Part 2: Equipment-level inspection and operation and maintenance of PV side bracket and tracking transmission system of photovoltaic power station

Part 2: Equipment-level inspection and operation and maintenance SOP of PV side bracket and tracking transmission system of photovoltaic power station

This article corresponds to the panoramic topology diagram of the photovoltaic power station [Module 2: Photovoltaic brackets and tracking transmission system]. As the "bones and muscles" of the photovoltaic array, it covers the anti-corrosion of the metal structure of the fixed bracket, review of anchor bolt torque, foundation settlement and pull-out test, flat single-axis/dual-axis tracking bracket gearbox lubrication, drive motor insulation temperature measurement, tracking controller (TCU) inclination angle calibration, and actual measurement of wind/snow Stow protection mode.

1. Fixed support structure, foundation and anti-corrosion maintenance SOP

Fixed photovoltaic brackets (fixed inclination/adjustable inclination brackets) bear self-weight, wind load and snow load for a long time, and the mechanical stability of the structure is directly related to the safety of the entire station.

(1) Maintenance of metal structure and anti-corrosion layer of fixed bracket

Hot-dip galvanized steel bracket anti-corrosion layer inspection and repair:

Check that there is no red rust or powder on the surface of the hot-dip galvanized steel bracket. Use a coating thickness gauge to measure the thickness of the anti-corrosion galvanized layer: the thickness of the galvanized layer must be ≥ 65 μm in ordinary areas and ≥ 85 μm in high salt spray/seaside/coastal areas.

Anti-corrosion paint touch-up SOP (rust repair treatment): If local red rust is found, use a wire brush and 400-grit sandpaper to remove the floating rust until the copper metallic luster is exposed ➔ Wipe clean with isopropyl alcohol ➔ Apply two coats of cold spray zinc/zinc-rich primer (dry film thickness ≥ 40 μm) ➔ Apply two coats of epoxy polyurethane topcoat (dry film thickness ≥ 40 μm), the total thickness of the anti-corrosion layer must be ≥ 80 μm.

Inspection of aluminum alloy and weathering steel brackets:

Aluminum alloy bracket (aluminum alloy 6063-T6): Check that the thickness of the anodized film must be ≥ 15 μm, and there is no white spot pitting corrosion or electrochemical corrosion caused by contact with different metals.

(2) Standard table for review of bracket bolt tightening torque

Operation and maintenance personnel must use calibrated insulated torque wrenches to randomly inspect the key stress-bearing node bolts of the fixed bracket (sampling inspection rate is not less than 20%), and re-tighten the anti-loosening mark line after tightening:

(3) Settlement and pull-out resistance test of support foundation

Inspection of uneven foundation settlement: Check cast-in-place piles, prefabricated cement piers and spiral steel pile foundations. The uneven settlement of adjacent foundations must be < 10.0 mm; check that the soil around the foundation is not eroded by water flow and that there are no cracked or broken piles.

Sampling test of single pile pullout resistance (annual): Conduct sampling pullout test on the foundation (sampling test rate is not less than 1‰). The foundation pullout resistance must comply with the original engineering design value (for example, the pullout resistance of a single pile must be ≥ 15.0 kN).

2. Tracking bracket transmission mechanism (flat single axis/double axis) equipment level maintenance SOP

The tracking bracket (flat single-axis/oblique single-axis/double-axis tracking) can increase power generation by 10% to 25% by aligning with the sun in real time, but its mechanical transmission part is a high-maintenance area.

(1) Maintenance of reduction gearbox (Gearbox) and slewing bearing (Slew Drive)

Oil/grease replacement and replenishment:

Check the oil level gauge of the reduction gearbox. The oil level must be maintained at 1/2 ~ 2/3. Replenish or replace heavy-duty industrial gear oil (such as CKD 220) annually.

Add extreme pressure lithium grease (NLGI grade 2) to the slewing bearing worm gear every six months until the new grease overflows from the oil drain port.

Gear play and bite clearance inspection:

Use a dial indicator to measure the meshing clearance of the slewing bearing gear. The axial and radial clearance must be < 0.50 mm.

If the gearbox emits a "click-click" sound of violent metal dry friction and impact when the motor is running, it indicates that the gear is seriously worn or collapsed, and the gear box must be stopped and replaced.

(2) Drive motor and transmission spindle bearings

Drive motor electrical and temperature rise inspection:

Measure the operating current of the 24V/48V DC or 380V AC drive motor. The operating current must be within the rated current range of the motor (without overload and jamming).

Use a 500V/1000V megger to measure the insulation resistance of the motor winding to ground. It must be ≥ 5.0 MΩ. The motor operating temperature rise must be < 40.0 ℃.

Universal coupling and transmission spindle:

Check that the universal joint bolts of the connecting rod are not sheared and loose, and that the pins are not falling off; check that the main shaft (main beam) is not twisted and deformed; add anti-rust lubricating oil to the rotating bearing slider.

3. Tracking control system (TCU) angle calibration and Stow protection measured SOP

(1) Tracking controller (TCU) angle calibration and inverse tracking algorithm

Tracking angle deviation calibration:

Use an electronic high-precision inclinometer close to the frame of the component to measure the actual inclination of the bracket and compare it with the angle displayed on the TCU screen or SCADA monitoring.

Angle error standard: The deviation between the actual tilt angle and the theoretical astronomical tilt angle must be < 1.5°. When the angle deviation is ≥ 2.0°, it will cause severe "shadow blocking" of the front and rear components, resulting in a power generation loss of > 5%.

Backtracking algorithm calibration:

One hour after sunrise in the morning and one hour before sunset in the evening, check that the reverse tracking algorithm of the tracking system is running normally, and the bracket automatically returns to a gentler angle to prevent the front bracket from blocking the rear components.

(2) Actual measured SOP (forced safety logic) in Stow protection mode in strong wind/snow

When encountering bad weather, the tracking system must automatically switch to Stow (safety tile) protection mode to prevent huge wind resistance from blowing over the bracket.

Measured SOP in strong wind Stow protection mode:

Test cycle: Test once every six months using simulated wind speed signals.

Actual measurement process and response timing:

Step 1: The wind speed and direction instrument of the weather station detects a gust speed ≥ 17.2 m/s (reaching the level 8 wind warning line).

Step 2: The weather station sends a group wind warning broadcast signal to the TCU tracking controller in milliseconds.

Step 3: The TCU controller forcibly interrupts the current sun tracking logic and starts the drive motor.

Step 4: The tracking bracket must quickly rotate to

Heavy snow/hail snow removal protection mode:

When the snow load sensor detects that the snow load thickness is > 10 cm, the TCU controller drives the bracket to rotate to the maximum inclination angle (such as 50 degrees), and uses gravity to automatically slide and unload the snow to prevent heavy snow from collapsing the bracket.

Anemometer loss safety countdown protection:

When the communication interruption between the TCU controller and the main weather station lasts for more than 5 minutes, the TCU must automatically and forcibly control the bracket to cut into the 0-degree horizontal Stow protection position to prevent loss of control and destruction due to communication interruption during sudden strong winds.

Photovoltaic power station PV side bracket and tracking transmission system equipment level inspection and operation and maintenance sign-in form

Power station name: _______________________________ Inspection date: ____ month ____ day, 2026

Inspection area: Photovoltaic bracket and tracking transmission area Inspection person in charge: ____________________

1. On-site equipment inspection and test data recording

2. Inspection defect registration and defect elimination dispatch

3. Inspection sign-in and review signature

Inspection Engineer (Signature): _______________ Supervision Engineer (Signature): _______________

Review (signature) of the shift leader: _______________ Sign-in and filing time: ____ hour on ____ month ____ day 2026

第2篇:光伏电站PV侧支架与跟踪传动系统设备级巡检与运维

第2篇:光伏电站PV侧支架与跟踪传动系统设备级巡检与运维 SOP

本篇对应光伏电站全景拓扑图【模块二:光伏支架与跟踪传动系统】,作为光伏方阵的“骨骼与筋肉”,涵盖固定支架金属结构防腐、地脚螺栓力矩复核、基础沉降抗拔测试、平单轴/双轴跟踪支架齿轮箱润滑、驱动电机绝缘测温、跟踪控制器(TCU)倾角校准以及大风/大雪 Stow 保护模式实测。

一、 固定支架结构、基础与防腐维保 SOP

固定式光伏支架(固定倾角/可调倾角支架)长期承受自重、风载及雪载,结构机械稳定性直接关系全站安全。

(一)固定支架金属结构与防腐层检修

热镀锌钢支架防腐层检修:

检查热镀锌钢支架表面无红锈粉化。使用涂层测厚仪测量防腐镀锌层厚度:普通地区镀锌层厚度须 ≥ 65 μm,高盐雾/海边/沿海地区须 ≥ 85 μm。

防腐漆补喷 SOP(补锈处理):若发现局部红锈,须用钢丝刷及 400 目砂纸清除浮锈至露铜金属光泽 ➔ 用异丙醇擦净 ➔ 涂刷两道冷喷锌/富锌底漆(干膜厚度 ≥ 40 μm) ➔ 涂刷两道环氧聚氨酯面漆(干膜厚度 ≥ 40 μm),防腐层总厚度须 ≥ 80 μm。

铝合金及耐候钢支架检查:

铝合金支架(铝合金 6063-T6):检查阳极氧化膜厚度须 ≥ 15 μm,无白点点蚀及与不同金属接触引发的电化学腐蚀。

(二)支架螺栓紧固力矩复核标准表

运维人员须使用校准后的绝缘扭力扳手,对固定支架关键受力节点螺栓进行抽检(抽检率不低于 20%),紧固后重打防松标记线:

(三)支架基础沉降与抗拔拉力测试

基础不均匀沉降排查:检查灌注桩、预制水泥墩及螺旋钢桩基础。相邻基础不均匀沉降量须 < 10.0 mm;检查基础周围土壤无水流冲刷淘空、无开裂断桩。

单桩抗拔拉力抽测(年度):对基础进行抽样抗拔测试(抽测率不低于 1‰),基础抗拔力须符合原工程设计值(如单桩抗拔力须 ≥ 15.0 kN)。

二、 跟踪支架传动机构(平单轴/双轴)设备级维保 SOP

跟踪支架(平单轴/斜单轴/双轴跟踪)通过实时对准太阳,可提升 10%~25% 的发电量,但其机械传动部分是高维护率区域。

(一)减速齿轮箱 (Gearbox) 与回转支承 (Slew Drive) 检修

润滑油/润滑脂更换与补充:

检查减速齿轮箱油位计,油位须保持在 1/2 ~ 2/3 处。每年补充或更换重负荷工业齿轮油(如 CKD 220)。

每半年对回转支承蜗轮蜗杆加注极压锂基润滑脂(NLGI 2 级),注油直至新油脂从排油口溢出为止。

齿轮游隙与咬合间隙检查:

用百分表测量回转支承齿轮咬合间隙,轴向及径向游隙须 < 0.50 mm。

若电机运转时齿轮箱发出“咔哒咔哒”剧烈金属干摩擦撞击声,说明齿轮磨损严重或塌陷,须停机更换齿轮箱。

(二)驱动电机与传动主轴轴承

驱动电机电气与温升检修:

测量 24V/48V DC 或 380V AC 驱动电机运行电流,运行电流须在电机额定电流范围内(无过载卡阻)。

用 500V/1000V 摇表测量电机绕组对地绝缘电阻,须 ≥ 5.0 MΩ。电机运行温升须 < 40.0 ℃。

万向联轴器与传动主轴:

检查连杆万向节螺栓无剪断松动,销轴无脱落;检查主轴(主梁)无扭曲变形;旋转轴承滑块加注防锈润滑油。

三、 跟踪控制系统 (TCU) 角度校准与 Stow 防护保护实测 SOP

(一)跟踪控制器 (TCU) 角度校准与逆跟踪算法

跟踪角度偏差校准:

使用电子高精度倾角仪贴近组件边框,实测支架实际倾角,与 TCU 屏或 SCADA 监控显示的角度比对。

角度误差标准:实际倾角与理论天文学倾角的偏差必须 < 1.5°。当角度偏差 ≥ 2.0° 时,会导致前后排组件产生严重的“阴影遮挡”,造成发电量损失 > 5%。

逆跟踪(Backtracking)算法校准:

早晨日出后 1 小时及傍晚日落前 1 小时,检查跟踪系统逆跟踪算法运行正常,支架自动退回较平缓角度,防止前排支架遮挡后排组件。

(二)大风/大雪 Stow 保护模式实测 SOP(强制安全逻辑)

当遇到恶劣气象时,跟踪系统须自动切入 Stow(安全平铺)保护模式,防止巨大风阻吹翻支架。

大风 Stow 保护模式实测 SOP:

测试周期:每半年利用仿真风速信号测试 1 次。

实测流程与响应时序:

第1步:气象站风速风向仪检测到阵风风速 ≥ 17.2 m/s(达到 8 级大风预警线)。

第2步:气象站毫秒级向 TCU 跟踪控制器群发大风告警广播信号。

第3步:TCU 控制器强行中断当前太阳跟踪逻辑,启动驱动电机。

第4步:跟踪支架须在 < 30 秒内迅速旋转至

大雪/冰雹卸雪保护模式:

当雪载传感器检测到雪载厚度 > 10 cm 时,TCU 控制器驱动支架旋转至最大倾角(如 50度),利用重力自动滑动卸雪,防止重雪压塌支架。

风速仪失联安全倒计时保护:

当 TCU 控制器与主气象站通讯中断持续超 5 分钟时,TCU 须自动强行控制支架切入0度水平 Stow 保护位置,防止突发大风时因通讯中断而失控破坏

光伏电站PV侧支架及跟踪传动系统设备级巡检与运维签到表

电站名称:_______________________________ 巡检日期:2026 年 ____ 月 ____ 日

巡检区域:光伏支架及跟踪传动区 巡检负责人:____________________

一、 现场设备巡检与测试实测数据记录

二、 巡检缺陷登记与消缺派工

三、 巡检签到与复核签字

巡检工程师 (签字):_______________ 监护工程师 (签字):_______________

值班长复核 (签字):_______________ 签到归档时间:2026 年 ____ 月 ____ 日 ____ 时