs under the inverter or combiner box. Use a multimeter/micrometer to test the insulation resistance of each string to ground (positive pole to ground, negative pole to ground). Locks out faulty strings with insulation resistance < 2.0 MΩ (e.g. PV String 08).

Step 4: Check along the line and repair the insulation. On-site inspection along the PV String 08 line ➔ Check whether the MC4 plug is soaked in the bracket water tank, the cable is worn by the sharp edge of the metal bracket to expose copper, or water has entered the junction box ➔ Replace the MC4 terminal/bandage and repair the damaged cable ➔ Retest the string insulation resistance > 10.0 MΩ ➔ Restore closing.

(2) Comprehensive fault two: Overvoltage/undervoltage/overfrequency/off-grid trip recovery SOP on the grid side of the inverter

Step 1: Call up the power quality analyzer waveform to confirm the true voltage and frequency of the power grid at the time of tripping.

Step 2: Check the protection action delay. If the grid-side voltage exceeds 1.1 Un (overvoltage) or is lower than 0.85 Un (undervoltage), confirm that the inverter trips accurately according to the protection delay.

Step 3: After the grid voltage/frequency returns to the normal range, perform a fault reset on the SCADA interface and resume grid-connected power generation according to the logic of "boost transformer ➔ AC circuit breaker ➔ DC side switch ➔ inverter standby ➔ power start".

(3) Comprehensive fault three: PV string zero current/low current (deviation > 10%) cascade troubleshooting SOP

Step 1: The SCADA background compares the current of each string under the same inverter. Locate abnormal strings whose operating current is 0 A or significantly more than 10% lower than other strings.

Step 2: Use a DC clamp meter to re-measure the string current on site. If the current measured by the clamp meter is normal, it is determined that the combiner box/inverter Hall sampling module is damaged and the sampling board must be replaced.

Step 3: If the measured current is indeed 0 A, test the string open circuit voltage Voc. If Voc is 0 V, check whether the DC fast fuse (Fuse) is blown or the MC4 plug is tripped and disconnected; if Voc is lower than 1/3 or 1/2, check whether the bypass diode in the component junction box is broken down and short-circuited or the component has severe hot spots/cracks, and replace the faulty component or diode.

Photovoltaic power station PV side secondary system and power prediction dispatch equipment level inspection and operation and maintenance sign-in form

Power station name: _______________________________ Inspection date: ____ month ____ day, 2026

Inspection area: Main control room secondary system and SCADA backend Inspection person in charge: ____________________

Field equipment inspection and test data recording

2. Registration of inspection defects and dispatch of work to eliminate defects

3. Inspection sign-in and review signature

Inspection Engineer (Signature): _______________ Supervision Engineer (Signature): _______________

Review (signature) of the shift leader: _______________ Sign-in and filing time: ____ hour on ____ month ____ day 2026

第8篇:光伏电站PV侧二次系统与功率预测调度

第8篇:光伏电站PV侧二次系统与功率预测调度 SOP

本篇对应光伏电站全景拓扑图【模块八:二次系统与功率预测调度】,作为全站监控与指挥调度中枢,涵盖光伏 SCADA 监控后台、双机热备切换、数据库管理、光伏功率预测系统(短期/超短期)、AGC 自动发电控制、AVC 自动电压控制、PR 能效比核算、微机继电保护定值复核、GPS/北斗全站对时、远动 RTU 四遥测试以及全站跨系统综合故障排查 SOP。

一、 光伏 SCADA 监控后台、数据库与双机热备维保 SOP

SCADA 系统实现全站光伏方阵、逆变器、箱变、高压柜及气象站数据的集中监视与远程控制。

(一)SCADA 主/备服务器双机热备切换测试 SOP

主/备服务器运行状态检查:查看 SCADA 主服务器(Master)与备用服务器(Slave)运行状态,确认双机心跳线(Heartbeat Cable)连通正常,数据库实时冗余镜像同步无延迟。

双机热备自动切换测试 SOP(每半年执行):

在电站平稳运行状态下,人为拔掉主服务器网线或切断主服务器电源(模拟主机突发故障)。备用服务器必须在 < 1.0s 内自动接管全站控制权,SCADA 监控画面无卡顿崩溃,数据无丢失,正在执行的 AGC/AVC 策略不中断。

(二)时序数据库管理与性能优化

数据库磁盘空间检查:检查本地时序数据库(如 InfluxDB、TDengine 或 MySQL)磁盘分区空间。磁盘剩余空间必须 > 30%。

数据归档与备份:全站秒级采样数据本地须保存 ≥ 90 天;分钟级历史数据及告警日志须保存 ≥ 3 年。每季度须执行一次数据库索引重建与冷数据离线备份。

二、 光伏功率预测系统 (NWP) 与 AGC / AVC 功率控制 SOP

(一)光伏功率预测系统(短期 / 超短期)算法校准

光伏功率预测系统根据数值天气预报(NWP)数据及气象站实测数据,预测电站未来输出功率。

NWP 天气预报数据接收:检查 NWP 数据接收通道正常,每日按时接收最新的辐照度、云量、气温及风速预测数据。

预测准确率核算与模型校准:

评估指标:每月核算功率预测准确率。短期功率预测(072h)准确率须 ≥ 85.0%;超短期功率预测(04h)准确率须 ≥ 90.0%(准确率达标避免电网调度考核罚款)。

模型校准:当连续 3 天预测准确率 < 80% 时,须重新校准光伏方阵光电转换衰减系数及气象反演模型。

(二)AGC / AVC 功率控制与全站 PR 能效比核算

AGC(自动发电控制)有功降额与限电响应:

当接收到电网调度下发的 AGC 功率限额指令(如调度要求电站限功率输出 50%)时,SCADA/EMS 须在 < 1.0s 内完成指令分解并下发至各逆变器。全站实际输出功率对 AGC 指令的跟踪精度须 ≥ 99.0%。

AVC(自动电压控制)无功调节:

根据网侧节点电压波动,自动控制逆变器输出无功功率(超前/滞后),将 35kV 母线电压偏差控制在 ± 2.5% 额定电压范围内。

全站 PR(Performance Ratio)能效比核算:

每月核算全站 PR 能效比:PR = (实际输出上网电量 kWh) / [标称装机容量 kWp × (实际累积辐照度 kWh/m² / 1 kW/m²)] × 100%。合格标准全站 PR 须 ≥ 82.0%。

三、 继电保护装置、全站对时与远动 RTU “四遥”维保 SOP

(一)微机继电保护装置与防逆流系统

继电保护定值单复核:检查高压开关柜及主控室保护屏上的微机保护装置(过流、速断、零序过压、差动 protection)。导出装置整定值,与电网调度部门最新的整定通知单逐字逐句核对,电流/电压定值误差须 0.0%(绝对一致)。

防逆流保护装置测试:在禁止倒送电电站,测试防逆流保护装置。当检测到逆向功率达到设定阈值(如 10 kW)时,防逆流装置须在 < 200ms 内向 SCADA 及逆变器发送降额或切机指令。

(二)全站精确时钟同步(NTP / IEEE 1588 PTP)

检查主控室卫星对时接收机(GPS / 北斗双模对时源)接收正常。全站所有服务器、逆变器控制板、气象站及继电保护装置的时钟误差须 ≤ 1.0 ms,确保发生事故时事故顺序记录(SOE)的时间戳完全吻合。

(三)远动 RTU 与调度网关“四遥”测试 SOP

与电网调度主站通过 IEC 60870-5-104 协议进行通讯,定期进行“四遥”功能核对:

遥测 (YC):核对全站总有功/无功功率、35kV 母线电压、组串电流模拟量,误差 ≤ ± 0.5%;

遥信 (YX):测试开关断路器分合闸状态、故障告警信号,变位响应时间 < 100ms;

遥控 (YK):测试调度远程控制主断路器分合闸功能,闭锁逻辑安全正确;

遥调 (YT):测试调度远程下发逆变器有功/无功功率定值。

四、 光伏电站全站典型跨系统故障排查与恢复 SOP(代码级诊断)

(一)综合故障一:全站绝缘电阻阻抗过低 (Riso Low) 组串级联排查 SOP

第1步:环境排查。在 SCADA 界面检查气象数据。若天气大雨降雪导致方阵湿度 > 90% RH,且等雨过天晴湿度下降后绝缘恢复,判定为高湿凝露引发。若湿度正常但绝缘低,进入第2步。

第2步:逆变器侧与方阵侧切分。断开逆变器直流侧输入断路器。用 1000V 绝缘摇表分别测量逆变器 DC 输入端对地阻抗和光伏方阵直流母线对地阻抗。若逆变器侧阻抗低,检修逆变器直流输入滤波电路;若方阵侧阻抗低,进入第3步。

第3步:组串拔插测试(定位故障组串)。拔出逆变器或汇流箱下方的所有 DC 组串 MC4 插头。使用万用表/摇表对每路组串进行对地绝缘电阻测试(正极对地、负极对地)。锁定绝缘电阻阻抗 < 2.0 MΩ 的故障组串(如 PV String 08)。

第4步:沿线排查与绝缘修复。沿着 PV String 08 线路现场排查 ➔ 检查 MC4 插头是否浸泡在支架积水槽中,电缆被金属支架锐利边缘磨损破皮露铜,或接线盒进水 ➔ 更换 MC4 端子 / 包扎修复破损电缆 ➔ 重新测试组串绝缘阻抗 > 10.0 MΩ ➔ 恢复合闸。

(二)综合故障二:逆变器网侧过压/欠压/过频/脱网跳闸恢复 SOP

第1步:调取电能质量分析仪波形,确认跳闸时电网真实电压与频率。

第2步:核对保护动作延时。若网侧电压超过 1.1 Un(过压)或低于 0.85 Un(欠压),确认逆变器按保护延时准确跳闸。

第3步:电网电压/频率恢复正常范围后,在 SCADA 界面进行故障复位(Fault Reset),按“升压变 ➔ 交流断路器 ➔ 直流侧开关 ➔ 逆变器待机 ➔ 功率启动”的逻辑恢复并网发电。

(三)综合故障三:光伏组串零电流 / 低电流(偏离 > 10%)级联排查 SOP

第1步:SCADA 后台对比同一逆变器下各个组串的电流。定位运行电流为 0 A 或显著低于其他组串 10% 以上的异常组串。

第2步:现场使用直流钳形表复测该组串电流。若钳形表实测电流正常,判定为汇流箱/逆变器霍尔采样模块损坏,更换采样板。

第3步:若实测电流确实为 0 A,测试组串开路电压 Voc。若 Voc 为 0 V,排查直流快速熔断器(Fuse)是否烧断或 MC4 插头脱扣断路;若 Voc 偏低 1/3 或 1/2,排查组件接线盒旁路二极管击穿短路或组件严重热斑/隐裂,更换故障组件或二极管。

光伏电站PV侧二次系统与功率预测调度设备级巡检与运维签到表

电站名称:_______________________________ 巡检日期:2026 年 ____ 月 ____ 日

巡检区域: 主控室二次系统及 SCADA 后台 巡检负责人:____________________

现场设备巡检与测试实测数据记录

二、巡检缺陷登记与消缺派工

三、 巡检签到与复核签字

巡检工程师 (签字):_______________ 监护工程师 (签字):_______________

值班长复核 (签字):_______________ 签到归档时间:2026 年 ____ 月 ____ 日 ____ 时