第五 章

Chapter 5: PCS (energy storage converter) operation and maintenance standards

This chapter stipulates the standardized operations for daily inspection and preventive maintenance of the hybrid inverter (PCS) by CoreTect authorized engineers. ⚠️ Note: This chapter only covers the O&M (operation and maintenance) level. Engineers are strictly prohibited from performing motherboard-level welding repairs on site.

5.1 PCS Safety Isolation and Electrical Test Specification (LOTO)

Before performing any operation to open the inverter wiring compartment cover, the following discharge red lines must be strictly observed:

1. Disconnect AC and DC: Disconnect the AC grid circuit breaker, load circuit breaker, PV isolation switch and battery DC main gate in sequence.

2. Force the static capacitor to discharge: After powering off, force the device to wait for ≥ 5 minutes (models above 100kW need to wait 15 minutes) to allow the internal DC-Link large-capacity electrolytic capacitor to completely discharge.

3. High-voltage electrical test: Wear insulating gloves and use a multimeter at the DC 1000V range to measure BAT+ and BAT-. Only after confirming that the internal residual voltage is < 36V DC can you start touching.

5.2 PCS electrical connection and torque maintenance

Since the inverter operates under high current and thermal expansion and contraction conditions for a long time, the AC and DC terminals can easily become loose and cause arc fire.

1. Thermal imaging inspection (performed with power on): When running at full load every quarter, use an infrared thermal imaging camera to scan the GRID/LOAD AC output terminals and BAT/PV DC terminals. If the terminal temperature is > 65°C, or the temperature difference between phases is > 5°C, it is marked as abnormal.

2. Torque retightening (executed when power is off): Use an insulated torque wrench to retighten the detected abnormal heating points (reference standards: M6 bolts 5N·m, M8 bolts 12N·m, M12 bolts 45N·m), and redraw the red/blue anti-loosening lines.

5.3 PCS heat dissipation and dust-proof maintenance

The life of the inverter is determined by the heat dissipation of the IGBTs. In the high dust environment of the Philippines, strict implementation is required:

1. External dust filter: During monthly inspection, remove the dust filter from the bottom/side air inlet of the inverter, use a high-pressure air gun (pressure < 0.3MPa) or clean water to rinse and dry it thoroughly before reinstalling it.

2. Cooling fan test: Force the fan to run at 100% through the on-screen diagnostic menu. If there is abnormal bearing noise or speed alarm, it must be recorded and the fan module must be replaced as a whole during the next inspection.

Chapter 6: Communication and Cloud Platform Operation and Maintenance Standards

Communication links are the lifeblood of CoreTect's SaaS services and remote risk control, and must ensure an online rate of 99.9%.

6.1 Physical Link Layer Check (Physical Layer)

- Anti-interference of communication cables: Check whether the RS485 and CAN communication lines use shielded twisted pairs (Shielded Twisted

Pair). The shield must be connected to ground at one end at the inverter end. It is strictly prohibited to bundle communication lines and AC and DC thick cables in parallel in the same cable trough. They must be kept 15cm apart.

以上间距。

- Terminal matching resistor: If the bus distance exceeds 50 meters or there is serious garbled packet loss on site, check whether the A/B pins of the device at the end of the bus have been connected in parallel with a 120Ω terminal resistor.

6.2 Edge Intelligent Gateway (4G DTU/ESP32) Operation and Maintenance

- Signal dead zone test: Check the RSSI value of the gateway background. Standard requirements RSSI >

-85dBm. If the signal is lower than this value, it is strictly forbidden to lock the antenna in the metal cabinet. You must use an extension cord to move the suction cup antenna to an unobstructed place outdoors.

- Watchdog and reconnection test (Watchdog Test): Unplug the 4G gateway antenna on site to simulate a network disconnection, and observe whether the gateway can be disconnected within 300

Trigger the hardware watchdog within seconds, automatically power off, restart and reconnect.

CoreTect ThingsBoard cloud platform.

Chapter 7: Failure Response and RCA Investigation

7.1 Service Level Agreement (SLA) Response Matrix

Based on the SaaS level of customer subscription, CoreTect Operation and Maintenance Center strictly implements the following response time:

- 🚨 Level P1 (major failure): PCS down/fire alarm/battery communication offline.

- Response mechanism: The cloud intervenes and issues a safe power-off command within 30 minutes; Metro Manila area engineers arrive at the scene with spare parts within 4 hours.

- ⚠️Level P2 (general failure): cell voltage difference > 100mV / battery environment high temperature warning.

- Response mechanism: The cloud will respond within 4 hours and try to issue remote balancing instructions; if it does not recover, on-site investigation will be conducted within 24 hours.

- ℹ️ Level P3 (minor abnormality): Weak 4G signal causes occasional data delays.

- Response mechanism: Register within 24 hours and resolve the issue during the next routine inspection.

7.2 Major accident RCA (root cause analysis) and liability investigation

When P1-level equipment blows up or a customer makes a claim, engineers must issue an 8D standard RCA report within 48 hours to clarify the responsibility (line of defense):

1. Evidence collection of illegal loads: Check the distribution box on site. If a customer is found to have privately connected a large inductive load such as a deep well water pump, take photos and collect evidence, and it will be determined as [reverse electromotive force breakdown IGBT], which is a human violation by the customer and the warranty will be refused.

2. Harsh environment evidence collection: If you find water leaking from the roof and dripping into the cabinet, or the tamper-resistant warranty seal (Warranty Seal) is torn, immediately shut down the machine and take photos.

3. Black box log extraction: Use a computer to connect to the BMS/PCS, export the underlying logs 5 minutes before the crash, and analyze whether there is an ultra-high voltage surge in the power grid (Grid

Surge). If the power grid is struck by lightning, it is a force majeure event.

Chapter 8: Philippine Field Operation and Maintenance Standards (PH Localized Standards)

Special operation and maintenance specifications are formulated based on the tropical island climate and underdeveloped power grid environment of the Philippines.

8.1 Extreme moisture resistance and salt spray resistance (Anti-Corrosion Protocol)

- Contact sealing: The Philippines has high humidity and salt, which can easily cause green patina or electrochemical corrosion on electrical terminals. During inspection, the oxide layer must be cleaned with electronic cleaner, industrial conductive paste should be applied after tightening, and polyurethane conformal paint should be sprayed

(Conformal Coating) Completely isolates moisture.

- Anti-condensation management: During rainy season inspections, it is necessary to check whether the anti-condensation heating plate at the bottom of the cabinet is working properly to prevent water vapor from condensing and causing high-voltage discharge.

8.2 防虫鼠害灾难排查 (Pest Control)

- Geckos (Tuko), rats, and red ants are the number one killers of motherboard short circuits in the Philippines.

- Mandatory action: Every time you open a cabinet, you must clean up the debris at the bottom. Firestop Putty must be used in the cable entry and exit holes inside and outside the cabinet.

Seal tightly; industrial insect repellent/rodent repellent tablets must be regularly placed in the corners of the electrical cabin.

8.3 Typhoon and Flooding Emergency Plan (Typhoon Emergency SOP)

- 48 hours before typhoon (Pre-Typhoon): The cloud issues a mandatory charging command to increase the battery SOC lower limit to 90% in preparation for war.

- Flood rescue (Flood): If the water level warning submerges 10cm from the bottom of the cabinet, the DC main gate will be forcibly cut off remotely/on-site and the power supply of the 4G gateway will be unplugged.

- Red line for water receding and recovery: Customers are strictly prohibited from closing the gate on their own! An engineer must come to clean and dry the device, and use a 1000V megger to measure the AC and DC insulation resistance > 2MΩ before powering on again.

Chapter 9: Customer Service and Asset Management

This chapter establishes CoreTect’s commercial implementation mechanism for transforming “low-frequency maintenance” into “high-frequency value-added services”.

9.1 SOH life tracking and asset health score (Health Score)

- The cloud system integrates underlying data such as SOC, SOH, maximum pressure difference, and historical overtemperature times, and uses algorithms to automatically generate a 100-point "health score".

- Monthly Health Report: The system automatically generates a PDF report and sends it to the customer on the first day of each month.

- Commercial conversion: For sub-health assets with a score lower than 80 points, customer service proactively sends early warnings and attaches a "CoreTect Deep Balance and Life Extension Maintenance Quotation" to achieve proactive marketing.

9.2 White-Label system (White-Label) and agent management

- For large installers (Installer), CoreTect provides cloud ThingsBoard tenant-level permissions (Tenant Admin).

- Brand Enabling: Replace the proprietary logo and domain name in the system interface to enable the agency business.

- Ultimate risk control (Kill-Switch): CoreTect Asia Pacific headquarters retains the final control of the underlying gateway. If the agent maliciously defaults on SaaS

For a subscription fee, the headquarters has the right to cut off communications and even issue power-off instructions with one click on the cloud.

9.3 Spare parts warehousing and sluggish material flow (Spare Parts Management)

- Safety stock bottom line (Min-Max Inventory): Marikina laboratory needs to maintain core consumables (such as 4G

Gateway, DC circuit breaker, fuse tube, spare battery core) are above the safety stock water level.

- One-in, one-out principle: Engineers apply for new motherboards/gateways and go to the site for repairs. When they return, they must return the burned old parts and enter them into the black box system for write-off, to prevent spare parts from being lost or resold without permission.

Chapter 10: Rooftop Photovoltaic (PV) Troubleshooting and Practical Demining Guide

Note: According to CoreTect big data statistics, 70% of inverters in the Philippines report errors, and the root cause is the rooftop photovoltaic array (periphery). This chapter combines front-line practical experience to specifically deal with high-frequency deadlocks on the PV side.

10.1 "Voltage but no current (virtual electricity)" ghost troubleshooting method

Phenomenon description: The inverter does not generate electricity. Use a multimeter to measure the open circuit voltage at the PV port of about 400V, but after closing the DC switch, the input current at the inverter end is always 0A.

Actual root cause (RCA): This is a typical "virtual connection". It often occurs when the MC4 connector is not pressed tightly, the wire core is oxidized and broken, leaving only a single wire connected, or the bypass diode in the photovoltaic module junction box has a thermal breakdown and open circuit.

Troubleshooting standards: It is strictly prohibited to rely solely on a multimeter to measure the no-load voltage qualitatively! The MC4 connectors of the rooftop strings must be disconnected one by one and scanned with an infrared thermal imaging camera at the moment when the load is attempted. The connectors with abnormally high temperatures are virtual contacts. Simply cut away and redo the MC4 connector using professional crimping pliers.

10.2 “DC Arc & Isolation” fatal precautions

Phenomenon description: The inverter reports that the PV insulation resistance is too low (Isolation Fault). Forcibly closing the inverter may hear the hissing discharge sound from the roof.

Actual Root Cause (RCA): High incidence during the rainy season in the Philippines. Rats/pests chew the wire sheath, or the cable is damaged by long-term friction at the sharp edge of the color steel tile. Once high-voltage DC discharges to the ground, it is easy to pull out an arc with a high temperature of several thousand degrees and burn the roof.

排查标准:

Must use 1000V megohmmeter to measure. It is strictly prohibited to use an ordinary multimeter (the voltage of the multimeter is only 9V and cannot penetrate the water film to find leaks).

Carry out the "dichotomy" investigation: disconnect the string from the middle, conduct segmental shake measurements, and quickly approach the leaky photovoltaic panel or cable segment.

After repair, all DC cables passing through the iron roof must be compulsorily installed with flame-retardant corrugated conduits and silicone sealants.

10.3 “DC Voltage Reverse Current” Fire Prevention Verification

Phenomenon description: When multiple photovoltaic groups are connected in series and parallel to the same MPPT of the inverter, the total power generation is far lower than expected, and the surface temperature of a certain group of photovoltaic panels is abnormally high.

Actual root cause (RCA): The voltage difference occurs due to the different shadow occlusion conditions of the two strings or the inconsistent number of series blocks. The current of the high-voltage string does not enter the inverter, but flows back to the low-voltage string, serving as a load for continuous heating.

Troubleshooting criteria: Disconnect the parallel connection point and measure the open circuit voltage of each string. If the voltage difference is > 10V, direct parallel connection is strictly prohibited! It is mandatory to install a 15A/1000V photovoltaic anti-reverse charging diode (Blocking Diode) in the combiner box or re-plan the string wiring.

10.4 DC/AC Ratio Imbalance Assessment

Phenomenon description: The inverter cooling fan spins wildly, the chassis temperature is too high, and the over-temperature load reduction protection is often triggered at noon.

Actual verification: retrieve the rated input power from the inverter nameplate and check the total power of the actually installed photovoltaic modules. If the capacity ratio (total photovoltaic power ÷ inverter power) > 1.5 (depending on the specific model), it is determined to be excessive over-provisioning.

Solution: Issue a capacity expansion proposal to the customer. It is recommended to install an energy storage battery module to absorb excess peak energy, or to increase the parallel inverter shunt, otherwise the inverter extended warranty service will be refused.

Chapter 10: Investigation and rescue procedures for fatal hidden dangers on the roof photovoltaic side (PV)

This chapter is extracted from the practical experience of front-line senior operation and maintenance. In the Philippine market, due to extremely irregular construction by local installers, 90% of fatal failures reported by inverters are caused by peripheral cables on the roof. This chapter is CoreTect’s core guide to charging high Troubleshooting Work Fees.

10.1 Fake Voltage & Burned MC4

(Corresponding information: There is voltage but no current, and colleagues who can see the fault at a glance (scorched connectors))

• Phenomenon description: The inverter does not generate electricity. The multimeter measured a voltage of about 400V at the PV end, but when it was turned on, the current was always 0A.

• Old Cannon Root Cause (RCA): This is the classic “virtual electricity” trap for newbies. The root cause is usually that the internal metal pins of the MC4 plastic connector on the roof are not crimped tightly (virtually connected). When there is no load, the energy reaches the voltage. Once the inverter draws a large current, a high temperature of several hundred degrees will be generated at the joint instantly, directly burning the internal copper core or melting the plastic shell (such as the burnt joint shown by the veteran).

• 抢救 SOP:

1. It is strictly prohibited to only measure voltage! A thermal imaging camera must be carried on the roof.

2. Scan all MC4 connectors while the inverter attempts to pull load. The red and hot connector is the culprit!

3. Cut off the burned connector and use professional photovoltaic crimping pliers to re-press the new MC4.

4. Commercial charges: Replacement of one joint costs 10 pesos, and a “roof depth demining fee” starts at 3,000 pesos!

10.2 DC Arc & Isolation Fault

(Corresponding information: insulation resistance alarm shutdown, DC arc fire)

• Phenomenon description: After the rainy season or strong winds, the inverter frequently crashes and reports Isolation Fault (low insulation resistance). There is even a burning smell on the roof and fire in the wires.

• Old root causes (RCA): Philippine rats chew the wire sheath, or photovoltaic cables are rubbed and broken at the sharp corners of the color steel tiles for a long time. Once the 600V DC high voltage comes into contact with the water film or metal roof, it will pull out an extremely terrifying "DC Arc"** and instantly ignite the surrounding weeds or houses!

• 抢救 SOP:

1. The red line of death: Once arcing occurs, it is strictly prohibited to splash water directly! The DC switch at the bottom of the inverter must be pulled down immediately!

2. Megger tracking: After the inverter is powered off, unplug the PV wire. Use a 1000V megger to measure the impedance of the positive and negative poles to ground. If it is < 1MΩ, go to the roof immediately, cut the cables in sections, and conduct shake measurements until you find the leakage point.

3. Commercial charges: Issue a "Fire Hazard Investigation Report" to persuade the customer to carry out the "Full Roof Cable Flame-Retardant Pipe Reconstruction Project", the quotation starts at 20,000 pesos! **

10.3 Over-temperature load reduction and unbalanced capacity ratio of the inverter (Over-Temp & Clipping)

(Corresponding information: Inverter over-temperature alarm, power generation continues to decrease, capacity ratio imbalance)

• Phenomenon description: When the sun is strongest at noon, the inverter alarms and the fan spins wildly, and the power generation not only does not increase but decreases.

• 老炮根因 (RCA):

1. The installer’s greed: In order to make more money, the contractor installed 18kW photovoltaic panels (capacity ratio > 1.8) for the 10kW inverter. All the excess energy is stored in the inverter and turns into a high temperature of several hundred degrees!

2. Environmental strangulation: The computer room is airtight, and all the inverter inhales is hot air, which triggers the motherboard's "Thermal Derating" self-protection mechanism.

• 抢救 SOP:

1. Check the total power of the components actually installed on site and compare it with the inverter nameplate.

2. If the over-provisioning is serious, the excess strings must be removed, or the customer may be advised to purchase an additional CoreTect inverter for shunting.

3. It is mandatory to install a high-power industrial exhaust fan in the computer room and aim it at the inverter’s cooling fins to draw strong air.

10.4 Four “Yield Killers” with Low Power Generation

(Corresponding information: Why your photovoltaic power generation is lower than that of your neighbors and why the power generation does not meet the standard)

When a customer complains that the system does not save power, do not suspect that the machine is broken. Take the customer directly to the roof to verify these 4 points:

1. Severe shading: Even if only 10% of a board is covered by a tall tree growing next to it or a neighbor’s new second floor, the power generation of the entire string of boards will plummet by 50% due to the “barrel effect”! (Countermeasure: Prune branches, or install Optimizer).

2. Dust-heavy areas: As a veteran said, "3 megawatts a day can't be washed out." The Philippines has a long dry season, and the bird droppings and thick ash layer on the boards will seriously block sunlight. (Business conversion: Launch of "quarterly professional photovoltaic panel cleaning service", annual fee).

3. Micro-cracks: The contractor stepped on the photovoltaic panels during construction, causing the internal crystalline silicon to break. Invisible to the naked eye, the "heat black spots" must be scanned out with a thermal imaging camera or EL tester.

4. Grounding Issue: Such as veteran video (ground resistance detection). If the ground stake is not installed or the resistance value is > 4Ω, it is not only vulnerable to lightning strikes, but also interferes with the high-frequency leakage current detection of the inverter, causing inexplicable shutdowns.

第五 章

第 5 章:PCS (储能变流器) 运维标准

本章规定 CoreTect 授权工程师对混合逆变器(PCS)进行日常巡检与预防性维护的标准化操作。⚠️ 注:本章仅涉及O&M(运维)层面,严禁工程师在现场进行主板级焊接维修。

5.1 PCS 安全隔离与验电规范 (LOTO)

在进行任何打开逆变器接线舱盖的操作前,必须严格遵守以下放电红线:

1. 断开交直流:依次断开交流电网断路器、负载断路器、PV 隔离开关及电池直流总闸。

2. 强制静置电容放电:断电后,强制静置等待 ≥ 5 分钟(100kW 以上机型需等待 15 分钟),让内部 DC-Link 大容量电解电容完全放电。

3. 高压验电:穿戴绝缘手套,使用万用表直流 1000V 档测量 BAT+ 与 BAT-,确认内部残余电压 < 36V DC 后,方可进行触碰作业。

5.2 PCS 电气连接与扭矩维保

由于逆变器长期在大电流和热胀冷缩环境下运行,交直流端子极易松动引发电弧起火。

1.热成像巡检(带电执行):每季度满载运行时,使用红外热像仪扫描 GRID/LOAD 交流输出端子及 BAT/PV 直流端子。若端子温度 > 65℃,或相间温差 > 5℃,标记为异常。

2.扭矩复紧(断电执行):针对查出的异常发热点,使用绝缘扭矩扳手重新紧固(参考标准:M6螺栓 5N·m,M8螺栓 12N·m,M12螺栓 45N·m),并重新划定红/蓝防松线。

5.3 PCS 散热与防尘维保

逆变器的寿命由 IGBT 的散热决定。在菲律宾高灰尘环境下,必须严格执行:

1.外置防尘网:每月巡检时,拆卸逆变器底部/侧面进风口防尘网,使用高压气枪(压力 < 0.3MPa)或清水冲洗并彻底晾干后装回。

2.散热风扇测试:通过屏幕诊断菜单强制启动风扇 100% 运转。若有轴承异响或转速告警,须记录并在下次巡检时实施风扇模块整体替换。

第 6 章:通讯与云平台运维标准

通讯链路是 CoreTect 提供 SaaS 服务及远程风控的命脉,必须保证 99.9% 的在线率。

6.1 物理链路层检查 (Physical Layer)

- 通讯线缆抗干扰:检查 RS485 和 CAN 通讯线是否使用双绞屏蔽线 (Shielded Twisted

Pair)。屏蔽层必须在逆变器端单端接地。严禁通讯线与交直流粗电缆在同一线槽内平行捆扎,必须保持 15cm

以上间距。

- 终端匹配电阻:若总线距离超过 50 米或现场存在严重乱码丢包,检查总线最末端设备的 A/B 引脚是否已并联 120Ω 终端电阻。

6.2 边缘智能网关 (4G DTU/ESP32) 运维

- 信号盲区测试:查看网关后台 RSSI 值。标准要求 RSSI >

-85dBm。若信号低于此值,严禁将天线锁在铁皮机柜内,必须使用延长线将吸盘天线移至室外无遮挡处。

- 看门狗与重连测试 (Watchdog Test):现场拔掉 4G 网关天线模拟断网,观察网关能否在 300

秒内触发硬件看门狗,自动断电重启并重新拨号连上

CoreTect ThingsBoard 云平台。

第 7 章:故障响应与 RCA 调查

7.1 服务级别协议 (SLA) 响应矩阵

基于客户订阅的 SaaS 级别,CoreTect 运维中心严格执行以下响应时效:

- 🚨 P1 级(重大故障):PCS 宕机 / 消防告警 / 电池通讯离线。

- 响应机制:云端 30 分钟内 介入并下发安全断电指令;大马尼拉地区工程师 4 小时内 携备件到达现场。

- ⚠️ P2 级(一般故障):电芯压差 > 100mV / 电池环境高温预警。

- 响应机制:云端 4 小时内 响应并尝试下发远程均衡指令;若未恢复,24 小时内 现场排查。

- ℹ️ P3 级(轻微异常):4G 信号弱导致偶发数据延迟。

- 响应机制:24 小时内 登记入库,并于下次例行巡检时解决。

7.2 重大事故 RCA (根因分析) 与定责调查

发生 P1 级设备炸毁或客户索赔时,工程师必须在 48 小时内出具 8D 标准的 RCA 报告,明确责任归属(甩锅防线):

1. 违规负载取证:现场核查配电箱。若发现客户私接深井水泵等超大感性负载,拍照取证,定性为【反向电动势击穿 IGBT】,属客户人为违规,拒绝质保。

2. 恶劣环境取证:若发现屋顶漏水滴入机柜、或防拆保修贴纸 (Warranty Seal) 被撕毁,立即封机拍照。

3. 黑匣子日志提取:使用电脑连接 BMS/PCS,导出崩溃前 5 分钟底层日志,分析是否存在电网超高压浪涌 (Grid

Surge)。若系电网雷击,属不可抗力。

第 8 章:菲律宾现场运维规范 (PH Localized Standards)

针对菲律宾热带海岛气候及欠发达电网环境,制定特种运维规范。

8.1 极端防潮与盐雾对抗 (Anti-Corrosion Protocol)

- 接点密封:菲律宾高湿高盐,易导致电气端子产生绿色铜锈或电化学腐蚀。巡检时必须用电子清洁剂清理氧化层,拧紧后涂抹工业导电膏,并喷涂聚氨酯三防漆

(Conformal Coating) 彻底隔绝湿气。

- 防凝露管理:雨季巡检必须核查机柜内底部防凝露加热板是否正常工作,防止水汽冷结导致高压放电。

8.2 防虫鼠害灾难排查 (Pest Control)

- 壁虎 (Tuko)、老鼠、红蚂蚁是导致主板短路的菲律宾第一杀手。

- 强制动作:每次开柜必须清理底部杂物。机柜内外电缆进出孔必须使用防火泥 (Firestop Putty)

严密封堵;电气舱角落需定期投放工业驱虫/驱鼠药锭。

8.3 台风与内涝应急预案 (Typhoon Emergency SOP)

- 台风前 48 小时 (Pre-Typhoon):云端下发强制充电指令,提高电池 SOC 下限至 90% 备战。

- 内涝抢险 (Flood):若水位预警淹没机柜底部 10cm,远程/现场强制切断直流总闸,拔除 4G 网关电源。

- 水退恢复红线:严禁客户自行合闸!必须由工程师上门清理烘干,并使用 1000V 兆欧表测量交直流绝缘阻抗 > 2MΩ 后方可重新上电。

第 9 章:客户服务与资产管理

本章确立 CoreTect 将“低频维修”转化为“高频增值服务”的商业落地机制。

9.1 SOH 寿命追踪与资产健康评分 (Health Score)

- 云端系统融合 SOC、SOH、最大压差、历史过温次数等底层数据,利用算法自动生成百分制“健康评分”。

- 月度体检报告 (Monthly Health Report):系统每月首日自动生成 PDF 报告发送给客户。

- 商业转化:对于评分低于 80 分的亚健康资产,客服主动发送预警,并附带《CoreTect 深度均衡与延寿保养报价单》,实现主动营销。

9.2 白标系统 (White-Label) 与代理商管理

- 针对大型安装商(Installer),CoreTect 提供云端 ThingsBoard 租户级权限 (Tenant Admin)。

- 品牌赋能:在系统界面为其替换专属 Logo 与域名,赋能代理商业务。

- 终极风控 (Kill-Switch):CoreTect 亚太总部保留底层网关的最终控制权。若代理商发生恶意拖欠 SaaS

订阅费,总部有权在云端一键切断通讯甚至下发断电指令。

9.3 备件仓储与呆滞料流转 (Spare Parts Management)

- 安全库存底线 (Min-Max Inventory):Marikina 实验室需保持核心耗材(如 4G

网关、直流空开、保险丝管、备用电芯)处于安全库存水位线以上。

- 交旧领新原则 (One-in, One-out):工程师申领新主板/网关去现场抢修,返回时必须交回烧毁的旧件录入黑匣子系统核销,严防备件私自流失或倒卖。

第 10 章:屋顶光伏侧 (PV) 疑难杂症与实战排雷指南

注:据 CoreTect 大数据统计,菲律宾现场 70% 的逆变器报错,根因均在屋顶光伏阵列(外围)。本章结合一线实战经验,专门处理 PV 侧高频死局。

10.1 “有电压无电流 (虚电)” 幽灵排障法

现象描述:逆变器不发电。使用万用表测量 PV 端口有 400V 左右开路电压,但闭合直流开关后,逆变器端输入电流始终为 0A。

实战根因 (RCA):此为典型“虚接”。多发于 MC4 连接器压接不紧、线芯氧化断裂仅剩单丝相连、或光伏组件接线盒内旁路二极管热击穿开路。

排查标准:严禁仅依靠万用表测空载电压定性!必须逐个断开屋顶组串的 MC4 接头,使用红外热像仪在尝试拉载瞬间扫描,温度异常飙高的接头即为虚接点。直接剪除并使用专业压线钳重做 MC4 接头。

10.2 “直流电弧与漏电 (DC Arc & Isolation)” 致命防范

现象描述:逆变器报 PV 绝缘阻抗过低 (Isolation Fault),强行合闸可能听见屋顶滋嘶放电声。

实战根因 (RCA):菲律宾雨季高发。老鼠/害虫啃咬线皮,或线缆在彩钢瓦边缘锐角处长期摩擦破损。高压直流一旦对地放电,极易拉出几千度高温电弧烧毁屋顶。

排查标准:

必须使用 1000V 兆欧表摇测。严禁使用普通万用表(万用表电压仅 9V 无法击穿水膜发现漏点)。

执行“二分法”排查:将组串从中间断开,分段摇测,快速逼近漏电光伏板或线缆段。

修复后,所有穿过铁皮屋顶的直流线缆必须强制加装阻燃波纹穿线管,并打硅酮密封胶。

10.3 “直流电压倒灌 (Reverse Current)” 防火核查

现象描述:多组光伏串并联接入逆变器同一 MPPT 时,总发电量远低于预期,且某一组光伏板表面温度异常偏高。

实战根因 (RCA):由于两组串的阴影遮挡情况不同,或串联块数不一致,导致出现压差。高压组串的电流未进入逆变器,而是倒灌回低压组串,将其作为负载持续加热。

排查标准:断开并联点,分别测量各组串的开路电压。若压差 > 10V,严禁直接并联!必须在汇流箱内强制加装 15A/1000V 光伏防反充二极管 (Blocking Diode),或重新规划组串接线。

10.4 容配比 (DC/AC Ratio) 失衡评估

现象描述:逆变器散热风扇狂转,机壳温度过高,午间常触发过温降载保护。

实战核查:调取逆变器铭牌额定输入功率,核对实际安装的光伏组件总功率。若容配比(光伏总功率 ÷ 逆变器功率)> 1.5(视具体机型而定),判定为过度超配。

处理方案:向客户出具扩容建议书。建议加装储能电池模块吸收多余峰值能量,或增加并联逆变器分流,否则拒绝提供逆变器延保服务。

第 10 章:屋顶光伏侧 (PV) 致命隐患排查与抢险规程

本章提炼自一线资深运维实战经验。在菲律宾市场,由于本地安装商施工极度不规范,逆变器报出的致命故障,90% 根因在于屋顶外围线缆。本章是 CoreTect 收取“高额排障工程费”的核心指南。

10.1 夺命“虚电”与 MC4 接头熔毁 (Fake Voltage & Burned MC4)

(对应情报:有电压无电流、一眼看出故障的同行(烧焦接头))

• 现象描述:逆变器不发电。万用表测 PV 端有 400V 左右电压,但一开机,电流始终为 0A。

• 老炮根因 (RCA):这是典型的新手陷阱“虚电”。根因通常是屋顶的 MC4 塑料接头内部金属插针压接不紧(虚接)。空载时能量到电压,一旦逆变器拉取大电流,接头处瞬间产生几百度高温,直接将内部铜芯烧断或融化塑料外壳(如老兵展示的烧焦接头)。

• 抢救 SOP:

1. 严禁只量电压!必须携带红外热像仪上屋顶。

2. 在逆变器尝试拉载时,扫描所有 MC4 接头。发红发烫的那个接头就是元凶!

3. 剪掉烧毁接头,使用专业光伏压线钳重新压制新的 MC4。

4. 商业收费:更换一个接头成本 10 比索,收取“屋顶深度排雷费” 3000 比索起!

10.2 直流拉弧起火与绝缘阻抗骤降 (DC Arc & Isolation Fault)

(对应情报:绝缘阻抗报警停机、直流拉弧起火)

• 现象描述:雨季或大风后,逆变器频繁死机,报 Isolation Fault (绝缘阻抗低),甚至屋顶闻到焦味、电线起火。

• 老炮根因 (RCA):菲律宾老鼠啃咬线皮,或光伏线缆在彩钢瓦锐角处长期摩擦破皮。600V 的直流高压一旦接触水膜或金属屋顶,会拉出极其恐怖的**“直流电弧(DC Arc)”**,瞬间点燃周围杂草或房屋!

• 抢救 SOP:

1. 绝命红线:一旦发生拉弧,严禁直接用水泼!必须第一时间拉下逆变器底部的直流总闸(DC Switch)!

2. 摇表寻踪:逆变器断电后,拔下 PV 线。使用 1000V 兆欧表摇测正负极对地阻抗。若 < 1MΩ,立刻上屋顶,分段剪断线缆摇测,直至找出破皮漏电点。

3. 商业收费:出具《火灾隐患排查报告》,说服客户进行**“全屋顶线缆阻燃穿管重构工程”,报价 2 万比索起!**

10.3 逆变器过温降载与容配比失衡 (Over-Temp & Clipping)

(对应情报:逆变器过温报警、发电量持续降低之容配比失衡)

• 现象描述:中午阳光最烈时,逆变器狂报警、风扇狂转,发电量不仅没增加反而下降。

• 老炮根因 (RCA):

1. 安装商的贪婪:包工头为了多赚钱,给 10kW 的逆变器硬配了 18kW 的光伏板(容配比 > 1.8)。多余的能量全憋在逆变器里变成了几百度的高温!

2. 环境扼杀:机房密不透风,逆变器吸入的全是热风,触发了主板的**“热降额(Thermal Derating)”**自我保护机制。

• 抢救 SOP:

1. 核查现场实际安装的组件总功率,比对逆变器铭牌。

2. 若超配严重,必须拆除多余组串,或建议客户增购一台 CoreTect 逆变器进行分流。

3. 强制要求在机房加装大功率工业排风扇,对准逆变器散热鳍片强抽风。

10.4 发电量低下的四大“隐形杀手” (Yield Killers)

(对应情报:你家光伏为啥比邻居发电量低、发电量不达标原因)

当客户抱怨系统不省电时,不要怀疑机器坏了,直接带客户上屋顶核查这 4 点:

1. 严重遮挡 (Shading):旁边长高的大树、邻居新建的二楼,哪怕只遮住了一块板子的 10% 面积,由于“木桶效应”,整串板子的发电量会暴跌 50%!(对策:修剪树枝,或加装优化器 Optimizer)。

2. 灰尘重灾区:如老兵所说“一天 3 兆瓦真洗不出来”。菲律宾旱季长,板子上的鸟粪、厚灰层会严重阻挡阳光。(商业转化:推出“季度光伏板专业清洗服务”,包年收费)。

3. 隐裂 (Micro-cracks):包工头施工时踩踏光伏板,导致内部晶硅断裂。肉眼看不见,必须用热像仪或 EL 测试仪扫出“发热黑斑”。

4. 接地不良 (Grounding Issue):如老兵视频(接地电阻检测)。未打接地桩或阻值 > 4Ω,不仅易受雷击,还会干扰逆变器的高频漏电流检测,导致莫名其妙的停机。