Part 5: Equipment-level inspection and operation and maintenance of the high-voltage transformation, distribution and booster station system on the PV side of the photovoltaic power station

Part 5: Equipment-level inspection and operation and maintenance SOP of the high-voltage transformation, distribution and booster station system on the PV side of the photovoltaic power station

This article corresponds to the panoramic topology diagram of the photovoltaic power station [Module 5: High-voltage Transformer, Distribution and Booster Station System], which is the final channel for high-voltage boost and grid connection of the power station, covering 10kV/35kV high-voltage switch cabinet, local step-up box-type transformer (box transformer), high-voltage cable head infrared temperature measurement and partial discharge (PD) detection, zinc oxide high-voltage arrester (SPD) and maintenance of the main grounding network for the station.

1. 10kV / 35kV high-voltage switchgear maintenance and inspection SOP

The high-voltage switch cabinet (SF6 ring main unit or central vacuum switch cabinet) is responsible for controlling, protecting and isolating the 35kV / 10kV high-voltage AC main circuit of the entire station.

(1) SF6 gas pressure and air tightness inspection

SF6 gas pressure gauge inspection: Check the switch cabinet SF6 gas pressure gauge pointer. The air pressure must be in the green qualified area (usually 0.35 ~ 0.45 MPa). If the pointer drops to the red zone (low voltage lockout), it is strictly forbidden to force the opening and closing operations. Nitrogen/gas must be filled and the leakage point must be checked.

Air tightness check: Use a portable SF6 gas leak detector close to the welding seam of the switch cabinet gas chamber and the gas valve pipeline. The detection rate of air leakage must be < 1%/year.

(2) Vacuum circuit breaker, energy storage mechanism and three-phase asynchronous

Circuit breaker position and energy storage status: Confirm that the opening/closing position indicator light and mechanical mark are correct; check that the energy storage time of the electric energy storage mechanism is < 10s, and the sign shows "Storeed".

Three-phase closing asynchronous test: During power outage and overhaul, use a switching characteristic tester to measure the three-phase closing asynchronous test of the vacuum circuit breaker, which must be < 1.0 ms; the closing bounce time must be < 2.0 ms.

(3) Handcart position, mechanical five-proof locking and live display

Handcart position and heavy-duty plug: Check that the circuit breaker handcart is in the "working position" or "test position", the handcart locking pin is in place, and the secondary heavy-load plug is locked firmly.

Mechanical five-proof locking verification: Confirm that when the circuit breaker is in the closed state, the grounding knife switch and cabinet door are mechanically locked and cannot be forcibly opened.

High-voltage live indicator: The three-phase indicators L1, L2, and L3 of the high-voltage live indicator light up normally, and there is no missing phase on the high-voltage side.

2. Maintenance SOP for on-site step-up box-type transformer (box-type transformer)

The box-type transformer steps up the low-voltage AC power (such as 800V) output by the inverter to 10kV or 35kV and then sends it to the high-voltage switch station. Divided into oil-immersed transformers and dry-type transformers.

(1) Inspection specifications for oil-immersed box-type transformers

Oil level gauge and oil color check:

Observe the indication of the oil level gauge. The oil level must be between the scale lines corresponding to the ambient temperature (such as the 25°C scale line).

The transformer oil must be transparent and light yellow in color. If the oil is black, dark or turbid, it means that partial discharge has occurred internally or the insulating oil is carbonized, and a sample must be taken for oil dissolved gas analysis (DGA chromatography analysis).

Respirator (moisture absorber) silicone inspection:

Check that there is oil in the sealed oil cup at the bottom of the moisture absorber, and the discolored silica gel particles in the tank are dark blue. If > 2/3 of the silica gel turns pink or white, it means that the silica gel is saturated with moisture and must be replaced with dry silica gel immediately.

Casing and leakage inspection: Check that the high and low voltage porcelain casings have no cracks or traces of discharge; check that there is no oil leakage in the box radiator and high-pressure valves.

(2) Inspection specifications for dry box-type transformers

Winding temperature control: Check the three-phase winding temperature of the temperature controller. Under natural air cooling, the winding temperature must be < 90.0 ℃; when the temperature ≥ 100.0 ℃, the forced air cooling fan starts automatically; when the temperature ≥ 130.0 ℃, an over-temperature alarm is triggered; when it reaches 150.0 ℃, a trip is triggered.

3. Maintenance SOP for high-voltage busbars, cable heads and high-voltage lightning arresters (SPD)

(1) Infrared temperature measurement and partial discharge (PD) detection of high-voltage cable heads

Infrared thermal imaging temperature measurement: When the power station is running at full power, infrared temperature measurement is performed on the intermediate head and terminal head of the 35kV cable. The maximum temperature of the bushing and terminal block must be < 70.0 ℃, and the temperature difference between phases ΔT ≤ 5.0 ℃.

Ultrasonic partial discharge (PD) detection: Use a portable partial discharge tester close to the high-voltage cable head and switch cabinet busbar. The partial discharge pulse must be <20 pC, and there should be no obvious high-frequency corona discharge sound. If the partial discharge value is > 50 pC, a power outage withstand voltage test and a redo of the cable head must be arranged.

(2) Maintenance of zinc oxide high-voltage arrester (SPD)

Appearance and counter records: Check that the porcelain sleeve/composite insulation sleeve of the lightning arrester is free of damage and flashover; record the lightning strike action counter reading.

Continuous leakage current test: Use a leakage current tester to measure, the continuous leakage current of the arrester must be < 1.0 mA. If the leakage current exceeds the standard, it means that the valve plate is old and damp, and must be replaced after a power outage.

4. Station main grounding grid and equipotential grounding test SOP

Grounding network power frequency resistance test (annual):

Testing tools: Large-scale multi-frequency ground resistance tester.

Standard: The power frequency grounding resistance of the main grounding network of the power station must be < 4.0 Ω (large booster stations/high-salt areas must be < 1.0 Ω).

SOP for anti-corrosion repair welding of ground lap and flat steel:

Check that the flat steel (or copper cable) overlap between the booster transformer casing, high-voltage cabinet base, arrester grounding terminal and main grounding grid is not loose.

Check for corrosion 0.5 meters underground on the grounded flat steel. If the cross-section corrosion rate is >30%, galvanized flat steel of the same specifications must be repaired (the length of double-sided lap welding must be ≥ 2 times the width of the flat steel), and the welds must be repaired with anti-corrosion asphalt paint.

Equipment-level inspection and operation and maintenance sign-in form for the high-voltage transformation, distribution and booster station system on the PV side of the photovoltaic power station

Power station name: _______________________________ Inspection date: ____ month ____ day, 2026

Inspection area: high-voltage switch room and booster box area Inspection person in charge: ____________________

Field equipment inspection and test data recording

Inspection defect registration and defect elimination dispatch

3. Inspection sign-in and review signature

Inspection Engineer (Signature): _______________ Supervision Engineer (Signature): _______________

Review (signature) of the shift leader: _______________ Sign-in and filing time: ____ hour on ____ month ____ day 2026

第5篇:光伏电站PV侧高压变配电与升压站系统设备级巡检与运维

第5篇:光伏电站PV侧高压变配电与升压站系统设备级巡检与运维 SOP

本篇对应光伏电站全景拓扑图【模块五:高压变配电与升压站系统】,作为电站高压升压与并网的最终通道,涵盖 10kV/35kV 高压开关柜、就地升压箱式变压器(箱变)、高压电缆头红外测温与局放(PD)检测、氧化锌高压避雷器(SPD)及站用主接地网维保。

一、 10kV / 35kV 高压开关柜检修与巡检 SOP

高压开关柜(SF6 环网柜或中置式真空开关柜)负责控制、保护和隔离整站的 35kV / 10kV 高压交流主回路。

(一)SF6 气体压力与气密性检查

SF6 气体压力表检查:检查开关柜 SF6 气体压力表指针。气压须处于绿色合格区域(通常为 0.35 ~ 0.45 MPa)。若指针降至红区(低压闭锁),严禁强行进行分合闸操作,须充氮/充气并排查漏气点。

气密性排查:使用便携式 SF6 气体检漏仪贴近开关柜气室焊缝及气阀管路。检测漏气速率须 < 1% / 年。

(二)真空断路器、储能机构与三相不同期性

断路器位置与储能状态:确认分/合闸位置指示灯与机械标志正确;检查电动储能机构储能时间 < 10s,标牌显示“已储能(Stored)”。

三相合闸不同期性测试:停电大修时,使用开关特性测试仪测量真空断路器三相合闸不同期性,须 < 1.0 ms;合闸弹跳时间须 < 2.0 ms。

(三)手车位置、机械五防闭锁与带电显示器

手车位置与重载插头:检查断路器手车处于“工作位置”或“试验位置”,手车锁定销扣到位,二次重载插头锁定牢固。

机械五防闭锁校验:确认断路器在合闸状态时,接地刀闸及柜门被机械锁死,无法强制开启。

高压带电显示器:高压带电显示器 L1、L2、L3 三相指示灯发光正常,高压侧无缺相。

二、 就地升压箱式变压器(箱变)维保 SOP

箱变将逆变器输出的低压交流电(如 800V)升压至 10kV 或 35kV 后送入高压开关站。分为油浸式变压器与干式变压器。

(一)油浸式箱变巡检规范

油位计与油色检查:

观察油位计指示,油位须处于环境温度对应的刻度线之间(如 25 ℃ 刻度线)。

变压器油色必须呈现透明淡黄色。若油色发黑发暗或浑浊,说明内部发生过局部放电或绝缘油碳化,须抽样做油溶解气体分析(DGA 色谱分析)。

呼吸器(吸湿器)硅胶检查:

检查吸湿器底部的密封油杯有油,罐内变色硅胶颗粒呈深蓝色。若硅胶有 > 2/3 变为粉红色或白色,说明硅胶已吸湿饱和,必须立即更换干燥硅胶。

套管与渗漏排查:检查高低压瓷套管无裂纹、无放电痕迹;检查箱体散热片、高压阀门无渗油漏油。

(二)干式箱变巡检规范

绕组温度控制:检查温控仪三相绕组温度。自然风冷下,绕组温度须 < 90.0 ℃;当温度 ≥ 100.0 ℃ 时,强迫风冷风机自动启动;当温度 ≥ 130.0 ℃ 时,超温报警;达到 150.0 ℃ 时触发跳闸。

三、 高压母排、电缆头与高压避雷器(SPD)检修 SOP

(一)高压电缆头红外测温与局放(PD)检测

红外热成像测温:在电站满功率运行状态下,对 35kV 电缆中间头及终端头进行红外测温。套管及接线端子最高温度须 < 70.0 ℃,相间温差 ΔT ≤ 5.0 ℃。

超声波局部放电(PD)检测:使用便携式局放测试仪贴近高压电缆头与开关柜母线。局放脉冲须 < 20 pC,无明显高频电晕放电声。若局放值 > 50 pC,须安排停电耐压试验及电缆头重做。

(二)氧化锌高压避雷器(SPD)检修

外观与计数器记录:检查避雷器瓷套/复合绝缘套无破损闪络;记录雷击动作计数器读数。

持续泄漏电流测试:使用泄漏电流测试仪测量,避雷器持续泄漏电流须 < 1.0 mA。若泄漏电流超标,说明阀片老化受潮,须停电更换。

四、 站用主接地网与等电位接地测试 SOP

接地网工频电阻测试(年度):

测试工具:大型异频接地电阻测试仪。

标准:电站主接地网工频接地电阻须 < 4.0 Ω(大型升压站/高含盐地区须 < 1.0 Ω)。

接地搭接与扁钢防腐补焊 SOP:

检查升压变外壳、高压柜底座、避雷器接地端与主接地网的扁钢(或铜缆)搭接无松动。

检查接地扁钢地下 0.5 米处的腐蚀情况。若截面腐蚀率 > 30%,必须补焊同规格镀锌扁钢(双面搭接焊接长度须 ≥ 2 倍扁钢宽度),焊缝出补刷防腐沥青漆。

光伏电站PV侧高压变配电与升压站系统设备级巡检与运维签到表

电站名称:_______________________________ 巡检日期:2026 年 ____ 月 ____ 日

巡检区域:高压开关室和升压箱变区 巡检负责人:____________________

现场设备巡检与测试实测数据记录

巡检缺陷登记与消缺派工

三、 巡检签到与复核签字

巡检工程师 (签字):_______________ 监护工程师 (签字):_______________

值班长复核 (签字):_______________ 签到归档时间:2026 年 ____ 月 ____ 日 ____ 时