Part 3: Equipment-level inspection and operation and maintenance of PV side inverter (DC-AC) system of photovoltaic power station

Part 3: Equipment-level inspection and operation and maintenance SOP of PV side inverter (DC/AC) system of photovoltaic power station

This article corresponds to the panoramic topology diagram of the photovoltaic power plant [Module 3: Photovoltaic inverter system], as the core of DC/AC energy conversion, covering the appearance of string inverters and centralized inverter cabins, dust-proof purging, AC and DC incoming circuit breakers and terminal temperature rise, IGBT Power module and thermal grease overcoating, DC support capacitor (DC-Link), filter inductor, sampling accuracy calibration, actual measurement of anti-islanding protection (Anti-Islanding) and low/high voltage ride through (LVRT/HVRT) protection logic.

1. Inverter appearance protection, dustproof ventilation and AC/DC switch maintenance SOP

The photovoltaic inverter is responsible for inverting the DC power generated by the components into low-voltage AC power. It contains high-frequency switching power electronic devices and control cards, and is extremely sensitive to ambient temperature, humidity and dust accumulation.

(1) Cabin/cabinet environment and sealing and anti-condensation control

Cabin temperature and humidity control: Check the temperature and humidity sensor in the inverter cabin/cabinet. The ambient temperature must be controlled between 0 ℃ ~ 40 ℃; the relative humidity must be < 70% RH. The anti-condensation heater must start automatically when the humidity is ≥ 75% RH. Check that the EPDM sealing strips on the cabinet are not aging and falling off, and that the rainproof eaves and drainage channels are clear.

Protection level inspection: Check the cabinet door locking mechanism. The protection level must meet IP54/IP65 standards and there should be no severe vibration or abnormal noise.

(2) Dust filter cleaning and cabin water-free purging SOP

Removing and washing the primary dust filter: Remove the primary filter from the air inlet of the inverter, clean it with an industrial vacuum cleaner or rinse it with neutral detergent. It must be completely dried (moisture content 0%) and then reinstalled.

SOP for dry purging without water in the cabin (implemented for annual power outage and overhaul):

Apply for a power outage, check the power and connect the ground wire. Use a compressed air pump with a high-efficiency water removal filter (the air pressure is strictly controlled at 0.20 ~ 0.30 MPa), equipped with an insulated nozzle hose, and blow out the gaps between the circuit board and the radiator in the order of "top to bottom, from inside to outside". It is strictly prohibited to use a wet cloth with water or an air gun that has not removed water to directly blow the circuit board.

(3) Fastening of AC and DC side circuit breakers and infrared temperature measurement

DC side molded case circuit breaker (DC Breaker): Disassemble the arc extinguishing cover and check that the grid plate has no ablation and deformation; check that the magnetic blowing coil is well insulated and has no burnt smell; test that the shunt release is sensitive.

AC side frame circuit breaker (AC Breaker): Check the energy storage time of the electric energy storage mechanism < 10s; measure the three-phase closing aberration must be < 1.0 ms.

Infrared temperature measurement and tightening torque standards:

After the inverter runs at full power for 30 minutes, use an infrared thermal imaging camera to scan the AC/DC circuit breaker terminals. The operating temperature must be < 65.0 ℃, and the temperature difference between phases/poles ΔT ≤ 5.0 ℃.

Heating treatment SOP: If the terminal temperature > 75.0 ℃ or the temperature difference ΔT ≥ 15.0 ℃, the power must be cut off to disassemble the copper bar, polish the oxide layer with 1000-grit sandpaper and apply 0.1 mm anti-oxidation conductive paste, and then tighten the bolts according to the following table:

2. Equipment-level maintenance SOP for IGBT power modules, DC-Link capacitors and filter inductors

The IGBT module is the core AC-DC conversion semiconductor component inside the inverter that changes the direction and frequency of current.

(1) IGBT power module and thermal grease overcoating SOP

IGBT junction temperature monitoring: Read the IGBT junction temperature of each phase through the inverter’s local screen or SCADA. The junction temperature must be < 85.0 ℃ at full load operation; when the junction temperature reaches 95.0 ℃, the power will be automatically derated by 50%; when the junction temperature reaches 105.0 ℃, an over-temperature trip will be triggered. Check that the driver board triggering fiber is not bent or blocked, and that the driver board indicator light is normal.

Thermal grease recoating SOP (performed every 3 years or when the junction temperature rises > 10.0°C from the initial level):

Step 1: Cut off the power, check the power, and use a special discharge rod to release the residual charge of the DC bus (make sure the DC bus voltage is < 10.0 V).

Step 2: Remove the IGBT module connection cable, and use isopropyl alcohol and a lint-free cloth to completely wipe off the old silicone grease on the bottom plate.

Step 3: Use a scraper or screen printing to evenly apply a layer of new thermal conductive silicone grease (thermal conductivity > 3.0 W/m·K, thickness controlled at 50 ~ 100 μm).

Step 4: Reinstall the module, tighten the bolts twice in a diagonal cross sequence (torque: 3.0 ~ 5.0 N·m), and rewire and receive power.

(2) DC bus support capacitors (DC-Link Capacitors) maintenance

Appearance and leakage inspection: Check that the film/electrolytic capacitor shell has no bulges, leakage, and explosion-proof valve rupture.

Capacity and ESR test: After full discharge after a power outage, use an LCR meter to measure the capacitance capacity. When the capacity attenuates > 10% from the nominal value or the equivalent series resistance (ESR) increases > 50% from the initial value, the entire capacitor must be replaced.

Bus voltage ripple coefficient: Under full power discharge, the DC bus voltage ripple coefficient γ measured using an oscilloscope (AC coupling mode) must be < 1.0%.

(3) Maintenance of DC/AC filter inductor and LC filter

Insulation and temperature rise test: Use a 1000V megger to measure the insulation resistance of the inductor winding to ground. It must be ≥ 100 MΩ; the operating temperature of the inductor must be < 90.0 ℃.

Noise check: Under full load operation, the measured noise at a distance of 1 meter from the cabinet must be < 75 dB. If there is abnormal high-frequency magnetic shock and abnormal sound, the power must be cut off and the core bolts must be retightened (M12 torque: 70 N·m).

3. Secondary control loop, sampling accuracy, phase locking and grid adaptive protection logic measured SOP

(1) Sampling accuracy and zero point calibration

Sampling accuracy verification: Use a power quality analyzer to measure the inverter AC/DC voltage and current, and compare it with the monitoring screen. The voltage sampling error must be ≤ ± 0.5%, and the current sampling error must be ≤ ± 0.5%.

Zero point calibration: If the monitor displays a small current in the standby state (current 0 A), "Hall sensor zero offset automatic calibration" must be performed in the control background.

(2) Measured SOP of phase-locked loop (PLL) and anti-islanding (Anti-Islanding)

Phase-locked loop tracking: When the grid-side frequency fluctuates within the range of 45.0 ~ 55.0 Hz, the phase-locked loop must accurately lock the phase within < 20 ms, with a phase tracking error of < 1°.

Measured SOP for anti-islanding protection:

When the large power grid loses power, the inverter must automatically disconnect the grid-connected switch and stop inversion within ≤ 2.0s to prevent power supply to unplanned islands.

Actual measurement steps: In the grid-connected discharge (50% power) state, manually open the grid-side analog circuit breaker. Oscilloscope monitoring shows that the inverter must cut off the AC current output and report a grid-side power loss alarm within < 200 ms.

(3) Low/high voltage ride through (LVRT/HVRT) and wind turbine maintenance

Low/high voltage ride-through: When the grid-side voltage drops to 20% of the rated voltage, the inverter must ensure that it does not go off-grid within 0.625s and inject dynamic reactive current; when the voltage rises to 130%, it must ensure that it does not go off-grid for 0.50s.

Cooling fan array: Check the Wind Pressure Switch function. When a fan fails and stops spinning, the inverter must report a fan failure within <3s and derate the power by 30%. Fans must be replaced in groups after 20,000 operating hours.

Photovoltaic power station PV side inverter (DC/AC) system equipment level inspection and operation and maintenance sign-in form

Power station name: _______________________________ Inspection date: ____ month ____ day, 2026

Inspection area: Inverter cabin/string inverter area Inspection person in charge: ____________________

Field equipment inspection and test data recording

2. Inspection defect registration and defect elimination dispatch

3. Inspection sign-in and review signature

Inspection Engineer (Signature): _______________ Supervision Engineer (Signature): _______________

Review (signature) of the shift leader: _______________ Sign-in and filing time: ____ hour on ____ month ____ day 2026

第3篇:光伏电站PV侧逆变器(DC-AC)系统设备级巡检与运维

第3篇:光伏电站PV侧逆变器(DC/AC)系统设备级巡检与运维 SOP

本篇对应光伏电站全景拓扑图【模块三:光伏逆变器系统】,作为 DC/AC 能量转换的核心,涵盖组串式逆变器与集中式逆变器舱外观防尘吹扫、交直流进线断路器与端子温升、IGBT 功率模组与导热硅脂复涂、直流支撑电容(DC-Link)、滤波电感、采样精度校准、防孤岛保护(Anti-Islanding)实测以及低/高电压穿越(LVRT/HVRT)保护逻辑。

一、 逆变器外观防护、防尘通风与交直流开关维保 SOP

光伏逆变器负责将组件生成的直流电逆变成低压交流电,内部包含高频开关电力电子器件与控制卡,对环境温湿度及积灰极其敏感。

(一)舱体/柜体环境与密封防凝露控制

舱体温湿度控制:检查逆变器舱内/柜内温湿度传感器。环境温度须控制在 0 ℃ ~ 40 ℃ 之间;相对湿度须 < 70% RH。当湿度 ≥ 75% RH 时,防凝露加热器必须自动启动。检查柜体 EPDM 密封胶条无老化脱落,防雨檐与排水槽畅通。

防护等级检查:检查柜门闭锁机构,防护等级须达到 IP54 / IP65 标准,无剧烈振动异响。

(二)防尘滤网清理与舱内无水吹扫 SOP

初效防尘网拆洗:拆下逆变器进风口初效过滤网,使用工业吸尘器清理或中性洗涤剂冲洗,必须完全晾干(含水率 0%)后装回。

舱内无水干吹扫 SOP(每年停电大修执行):

申请停电、验电并挂接地线。使用带高效除水滤清器的压缩空气泵(气压严格控制在 0.20 ~ 0.30 MPa),配绝缘喷嘴软管,按“自上而下、由内向外”顺序吹扫电路板与散热器缝隙。严禁使用带水湿布或未除水的风枪直接吹扫电路板。

(三)交直流侧断路器与红外测温紧固

直流侧塑壳断路器(DC Breaker):拆开灭弧罩,检查栅片无烧蚀变形;检查磁吹线圈绝缘良好,无发焦异味;测试分励脱扣器动作灵敏。

交流侧框架断路器(AC Breaker):检查电动储能机构储能时间 < 10s;测量三相合闸不同期性须 < 1.0 ms。

红外测温与紧固力矩标准:

在逆变器满功率运行 30 分钟后,使用红外热像仪扫描 AC/DC 断路器接线端子,运行温度须 < 65.0 ℃,相间/极间温差 ΔT ≤ 5.0 ℃。

发热处理 SOP:若接线端子温度 > 75.0 ℃ 或温差 ΔT ≥ 15.0 ℃,须停电拆开铜排,用 1000 目砂纸打磨氧化层并涂抹 0.1 mm 防氧化导电膏后,按下表紧固螺栓:

二、 IGBT 功率模组、DC-Link 电容与滤波电感设备级维保 SOP

IGBT 模块是逆变器内部改变电流方向与频率的核心交直流转换半导体元件。

(一)IGBT 功率模组与导热硅脂复涂 SOP

IGBT 结温监控:通过逆变器本地屏或 SCADA 读取各相 IGBT 结温。满载运行结温须 < 85.0 ℃;结温达 95.0 ℃ 时自动降额 50% 功率;达 105.0 ℃ 时触发过温跳闸。检查驱动板触发光纤无弯折卡阻,驱动板指示灯正常。

导热硅脂复涂 SOP(每3年或结温较初始升高 > 10.0 ℃ 时执行):

第1步:停电、验电并使用专用放电棒释放直流母线残余电荷(确保 DC 母线电压 < 10.0 V)。

第2步:拆下 IGBT 模块连接排线,用异丙醇和无尘布彻底擦除底板旧硅脂。

第3步:用刮刀或丝网印刷均匀涂抹一层新导热硅脂(导热系数 > 3.0 W/m·K,厚度控制在 50 ~ 100 μm)。

第4步:装回模块,按对角交叉顺序分二次紧固螺栓(扭矩:3.0 ~ 5.0 N·m),重新接线受电。

(二)直流母线支撑电容(DC-Link Capacitors)维保

外观与漏液检查:检查薄膜/电解电容外壳无鼓包、无漏液、无防爆阀破裂。

容量与 ESR 测试:停电充份放电后,使用 LCR 表测量电容容量。容量较标称值衰减 > 10% 或等效串联电阻(ESR)较初始值增加 > 50% 时,必须整组更换电容。

母线电压纹波系数:满功率放电下,使用示波器(AC 耦合档)实测直流母线电压纹波系数 γ 须 < 1.0%。

(三)DC/AC 滤波电感与 LC 滤波器检修

绝缘与温升测试:用 1000V 摇表测量电感绕组对地绝缘电阻须 ≥ 100 MΩ;电感运行温度须 < 90.0 ℃。

噪音检查:满负荷运行下,距离柜体 1 米处实测噪音须 < 75 dB。若有异常高频磁震异响,须停电重新紧固铁芯螺栓(M12 扭矩:70 N·m)。

三、 二次控制回路、采样精度、锁相与电网适应性保护逻辑实测 SOP

(一)采样精度与零点校准

采样精度校验:使用电能质量分析仪实测逆变器交流/直流电压和电流,与监控屏比对。电压采样误差须 ≤ ± 0.5%,电流采样误差须 ≤ ± 0.5%。

零点校准:待机状态(电流 0 A)下若监控显示微小电流,须在控制后台执行“霍尔传感器零点偏移自动校准”。

(二)锁相环(PLL)与防孤岛保护(Anti-Islanding)实测 SOP

锁相环跟踪:当网侧频率在 45.0 ~ 55.0 Hz 范围内波动时,锁相环须在 < 20 ms 内精准锁定相位,相位跟踪误差 < 1°。

防孤岛保护实测 SOP:

当大电网失电时,逆变器必须在 ≤ 2.0s 内自动断开并网开关并停止逆变,防止向非计划孤岛供电。

实测步骤:在并网放电(50% 功率)状态下,手动断开网侧模拟断路器。示波器监测显示逆变器须在 < 200 ms 内切断交流电流输出并报网侧失电告警。

(三)低/高电压穿越(LVRT/HVRT)与风机维保

低/高电压穿越:网侧电压跌落至 20% 额定电压时,逆变器须保证 0.625s 内不脱网运行,并注入动态无功电流;电压升高至 130% 时,须保证 0.50s 不脱网。

散热风扇阵列:检查风压开关(Wind Pressure Switch)功能,某个风扇故障停转时,逆变器须在 < 3s 内报风机故障并降额 30% 功率。风扇运行达到 20,000 小时须成组更换。

光伏电站PV侧逆变器(DC/AC)系统设备级巡检与运维签到表

电站名称:_______________________________ 巡检日期:2026 年 ____ 月 ____ 日

巡检区域:逆变器舱 / 组串逆变器区 巡检负责人:____________________

现场设备巡检与测试实测数据记录

二、 巡检缺陷登记与消缺派工

三、 巡检签到与复核签字

巡检工程师 (签字):_______________ 监护工程师 (签字):_______________

值班长复核 (签字):_______________ 签到归档时间:2026 年 ____ 月 ____ 日 ____ 时