Part 0: Acceptance and early handover specifications for PV side projects of photovoltaic power stations

Part 0: Acceptance and early handover specifications for PV side projects of photovoltaic power stations

This article stipulates the acceptance conditions, testing standards, defect rectification and delivery list from the completion of construction to the formal handover for operation and maintenance of photovoltaic power generation systems (including distributed and ground-based centralized photovoltaic power stations).

1. Cold-state static acceptance specifications for photovoltaic power station construction completion (uncharged state)

Cold acceptance is carried out before the system is powered on, and the core is to ensure that electrical insulation, mechanical connection torque, lightning protection grounding and pipe/structure sealing are up to standard.

(1) Cold test specifications for photovoltaic modules and arrays

100% blind test verification of string polarity and open circuit voltage (Voc) (CoreTect zero safety blind zone standard):

Test method: Disconnect the DC input switch of the combiner box/inverter, and the operation and maintenance engineer uses a calibrated DC multimeter (DC 1000V/1500V range) to measure 100% of the strings entering the inverter/combine box line by line. The red test lead is connected to the positive pole (PV+) of MC4, and the black test lead is connected to the negative pole (PV-).

合格标准:

Polarity determination (100% must check): The multimeter reading must show a positive value. If a negative number is displayed, it is judged to be a Class A fatal defect (reversed polarity). Closing is strictly prohibited and the construction party must be required to make rectifications immediately!

Voltage deviation (100% record): After the actual measured Voc is converted to standard test conditions (STC: 1000 W/m², 25 ℃), the deviation from the factory nameplate/design calculated value must be ≤ ± 3.0%. If the voltage is lower than the voltage of a single module, it means there is a missing connection or virtual connection.

String short-circuit current (Isc) and IV curve random test (≥ 10% random inspection quality control):

Test method: Randomly test no less than 10% of the strings in the photovoltaic array circuit, use a portable IV curve tester and a DC clamp meter to measure the string short-circuit current Isc and draw the IV curve.

Qualification standard: The deviation between the actual measured Isc and the nameplate after conversion to STC conditions must be ≤ ± 3.0%, and the IV curve should be smooth without step changes (no serious cracks or hot spots blocked).

Photovoltaic array DC insulation resistance impedance test:

Test method: Disconnect the DC switch of the combiner box/inverter, short-circuit the positive and negative poles of the string, and use a 1000V/2500V insulation megger to test the insulation resistance of the string to the ground (string frame/ground grid).

Qualification standard: DC-to-ground insulation resistance impedance must be ≥ 2.0 MΩ (1500V high-voltage system must be ≥ 5.0 MΩ). If the impedance is < 2.0 MΩ, closing is strictly prohibited.

(2) Mechanical connection and bolt tightening torque inspection

Use a calibrated torque wrench to conduct 100% bolt tightening inspections on photovoltaic brackets, module clamps, terminal blocks, etc. (the inspection rate shall not be less than 20%), and spray anti-loosening marking lines after tightening:

(3) Cable insulation, high voltage withstand and lightning protection grounding tests

DC/AC cable insulation resistance test:

The insulation resistance of the 1000V/1500V DC main cable between phases and to ground must be ≥ 10.0 MΩ (1000V megger test for 1 minute).

The insulation resistance of the 35kV high-voltage AC cable winding to ground must be ≥ 1000 MΩ (2500V megger test), and the absorption ratio K = R60s / R15s ≥ 1.3.

High voltage electrical withstand voltage test (Hip-Test):

When 1.5 Un + 1000V power frequency withstand voltage is applied to 35kV cables and high-voltage switch cabinets for 1 minute, the leakage current is < 5 mA, and there is no breakdown discharge flashover phenomenon.

Lightning protection grounding and equipotential jumper resistance test:

Use a ground resistance tester to measure the power frequency resistance of the main grounding network of the ground photovoltaic power station must be < 4.0 Ω (large booster stations must be < 1.0 Ω).

The equipotential cross-connection resistance between the component aluminum alloy frame and the bracket and the bracket and the main grounding grid must be ≤ 0.1 Ω.

2. Photovoltaic power station thermal live acceptance and trial operation specifications

(1) Logic sequence of receiving power and powering on

The system power receiving process must strictly follow the following safety logic steps:

Step 1: Close the AC 380V/220V auxiliary power supply for the station and check that the auxiliary voltage deviation is within ± 5% of the rated voltage range.

Step 2: Close the station DC panel/UPS AC incoming line and confirm that the control power supply DC 220V/110V outputs normally.

Step 3: Activate the fire main screen (FACP) and security monitoring system to confirm that there are no fire alarms or intrusion alarms.

Step 4: Start the SCADA background monitoring server and weather station sampling module to confirm data communication connectivity.

Step 5: Close the main circuit breaker of the 35kV booster station, receive power from the 35kV high-voltage busbar, and check the three-phase voltage balance.

Step 6: Close the load switch on the high-voltage side of the local box-type transformer step by step, perform impact power on the box-type transformer, and check that the voltage on the low-voltage side (such as 800V AC) of the box-type transformer is normal.

Step 7: Close the AC side circuit breaker of the string/centralized inverter, and the inverter completes AC adaptive phase locking.

Step 8: Close the DC side switch of the inverter or the main switch of the DC combiner box, and the inverter starts to connect to the grid to generate electricity.

(2) Point-to-point (P2P) sampling and verification between SCADA and inverter/combiner box

Telemetry sampling accuracy verification: Under full power generation, use Fluke's high-precision AC/DC clamp meter to measure the inverter's input DC voltage/current and output AC voltage/current, and compare with the SCADA monitoring interface. The voltage/current sampling error must be ≤ ± 0.5%.

Remote control derating and shutdown test: "Derate the inverter power by 50%" and "Emergency shutdown" commands are issued through SCADA, and the inverter must respond and accurately perform power derating or trip shutdown within < 100 ms.

(3) 72-hour continuous trial operation assessment standards

Before the power station is officially handed over to the operation and maintenance team, it must undergo a continuous 72-hour trouble-free trial operation:

Operational stability: No primary or secondary emergency protection tripped within 72 hours, and the inverter was only planned to be disconnected from the grid.

Overall site energy efficiency ratio (PR - Performance Ratio) assessment:

Calculation formula: PR = (actual output grid power kWh) / [nominal installed capacity kWp × (actual cumulative irradiance kWh/m² / 1 kW/m²)] × 100%.

Assessment standards: Under standard lighting conditions, the PR of the entire station during the trial operation must be ≥ 82.0%.

Protection function verification: During the trial operation, it successfully passed the anti-islanding protection (Anti-Islanding) and low voltage ride through (LVRT) simulated cut-off tests.

3. Photovoltaic power station handover defect order rectification and standard delivery list

(1) A/B/C three-level defect classification and closed-loop processing

Class A defects (fatal defects/strictly prohibited from receiving power): unqualified insulation impedance of the square array, failure to prevent false locking of the high-voltage switch cabinet, oil leakage from the box transformer, severe hot spots in the components (ΔT ≥ 20 ℃) ​​➔ Must be 100% rectified and eliminated before receiving power.

Class B defects (serious defects/time-limited rectification): string current deviation > 10%, abnormal noise of individual fans of the inverter, tracking angle deviation of the tracking bracket > 2.0° ➔ Derating operation is allowed, and the closed loop will be eliminated within 7 days.

Class C defects (minor defects/remaining rectification): local dust on the surface of the component glass, slight flaws in the paint on the bracket, and skewed nameplate logo ➔ Included in the defect elimination plan within 30 days.

(2) Operation and maintenance delivery documents and spare parts handover confirmation

When handing over the project, the construction unit must hand over a full set of engineering drawings, factory reports, spare parts and special tools to the CoreTect operation and maintenance team (see the printable form at the end for details).

Closed-loop table of completion acceptance and delivery of PV side project of photovoltaic power station

Power station name: _______________________________ Acceptance date: ____ month ____ day, 2026

Power plant scale: ______ MWp / ______ MW EPC construction unit: ____________________

1. Cold and hot key indicator acceptance confirmation form

2. Operation and maintenance delivery documents, drawings and spare parts inventory and handover confirmation form

3. Deadline for registration and rectification of defects left on site

4. Three-party signature confirmation and handover seal

第0篇:光伏电站PV侧项目验收与前期交接规范

第0篇:光伏电站PV侧项目验收与前期交接规范

本篇规定了光伏发电系统(含分布式与地面集中式光伏电站)施工完成至正式移交运维阶段的验收条件、测试标准、缺陷整改及交付清单。

一、 光伏电站施工完工冷态静态验收规范(未带电状态)

冷态验收在系统未带电前进行,核心确保电气绝缘、机械连接力矩、防雷接地及管道/结构密封达标。

(一)光伏组件与方阵冷态测试规范

组串极性与开路电压(Voc)100% 盲测校验(CoreTect 零安全盲区标准):

测试方法:断开汇流箱/逆变器直流输入开关,运维工程师使用校准后的直流万用表(DC 1000V/1500V 档),对进入逆变器/汇流箱的组串进行 100% 逐路测量。红表笔接 MC4 正极(PV+),黑表笔接负极(PV-)。

合格标准:

极性判定(100% 必查):万用表读数必须显示为正值。若显示负数,判定为 A 类致命缺陷(极性反接),严禁合闸,必须要求施工方立即整改!

电压偏差(100% 记录):实测 Voc 换算至标准测试条件(STC: 1000 W/m², 25 ℃)后,与出厂铭牌/设计计算值的偏差须 ≤ ± 3.0%。若电压偏低大于单块组件电压,说明存在漏接或虚接。

组串短路电流(Isc)与 IV 曲线抽测(≥ 10% 抽检质量把关):

测试方法:按光伏方阵回路抽测不低于 10% 的组串,使用便携式 IV 曲线测试仪及直流钳形表实测组串短路电流 Isc 并绘制 IV 曲线。

合格标准:实测 Isc 换算至 STC 条件后与铭牌偏差须 ≤ ± 3.0%,IV 曲线应平滑无阶梯异变(无严重隐裂或热斑遮挡)。

光伏方阵直流绝缘电阻阻抗测试:

测试方法:断开汇流箱/逆变器直流开关,将组串正负极短接,使用 1000V / 2500V 绝缘摇表测试组串对地(组串边框/接地网)绝缘电阻。

合格标准:直流对地绝缘电阻阻抗必须 ≥ 2.0 MΩ(1500V 高压系统必须 ≥ 5.0 MΩ)。若阻抗 < 2.0 MΩ,严禁合闸。

(二)机械连接与螺栓紧固力矩检验

使用经过计量校准的扭力扳手,对光伏支架、组件压块、接线端子等进行 100% 螺栓紧固抽检(抽检率不低于 20%),并在紧固后喷涂防松标记线:

(三)电缆绝缘、高压耐压与防雷接地测试

直流/交流电缆绝缘电阻测试:

1000V/1500V 直流主电缆相间及对地绝缘电阻须 ≥ 10.0 MΩ(1000V 摇表测试 1 分钟)。

35kV 高压交流电缆绕组对地绝缘电阻须 ≥ 1000 MΩ(2500V 摇表测试),吸收比 K = R60s / R15s ≥ 1.3。

高压电气耐压测试(Hip-Test):

35kV 电缆及高压开关柜施加 1.5 Un + 1000V 工频耐压 1 分钟,漏电流 < 5 mA,无击穿放电闪络现象。

防雷接地与等电位跨接电阻测试:

使用接地电阻测试仪测量,地面光伏电站主接地网工频电阻须 < 4.0 Ω(大型升压站须 < 1.0 Ω)。

组件铝合金边框对支架、支架对主接地网的等电位跨接导通电阻须 ≤ 0.1 Ω。

二、 光伏电站热态带电验收与试运行规范

(一)受电与上电逻辑顺序

系统受电带电过程必须严格遵循以下安全逻辑步骤:

第1步:闭合站用 AC 380V/220V 辅助电源,检查辅助电压偏差在 ± 5% 额定电压范围内。

第2步:闭合站用直流屏/UPS 交流进线,确认控制电源直流 220V/110V 正常输出。

第3步:激活消防主屏(FACP)及安防监控系统,确认无火警与入侵告警。

第4步:启动 SCADA 后台监控服务器及气象站采样模块,确认数据通讯连通。

第5步:闭合 35kV 升压站主断路器,对 35kV 高压母线冲击受电,检查三相电压平衡。

第6步:逐级闭合就地箱变高压侧负荷开关,对箱变进行冲击受电,检查箱变低压侧(如 800V AC)电压正常。

第7步:闭合组串式/集中式逆变器交流侧断路器,逆变器完成交流自适应锁相。

第8步:闭合逆变器直流侧开关或直流汇流箱总开关,逆变器启动并网发电。

(二)SCADA 与逆变器/汇流箱点对点(P2P)采样校验

遥测采样精度校验:在满功率发电状态下,使用 Fluke 高精度交流/直流钳形表实测逆变器输入直流电压/电流及输出交流电压/电流,与 SCADA 监控界面比对。电压/电流采样误差须 ≤ ± 0.5%。

遥控降额与停机测试:通过 SCADA 下发“逆变器功率降额 50%”及“紧急停机”指令,逆变器须在 < 100 ms 内响应并准确执行功率降额或跳闸停机。

(三)72 小时连续试运行考核标准

电站在正式移交运维团队前,必须进行连续 72 小时无故障试运行:

运行稳定性:72 小时内无任何一、二级紧急保护跳闸,逆变器无非计划脱网。

全站能效比(PR - Performance Ratio)考核:

计算公式:PR = (实际输出上网电量 kWh) / [标称装机容量 kWp × (实际累积辐照度 kWh/m² / 1 kW/m²)] × 100%。

考核标准:在标准光照条件下,试运行期间全站 PR 须 ≥ 82.0%。

保护功能验证:试运行期间成功通过防孤岛保护(Anti-Islanding)及低电压穿越(LVRT)模拟切断测试。

三、 光伏电站交接缺陷单整改与标准交付清单

(一)A/B/C 三级缺陷分类与闭环处置

A 类缺陷(致命缺陷 / 严禁受电):方阵绝缘阻抗不合格、高压开关柜防误闭锁失效、箱变渗油、组件严重热斑(ΔT ≥ 20 ℃) ➔ 必须 100% 整改消除后方可受电。

B 类缺陷(严重缺陷 / 限期整改):组串电流偏差 > 10%、逆变器个别风扇异响、跟踪支架跟踪角度偏差 > 2.0° ➔ 允许降额运行,7 天内消缺闭环。

C 类缺陷(轻微缺陷 / 遗遗留整改):组件玻璃表面局部灰尘、支架油漆微瑕、铭牌标识歪斜 ➔ 列入 30 天内消缺计划。

(二)运维交付文件与备品备件移交确认

工程交接时,施工单位须向 CoreTect 运维团队移交全套工程图纸、出厂报告、备品备件及专用工具(具体内容见末尾可打印表单)。

光伏电站PV侧工程竣工验收与交付闭环表

电站名称:_______________________________ 验收日期:2026 年 ____ 月 ____ 日

电站规模:______ MWp / ______ MW EPC施工单位:__________________

一、 冷态与热态关键指标验收确认表

二、 运维交付文件、图纸与备品备件清点移交确认表

三、 现场遗留缺陷登记与整改限期表

四、 三方签字确认与交接盖章