Part 1: Equipment-level inspection and operation and maintenance SOP for PV side components and array systems of photovoltaic power stations

Part 1: Equipment-level inspection and operation and maintenance SOP for PV side components and array systems of photovoltaic power stations (corresponding to topology module 1)

This article corresponds to the panoramic topology diagram of the photovoltaic power station [Module 1: Photovoltaic modules and square array system], covering photovoltaic module glass/backplate appearance inspection, infrared hot spot scanning, junction box bypass diode test, portable EL crack detection, PID effect (potential induced attenuation) nighttime pressure repair and photovoltaic module standard cleaning operations.

1. Photovoltaic module physical appearance and structural maintenance SOP

(1) Tempered glass and backplane packaging maintenance

Inspection of tempered glass and anti-reflective coating: Check that there are no spider web-like bursts and cracks on the surface of the glass; check that the anti-reflective (ARC) coating has no peeling, scratches or peeling; check that the silicone sealing edge at the junction of the glass and the aluminum alloy frame has no degumming or cracking.

Backsheet and double-glass module packaging inspection:

Single-glass module backplane: Check that the backplane has no yellowing, no scratches, no exposed copper, no bubbles, bulges, and no delamination. When the backplane is deeply scratched and has a fluorine coating, moisture can easily invade and cause the insulation to drop to 0 MΩ.

Double-glass components: Check that the POE/EVA film on the front and rear double-layer glass edges has no aging bubbles, no water vapor snail trails, and black tracks.

(2) Aluminum alloy frame, pressure block bolts and ground jumper

Tightening torque of frame and pressure block: Use a torque wrench to randomly test the middle pressure block and side pressure block bolts of the assembly. The tightening torque of M8 stainless steel bolts must be maintained at 16.0 ~ 20.0 N·m, and the locking washers must be well locked. The pressing block must not compress the effective light-emitting area of ​​the battery piece.

Module ground jumper resistance test: Use a microohmmeter to test the jumper resistance of the module's aluminum alloy frame to the photovoltaic bracket's ground terminal. The on-resistance must be ≤ 0.1 Ω. If the grounding bolt is found to be corroded, sand it with sandpaper and retighten it, and apply anti-rust conductive paste.

(3) MC4 DC plug polarity, temperature rise and junction box

MC4 quick plug arc prevention maintenance:

Polarity check: When reconnecting after disassembly and maintenance, you must use a multimeter to measure the positive and negative polarities. Reverse polarity is strictly prohibited.

Buckle and seal: Check whether the waterproof rubber sealing rings of the positive and negative MC4 plugs have aged and fallen off; the plug handle is locked firmly and there is no looseness due to tripping.

Infrared Thermometry: Use an infrared camera to scan a running MC4 plug. The operating temperature rise of the plug must be < 15.0 ℃, and the operating temperature must be < 60.0 ℃. If the plug is found to be discolored and black or the temperature rise exceeds the standard, it means that the contact resistance is too large. The circuit must be cut off and re-crimped to replace the new MC4 terminal.

Appearance and sealing of the junction box: Check that the junction box shell is not cracked or deformed, and that the box cover is fastened; the outlet anti-pulling nut (Cable Gland) is tightened and not loose.

2. Component hot spot effect (Hotspots) and junction box bypass diode maintenance SOP

(1) Infrared thermal imaging (FLIR) hot spot scanning SOP

Test meteorological conditions: Scanning operations must be carried out when there is sufficient sunshine, solar irradiance must be ≥ 700 W/m², wind speed < 4.0 m/s, and the entire station's photovoltaic array must be operating at full power.

Hot spot classification and treatment standards:

General hot spots (10.0 ℃ ≤ ΔT < 20.0 ℃): Single point slight heating, partially blocked by dust or bird droppings -> Record the number and include it in the cleaning and maintenance plan; retest after washing.

Severe hot spots (ΔT ≥ 20.0 ℃ or T ≥ 80.0 ℃): severe heat generation, EVA film turns yellow, and back panel is burnt -> Isolate the component and replace it within 48 hours to prevent fire.

Bypass breakdown: The entire string/half string of cells generates heat and temperature rise -> The bypass diode in the junction box breaks down and is short-circuited -> During a power outage, disassemble the junction box, measure and replace the bypass diode.

(2) Junction box bypass diode (Bypass Diode) detection SOP

When the bypass diode is short-circuited by reverse high voltage, the entire string or half of the string of cells will be bypassed normally, resulting in a loss of 1/3 or 1/2 of the module power.

Step 1: Open the DC input breaker/unplug the MC4 plug for the string to bring the assembly offline.

Step 2: Open the junction box cover and set the multimeter to the "diode measurement position".

Step 3: Connect the red test lead to the positive electrode of the diode, and the black test lead to the negative electrode, measure the forward voltage drop (the forward voltage drop of the Schottky diode must be between 0.30 ~ 0.70 V).

Step 4: Change the test leads to measure the reverse resistance. The impedance must be close to infinity (> 1.0 MΩ). If the reverse resistance impedance is close to 0 Ω, it is determined that the diode is broken down and short-circuited, and a soldering iron must be used to replace the diode of the same specification (such as 20A / 45V).

3. Portable EL Crack Test and PID Effect (Potential Induced Decay) Prevention SOP

(1) Portable EL (electroluminescence) crack detection SOP

Cell micro-cracks are internal physical fractures that are invisible to the naked eye and will seriously affect component life.

Step 1: The test must be conducted at night or in a special blackout environment.

Step 2: Connect the DC power output of the portable EL tester to the positive and negative MC4 plugs of the PV module.

Step 3: Apply a forward current that matches the open circuit voltage (usually 8.0 ~ 10.0 A) to the component, so that the cell sheet is excited to emit near-infrared light (800 ~ 1100 nm).

Step 4: Capture EL images using a highly sensitive infrared camera.

Judgment criteria: The dark and dark areas in the image are dead chips or cracks. When the cracked area of ​​a single cell exceeds 10% of the total area of ​​the cell, or there are cross fractures (Black Hearts), it is judged to be unqualified and the component must be replaced.

(2) PID effect (potential induced decay) diagnosis and Anti-PID nighttime reverse pressure repair SOP

The PID effect is that under the action of high-voltage DC (1000V/1500V), a high-voltage electric field is formed between the module frame and the cell sheet, causing sodium ions (Na+) in the glass to migrate to the surface of the cell sheet, causing a severe attenuation of 10% to 50% in power within 1-2 years.

PID diagnosis: In the SCADA system, it was found that the open-circuit voltage Voc of a certain string was normal, but the full-load operating current and power dropped significantly; the EL test showed a large number of black blocks on the edges of the battery cells.

Anti-PID nightly reverse pressure repair process:

Step 1: Install an intelligent PID repair generator (Anti-PID Box) on the AC side of the string inverter or the DC side of the combiner box.

Step 2: Set the PID generator control logic: When the weather station detects irradiance < 10 W/m² and the inverter stops working for 30 minutes, the PID generator starts automatically.

Step 3: The PID generator applies 500V ~ 1000V DC high voltage (current limited to < 5 mA) to the DC negative electrode of the photovoltaic array to the ground, and pressurizes continuously for 6 ~ 8 hours.

Step 4: 30 minutes before sunrise, the PID generator automatically cuts off the high voltage and returns to ground, and the inverter starts normally. After 3 to 7 consecutive nights of repair, the component power can be restored to more than 90%.

4. Photovoltaic module standard cleaning SOP (standardized operating procedure)

Cleaning period control (mandatory anti-explosion standard):

It is strictly prohibited to clean components during high-irradiation periods at noon! When exposed to direct sunlight, the surface temperature of the module glass can reach 50 ~ 60 ℃. At this time, rinse with cold water. The severe thermal expansion and contraction stress will instantly cause the entire tempered glass to burst.

Best cleaning time: 1 hour before sunrise to 2 hours after sunrise, or in the evening after sunset.

Water quality and water pressure standards:

Water quality requirements: The pH value of the flushing water must be between 6.0 and 8.0 (neutral); the water hardness must be < 100 mg/L (hard water flushing will leave white calcium and magnesium scale on the glass surface, which is difficult to remove).

Water pressure control: The pressure of the high-pressure water gun nozzle must be < 0.40 MPa. It is strictly prohibited to use high-pressure columnar water flow to directly spray the back panel, junction box and MC4 interface of the component.

杂草与树木遮挡刈割:

Weeds in the front rows and between the rows of the square array should be mowing and cleared every quarter, and the height of the weeds should be controlled below the height of the lower edge of the module (usually < 30 cm) to prevent hot spots caused by grass shadows.

Photovoltaic power station PV side components and array system equipment level inspection and operation and maintenance sign-in form

Power station name: _______________________________ Inspection date: ____ month ____ day, 2026

Inspection area: Photovoltaic module array area Inspection person in charge: ____________________

1. On-site equipment inspection and test data recording:

2. Inspection defect registration and defect elimination dispatch

3. Inspection sign-in and review signature

Inspection Engineer (Signature): _______________ Supervision Engineer (Signature): _______________

Review (signature) of the shift leader: _______________ Sign-in and filing time: ____ hour on ____ month ____ day 2026

第1篇:光伏电站PV侧组件与方阵系统设备级巡检与运维 SOP

第1篇:光伏电站PV侧组件与方阵系统设备级巡检与运维 SOP(对应拓扑模块一)

本篇对应光伏电站全景拓扑图【模块一:光伏组件与方阵系统】,涵盖光伏组件玻璃/背板外观检修、红外热斑扫描、接线盒旁路二极管测试、便携式 EL 隐裂检测、PID 效应(电势诱导衰减)夜间加压修复以及光伏组件规范清洗作业。

一、 光伏组件物理外观与结构检修 SOP

(一)钢化玻璃与背板封装检修

钢化玻璃与防反射涂层检查:检查玻璃表面无蜘蛛网状爆裂碎裂;检查防反射(ARC)涂层无脱落、无划痕剥离;检查玻璃与铝合金边框交界处的硅胶密封封边无脱胶开裂。

背板(Backsheet)与双玻组件封装检查:

单玻组件背板:检查背板无黄变、无划痕露铜、无气泡鼓包及脱层现象。背板划痕深及氟涂层时,湿气易侵入导致绝缘降至 0 MΩ。

双玻组件:检查前后双层玻璃封边 POE / EVA 胶膜无老化气泡、无水汽蜗牛纹(Snail Trails)发黑轨迹。

(二)铝合金边框、压块螺栓与接地跨接

边框与压块紧固力矩:使用扭力扳手抽测组件中压块及边压块螺栓。M8 不锈钢螺栓紧固力矩须保持在 16.0 ~ 20.0 N·m,防松垫片锁定良好。压块不得压挤电池片有效发光区域。

组件接地跨接电阻测试:使用微欧计测试组件铝合金边框对光伏支架接地端子的跨接电阻,导通电阻须 ≤ 0.1 Ω。如果发现接地螺栓锈蚀,须使用砂纸打磨后重紧并涂抹防锈导电膏。

(三)MC4 直流插头极性、温升与接线盒

MC4 快速插头防拉弧检修:

极性排查:维护拆装后重新插接时,必须使用万用表测量正负极极性,严禁极性反接。

扣手与密封:检查正负极 MC4 插头防水橡胶密封圈无老化脱落;插头扣手锁定牢固,无脱扣松动。

红外测温:使用红外热像仪扫描运行中的 MC4 插头。插头运行温升须 < 15.0 ℃,温度须 < 60.0 ℃。若发现插头变色发黑或温升超标,说明接触电阻过大,须切断电路后重新压接替换新 MC4 端子。

接线盒外观与密封:检查接线盒外壳无开裂变形,盒盖扣紧;出线防拉扯螺母(Cable Gland)拧紧无松动。

二、 组件热斑效应(Hotspots)与接线盒旁路二极管检修 SOP

(一)红外热成像(FLIR)热斑扫描 SOP

测试气象条件:扫描作业须在阳光充足时进行,太阳辐照度须 ≥ 700 W/m²,风速 < 4.0 m/s,全站光伏方阵处于满功率运行状态。

热斑分级判定与处理标准:

一般热斑(10.0 ℃ ≤ ΔT < 20.0 ℃):单点微发热,局部灰尘或鸟粪遮挡 -> 记录编号,列入清洗保养计划;洗后复测。

严重热斑(ΔT ≥ 20.0 ℃ 或 T ≥ 80.0 ℃):剧烈发热,EVA 膜变黄,背板焦黑 -> 48 小时内隔离该组件并更换,防火灾。

旁路击穿:整串/半串电池片发热温升 -> 接线盒旁路二极管击穿短路 -> 停电拆开接线盒,测量并更换旁路二极管。

(二)接线盒旁路二极管(Bypass Diode)检测 SOP

当旁路二极管被反向高压击穿短路时,会导致整串或半串电池片被常态旁路,损失 1/3 或 1/2 的组件功率。

第 1 步:断开该组串的直流输入断路器/拔出 MC4 插头,使组件处于离线状态。

第 2 步:打开接线盒盖,将万用表拨至“二极管测量档”。

第 3 步:红表笔接二极管正极,黑表笔接负极,测量正向压降(肖特基二极管正向压降须在 0.30 ~ 0.70 V 之间)。

第 4 步:调换表笔测量反向电阻,阻抗须接近无穷大(> 1.0 MΩ)。若反向电阻阻抗接近 0 Ω,判定为二极管击穿短路,须使用烙铁焊接更换同规格(如 20A / 45V)二极管。

三、 便携式 EL 隐裂测试与 PID 效应(电势诱导衰减)防范 SOP

(一)便携式 EL(电致发光)隐裂检测 SOP

电池片隐裂(Micro-cracks)是肉眼无法看见的内部物理断裂,会严重影响组件寿命。

第 1 步:检测须在夜间或使用专用遮光黑棚环境下进行。

第 2 步:将便携式 EL 测试仪的直流电源输出端连接至光伏组件的正负极 MC4 插头。

第 3 步:向组件施加与开路电压匹配的正向电流(通常为 8.0 ~ 10.0 A),使电池片受激发出近红外光(800 ~ 1100 nm)。

第 4 步:使用高感光红外相机拍摄 EL 图像。

判定标准:图像中无光黑暗区域为死片或裂纹。当单片电池片隐裂面积超过该电池片总面积的 10%,或存在交叉断裂(Black Hearts)时,判定为不合格,须更换组件。

(二)PID 效应(电势诱导衰减)诊断与 Anti-PID 夜间反向加压修复 SOP

PID 效应是在高压直流(1000V/1500V)作用下,组件边框与电池片之间形成高压电场,导致玻璃中的钠离子(Na+)迁移至电池片表面,使功率在 1-2 年内出现 10%~50% 的剧烈衰减。

PID 诊断:在 SCADA 系统中发现某组串开路电压 Voc 正常,但满载运行电流和功率大幅下降;EL 测试显示电池片边缘出现大量黑块。

Anti-PID 夜间反向加压修复流程:

第 1 步:在组串式逆变器交流侧或汇流箱直流侧加装智能 PID 修复发生器(Anti-PID Box)。

第 2 步:设定 PID 发生器控制逻辑:当气象站检测到辐照度 < 10 W/m² 且逆变器停止工作 30 分钟后,PID 发生器自动启动。

第 3 步:PID 发生器向光伏方阵直流负极对地施加 500V ~ 1000V 直流高压(电流限制在 < 5 mA),连续加压 6 ~ 8 小时。

第 4 步:日出前 30 分钟,PID 发生器自动断开高压并恢复接地,逆变器正常启动。连续修复 3 ~ 7 个夜间后,组件功率可恢复 90% 以上。

四、 光伏组件规范清洗 SOP(标准化作业流程)

清洗时段控制(强制防爆裂标准):

严禁在正午高辐照时段清洗组件!阳光直射时组件玻璃表面温度可达 50 ~ 60 ℃,此时用冷水冲洗,剧烈的热胀冷缩应力会瞬间导致钢化玻璃整块爆裂。

最佳清洗时段:日出前 1 小时至日出后 2 小时,或傍晚日落后。

水质与水压标准:

水质要求:冲洗水质 pH 值须在 6.0 ~ 8.0 之间(中性);水质硬度须 < 100 mg/L(硬水冲洗会在玻璃表面留下白色钙镁水垢,难以清除)。

水压控制:高压水枪喷嘴压力须 < 0.40 MPa,严禁使用高压柱状水流直接喷射组件背板、接线盒及 MC4 接口。

杂草与树木遮挡刈割:

每季度对方阵前排及行间杂草进行刈割清理,控制杂草高度在组件下沿高度以下(通常 < 30 cm),防止草影遮挡诱发热斑。

光伏电站PV侧组件与方阵系统设备级巡检与运维签到表

电站名称:_______________________________ 巡检日期:2026 年 ____ 月 ____ 日

巡检区域:光伏组件方阵区 巡检负责人:____________________

一、 现场设备巡检与测试实测数据记录 :

二、 巡检缺陷登记与消缺派工

三、 巡检签到与复核签字

巡检工程师 (签字):_______________ 监护工程师 (签字):_______________

值班长复核 (签字):_______________ 签到归档时间:2026 年 ____ 月 ____ 日 ____ 时