Chapter division of real on-site work steps for on-site debugging of PV side of photovoltaic power station

Chapter division of real on-site work steps for on-site debugging of PV side of photovoltaic power station

Phase 1: Commissioning team preparation and safety lockout (Day 1 morning)

Step 1.1: Review the calibration list of debugging instruments and tools (multimeter, megometer, phase sequence meter, clamp meter, infrared thermal imaging camera, torque wrench and calibration validity period)

Work step 1.2: PPE (personal protective equipment) equipment and arc protection confirmation for high-voltage/high-flow operations

Step 1.3: Start the on-site LOTO (Lockout/Tagout) safety isolation procedure and sign the Permit to Work (PTW)

Step 1.4: Review the as-built drawings, relay protection setting sheets and grid code parameters

Phase 2: Photovoltaic array and DC/AC side cold static test (Day 1 afternoon ~ Day 2)

Step 2.1 [Array area]: 100% blind test of the positive and negative polarity of the string (actual measurement with a multimeter to prevent reverse connection) and 100% verification of the Voc open circuit voltage

Step 2.2 [Array area]: Random test of string short-circuit current (Isc) and IV curve (≥10% random test, STC condition conversion comparison)

Step 2.3 [Array area]: DC string-to-ground insulation resistance (Riso) test (1000V/1500V megger test, impedance ≥ 2.0/5.0 MΩ)

Process step 2.4 [array area]: 100% extraction and review of component clamps, brackets and ground terminal bolt torques, 100% spraying of CoreTect anti-loosening marking lines

Work step 2.5 [Power distribution area]: DC/AC combiner box anti-condensation heater test, aR fast fuse resistance test at both ends and SPD lightning protection remote signaling trigger test

Step 2.6 [High-voltage area]: 35kV high-voltage AC cable megger insulation test (≥1000 MΩ) and power frequency withstand voltage (Hip-Test) test

Stage 3: Electrify the station power supply and control center (Day 3 - energize the "brain" first)

Step 3.1: Close the AC 380V/220V auxiliary power supply for the station, and check the auxiliary voltage deviation (within ±5%) and phase sequence

Step 3.2: Close the station DC panel (DC 220V/110V) and UPS, and test the stable output of the control power supply and the battery float voltage

Step 3.3: Activate the fire main screen (FACP) and security monitoring system to confirm that there are no fire alarms or intrusion alarms

Step 3.4: Start the SCADA background monitoring server, network switch and weather station sampling module (irradiance, shutter, plate temperature, anemometer)

Stage 4: High-voltage booster station and box-type transformer receive power (Day 4 - high voltage is supplied to the "blood vessels")

Step 4.1: Check the SF6 pressure gauge of the 35kV switch cabinet (green zone 0.35~0.45 MPa) and the three-phase anisotropy of the vacuum circuit breaker (< 1.0ms)

Step 4.2: Close the main circuit breaker of the 35kV booster station, conduct impact power on the 35kV high-voltage busbar, and check the three-phase voltage balance and positive phase sequence

Step 4.3: Gradually close the load switch on the high voltage side of the local box transformer to receive power from the box transformer.

Step 4.4: At the AC input end of the inverter, measure the low-voltage AC voltage (such as 800V AC) output by the box-type transformer and the A/B/C three-phase sequence.

Stage 5: Inverter power-on, grid-connected phase locking and SCADA P2P calibration (Day 5 - Node connected to the grid)

Step 5.1: Close the AC side circuit breaker of the inverter, and the inverter AC adaptive phase-locked loop (PLL) completes the grid voltage locking

Step 5.2: After checking the DC polarity for the second time, close the DC side switch of the inverter

Step 5.3: Connect the mobile APP to the inverter and load the Philippine local grid code (Grid Code, such as Philippines_NGCP 60Hz) and over-under voltage/over-under frequency parameters.

Step 5.4: Start the inverter self-test countdown (60~300 seconds), close the relay, and start the inverter to connect to the grid to generate electricity.

Step 5.5 [P2P comparison]: Under full power, use a Fluke clamp meter to measure the AC and DC voltage and current of the inverter, and compare it with the SCADA monitoring interface (error ≤ ±0.5%)

Step 5.6 [Emergency Stop Test]: SCADA issues a 50% power derating command and an "emergency stop" command to test the inverter response time (< 100ms)

Phase 6: Scheduling response, network planning test and full load scan (Day 6 - system joint debugging)

Step 6.1: Simulate power loss in the power grid, test the inverter anti-islanding protection (Anti-Islanding), cut off the grid connection and alarm within ≤ 2.0s

Step 6.2: Test scheduling AGC (automatic power generation control) active power tracking accuracy (≥ 99.0%) and AVC (automatic voltage control) reactive power adjustment

Step 6.3: After the entire station has been running at full power for 2 hours, use an infrared thermal imaging camera to conduct a thermal imaging scan of the MC4 connector, circuit breaker copper bar, and high-voltage cable head.

Phase 7: 72-hour trial operation and completion signed delivery (Day 7+ - stamped delivery)

Step 7.1: Start a 72-hour continuous trouble-free trial operation (no primary/secondary tripping, nothing more than planned disconnection)

Step 7.2: On-site calculation and qualification determination of PR (Performance Ratio) energy efficiency ratio of the whole station (PR of the whole station ≥ 82.0% under standard lighting)

Step 7.3: Organize and sign [Four sets of on-site commissioning delivery form packages] (the owner, EPC construction party, and CoreTect commissioning party stamp and sign)

光伏电站 PV 侧现场调试真实现场工步章节划分

光伏电站 PV 侧现场调试真实现场工步章节划分

阶段一:调试团队进场准备与安全上锁(Day 1 上午)

工步 1.1:调试仪器与工具校验清单复核(万用表、摇表、相序表、钳表、红外热像仪、力矩扳手及校验有效期)

工步 1.2:高压/高流作业 PPE(个人防护装备)配备与防电弧防护确认

工步 1.3:现场 LOTO(Lockout/Tagout 上锁挂牌)安全隔离程序启动与工作许可(PTW)签署

工步 1.4:审核竣工图纸、继电保护定值单与电网规范(Grid Code)参数

阶段二:光伏方阵与直流/交流侧冷态静态测试(Day 1 下午 ~ Day 2)

工步 2.1【阵列区】:组串正负极极性 100% 盲测(万用表实测,防反接)与 Voc 开路电压 100% 校验

工步 2.2【阵列区】:组串 short-circuit 电流(Isc)与 IV 曲线抽测(≥10% 抽测,STC 条件换算比对)

工步 2.3【阵列区】:直流组串对地绝缘电阻(Riso)测试(1000V/1500V 摇表测试,阻抗 ≥ 2.0/5.0 MΩ)

工步 2.4【阵列区】:组件压块、支架与接地端子螺栓力矩 100% 抽复核,100% 喷涂 CoreTect 防松标记线

工步 2.5【配电区】:直流/交流汇流箱防凝露加热器测试、aR 快速熔断器两端电阻测试与 SPD 防雷遥信触发测试

工步 2.6【高压区】:35kV 高压交流电缆摇表绝缘测试(≥1000 MΩ)与工频耐压(Hip-Test)测试

阶段三:站用电源与控制中枢受电(Day 3 —— 先给“大脑”通电)

工步 3.1:闭合站用 AC 380V/220V 辅助电源,检查辅助电压偏差(±5% 范围内)与相序

工步 3.2:闭合站用直流屏(DC 220V/110V)及 UPS,测试控制电源稳定输出与电池浮充电压

工步 3.3:激活消防主屏(FACP)及安防监控系统,确认无火警与入侵告警

工步 3.4:启动 SCADA 后台监控服务器、网络交换机及气象站采样模块(辐照度、百叶箱、板温、风速仪)

阶段四:高压升压站与箱变冲击受电(Day 4 —— 给“血管”通高压)

工步 4.1:检查 35kV 开关柜 SF6 气压表(绿区 0.35~0.45 MPa)与真空断路器三相不同期性(< 1.0ms)

工步 4.2:闭合 35kV 升压站主断路器,对 35kV 高压母线进行冲击受电,检查三相电压平衡与正相序

工步 4.3:逐级闭合就地箱变高压侧负荷开关,对箱变进行冲击受电

工步 4.4:在逆变器交流进线端,实测箱变输出低压交流电压(如 800V AC)及 A/B/C 三相顺相序

阶段五:逆变器通电、并网锁相与 SCADA P2P 校准(Day 5 —— 节点并网)

工步 5.1:闭合逆变器交流侧断路器,逆变器交流自适应锁相环(PLL)完成网压锁定

工步 5.2:二次核对直流极性后,闭合逆变器直流侧开关

工步 5.3:手机 APP 连入逆变器,加载菲律宾本地电网码(Grid Code,如 Philippines_NGCP 60Hz)及过欠压/过欠频参数

工步 5.4:启动逆变器自检倒计时(60~300秒),继电合闸,逆变器启动并网发电

工步 5.5【P2P比对】:满功率状态下,用 Fluke 钳表实测逆变器交直流电压电流,与 SCADA 监控界面比对(误差 ≤ ±0.5%)

工步 5.6【急停测试】:SCADA 下发 50% 功率降额指令及“紧急停机”指令,测试逆变器响应时间(< 100ms)

阶段六:调度响应、网规测试与满载扫描(Day 6 —— 系统联调)

工步 6.1:模拟电网失电,测试逆变器防孤岛保护(Anti-Islanding)在 ≤ 2.0s 内切断并网并告警

工步 6.2:测试调度 AGC(自动发电控制)有功跟踪精度(≥ 99.0%)与 AVC(自动电压控制)无功调节

工步 6.3:全站满功率运行 2 小时后,使用红外热像仪对 MC4 接头、断路器铜排、高压电缆头进行热成像扫描

阶段七:72 小时试运行与竣工签署交付(Day 7+ —— 盖章交付)

工步 7.1:启动连续 72 小时无故障试运行(无一/二级跳闸,无非计划脱网)

工步 7.2:全站 PR(Performance Ratio)能效比现场核算与合格判定(标准光照下全站 PR ≥ 82.0%)

工步 7.3:整理并签署 【四套现场调试交付表单包】(业主、EPC 施工方、CoreTect 调试方三方盖章签署)